Or. Admin. R. 860-031-0020

Current through Register Vol. 63, No. 8, August 1, 2024
Section 860-031-0020 - Responses Open to the Gas Pipeline Operator
(1) After receiving the citation, the gas pipeline operator may:
(a) Correct the violation within the time allotted in the inspection report and notify the Commission's gas pipeline safety section of the action taken; or
(b) Submit a written plan of action indicating the action to be taken to correct the probable violation, including a schedule and the date when the completion of corrective action is anticipated; or
(c) Request an informal conference with the Commission's gas pipeline safety section.
(2) If the plan of action is rejected, or if the operator selects the third option, an informal conference will be scheduled.

Or. Admin. R. 860-031-0020

PUC 18-1984, f. & ef. 9-4-84 (Order No. 84-685); PUC 1-1998, f. & cert. ef. 1-12-98; PUC 9-2001, f. & cert. ef. 3-21-01

Stat. Auth.: ORS 183, ORS 756 & ORS 757

Stats. Implemented: ORS 756.040 & ORS 757.039