Current through Bulletin No. 2024-21, November 1, 2024
Section R649-9-10 - Construction and Inspection Requirements for Disposal Facilities1. Division personnel shall be afforded a reasonable opportunity for inspection of any proposed disposal facility during the construction and operation of the facility.2. The division shall be notified at least 72 hours prior to the installation of leak detection systems or liners.3. The division shall be notified after completion of facility construction so that a final inspection can be conducted to verify that the facility has been constructed in accordance with the approved application.4. Failure to meet the requirements and standards for construction and operation of a disposal facility shall be considered as noncompliance and will result in the imposition of corrective actions and compliance schedules or a cessation of operations order.Utah Admin. Code R649-9-10