Section 918-020-0440 - Inspection Requirements that May Be Waived
(1) Subject to OAR 918-020-0430 and OAR 918-020-0450, a building official may waive certain jurisdictional responsibilities to a master builder on a project by project basis for the following inspections:
(a) Drywall;
(b) Footings and setbacks;
(c) Foundation walls, concrete encased electrode;
(d) Insulation;
(e) Masonry fireplace pre-cover;
(f) Masonry rebar;
(g) Gutters, downspouts and foundation drains;
(h) Roof sheathing nailing;
(i) Suspended ceiling;
(j) Underfloor structural; and
(k) Wall sheathing nailing.
(2) A building official for a jurisdiction that has a master builder program shall conduct inspections of at least 10 percent of projects built under a master builder program.