Wash. Admin. Code § 296-150T-0590

Current through Register Vol. 24-17, September 1, 2024
Section 296-150T-0590 - How do I obtain insignia for used factory-built structures?

We consider used factory-built housing and commercial structures as new structures for purposes of use as temporary worker housing and an insignia approval as temporary worker housing must be obtained. To obtain insignia, you must:

(1) Have the design plan approved by us (see WAC 296-150T-0300 through 296-150T-0480);
(2) Purchase insignia (see WAC 296-150T-0200 through 296-150T-0230); and
(3) Pass a unit inspection (see WAC 296-150T-0500 through 296-150T-0550) .

Note:

You will be required to open up as much of the construction of the unit as is necessary for inspection to show compliance with your approved design plan.

Wash. Admin. Code § 296-150T-0590

Statutory Authority: RCW 43.22.480. 99-12-079, § 296-150T-0590, filed 5/28/99, effective 6/28/99.