Or. Admin. R. 860-028-0180

Current through Register Vol. 63, No. 8, August 1, 2024
Section 860-028-0180 - Removal of Occupant Pole Attachments
(1) If the pole occupant fails to meet the time limitations set out in OARs 860-028-0120, 860-028-0130, 860-028-0140, or 860-028-0150 by 180 or more days, then the pole owner may request an order from the Commission authorizing removal of the pole occupant's attachments. Nothing in this section precludes a party from pursuing other legal remedies.
(2) This rule does not apply to a pole occupant that is a government entity.

Or. Admin. R. 860-028-0180

PUC 15-2000, f. 8-23-00, cert. ef. 1-1-01; PUC 23-2001, f. & cert. ef. 10-11-01, Renumbered from 860-022-0180 & 860-034-0880; PUC 2-2007, f. & cert. ef. 4-16-07

Stat. Auth.: ORS 183, 756, 757 & 759

Stats. Implemented: ORS 756.040, 757.035, 757.270-290, 759.045 & 759.650-675