In selecting an appropriate project delivery method for each of the State's Infrastructure Facilities , the governmental body should consider the results achieved on similar projects in the past and the methods used. Consideration should be given to all authorized project delivery methods, the comparative advantages and disadvantages of each, and how these methods may be appropriately configured and applied to fulfill State requirements. Additional factors to consider include:
The head of the governmental body shall make a written determination that must be reviewed by the State Engineer. The determination shall describe the project delivery method (Section 11-35-3005 ), source selection method (Section 11-35-3015 and 11-35-1510 ), any additional procurement procedures (11-35-3023 and 11-35-3024(2)(c)), and types of performance security (Sections 11-35-3030 and 11-35-3037 ) selected and set forth the facts and considerations leading to those selections. This determination shall demonstrate either reliance on paragraph (3) above, or that the considerations identified in paragraphs (1) and (2) above, as well as the requirements and financing of the project, were all considered in making the selection. Any determination to use a project delivery method other than design-bid-build must explain why the use of design-bid-build is not practical or advantageous to the State. Any determination to use any of the additional procedures allowed by Section 11-35-3024(2)(c) must explain why the use of such procedures are in the best interests of the State. Any request to use the prequalification process in a design-bid-build procurement must be in writing and must set forth facts sufficient to support a finding that pre-qualification is appropriate and that the construction involved is unique in nature, over ten million dollars in value, or involves special circumstances.
The provisions of Regulation 19-445.2040 shall apply to implement the requirements of Code Section 11-35-3220(2), Advertisement of Project Description.
The Office of State Engineer will provide forms in the Manual for Planning and Execution of State Permanent Improvements Projects-Part II for use by governmental bodies in submitting a contract for approval pursuant to Section 11-35-3220(8) of the Code.
For the purpose of these Regulations and Code Section 11-35-3240, a manual of procedures to be followed by governmental bodies for planning and execution of state permanent improvement projects is prepared and furnished by the designated board office, and included in this regulation. Part II of this manual, covering the procurement of construction for the projects, will be the responsibility of the Office of the State Engineer.
In accordance with Section 11-35-3023, the State Engineer's Office shall develop procedures for a prequalification process and shall include it in the Manual for Planning and Execution of State Permanent Improvements-Part II. The provisions of Regulation 19-445.2132 shall apply to implement Section 11-35-3023.
The provisions of Regulation 19-445.2040 shall apply to implement the requirements of Section 11-35-3020(a), Invitation for Bids. The provisions of Regulation 19-445.2090(B) shall not apply to implement the requirements of Code Section 11-35-3020.
To assure the timely, faithful, and uninterrupted provision of operations and maintenance services procured separately, or as one element of design-build-operate-maintain or design-build-finance-operate-maintain services, the governmental body shall identify, in the solicitation, one or more of the other forms of security identified in Section 11-35-3037 that shall be furnished to the governmental body by the offerors (or bidders) in order to be considered to be responsive.
S.C. Code Regs. § 19-445.2145