Section 19-450.5 - Application Procedure to Obtain Permit
A. Preliminary Interagency Meeting. The Department may convene at any time a meeting of commenting agencies and the applicant to provide assistance to the applicant, to explain the statutory requirements and areas of agency concern, to provide a preliminary review of the proposal, or to otherwise expedite the administrative aspects of filing an application for a permit.
B. Proposed Activity Requiring Only State Construction in Navigable Waters Permits. Except for applications filed with federal agencies described below, applications for a state permit shall be made to the Department on forms provided by the Department containing, but not limited to:
1. the name and address of the applicant;
2. the location of the proposed activity, including the navigable stream where the construction or activity is contemplated. An appropriate map of the area should be included;
3. a brief description of the proposed activity, its purpose and intended use, including a drawing of the type of structures and method of construction including a drawing of the type of structures and method of construction including size specifications;
4. a plan and elevation drawing showing the general and specific site locations and character of all proposed activities including the size relationship of the proposed structures to the size of the impacted waterway and depth of water in the area and the distance of encroachment of the activity into the water. A handdrawn sketch showing the size and shape of the structure and a location map will be considered sufficient detail for docks, piers, boardwalks or bulkheads without fill and extending no more than fifty (50) feet from the shoreline;
5. evidence of ownership or the consent of the owners of the adjacent high land on which any part of the projected activity will be located;
6. certification that the applicant has or will publish a notice describing the application in a newspaper of general or local circulation in the county where the encroachment is sought one time. Proof of the publication shall be furnished promptly, and the notice by the applicant shall be in the substantially the following form:

PUBLIC NOTICE

(Applicant) has applied to the South Carolina Department of Health and Environmental Control for a Construction in Navigable Waters Permit to (brief description of work) for (public/private) use in (name and location of waterbody). Comments will be received by South Carolina Department of Health and Environmental Control at 2600 Bull St., Columbia, SC, 29201, ATTN: Division of Water Quality and Shellfish Sanitation, until (insert date -15 days from date of this notice).

7. When considered appropriate by the Department, additional information may be required.
C. The Department shall promptly issue a notice to affected state agencies and make such other notice as it deems appropriate no later than fifteen (15) days after receipt of all information necessary to process the application.
D. Activity Requiring Construction in Navigable Waters and Federal Permits
1. When the applicant must obtain authorization from Corps of Engineers or the Coast Guard pursuant to federal law, he is directed to make application to those agencies in the style and on the forms provided by them. By agreement the above applications to federal agencies may be jointly used by the federal agencies and the State and no separate application may be required for the State permit.
2. The federal permitting agency shall publish and provide to interested agencies, groups and persons a joint public notice or public notice letter containing the permit application and clearly stating the requirement of a State permit and if required, certification that the permitted activity does not contravene the Coastal Zone Management Plan. Note: The federal permitting agency may require a certificate of water quality or waiver thereof from the Department of Health and Environmental Control.
E. Upon receipt of the joint public notice the Department shall notify the applicant that a state permit may or may not be required, and if, on the face of the joint public notice or application therein, it appears to the Department that insufficient or inaccurate information is presented, the Department shall notify the applicant and request such additional or corrected information as may be necessary, and that in addition to the joint public notice or public notice letter provided by government agencies, the applicant must publish a notice describing the application in a newspaper of general or local circulation in the county where the encroachment is sought one time. Proof of the publication shall be furnished promptly, and the notice by the applicant shall be in the substantially the following form:

PUBLIC NOTICE

(Applicant) has applied to the South Carolina Department of Health and Environmental Control for a Construction in Navigable Waters Permit to (brief description of work) for (public/private) use in (name and location of waterbody). Comments will be received by South Carolina Department of Health and Environmental Control at 2600 Bull St., Columbia, SC, 29201, ATTN: Division of Water Quality and Shellfish Sanitation, until (insert date - 15 days from date of this notice).

F. Processing of the State permit application by the Department shall commence upon receipt of the joint public notice and shall be processed concurrently but separately from any federal authorization.

S.C. Code Regs. § 19-450.5

Added by State Register Volume 10, Issue No. 6, eff June 27, 1986. Amended by State Register Volume 19, Issue No. 6, eff June 23, 1995.