Or. Admin. R. 860-024-0012

Current through Register Vol. 63, No. 8, August 1, 2024
Section 860-024-0012 - Prioritization of Repairs by Operators of Electric Supply Facilities and Operators of Communication Facilities
(1) A violation of the Commission Safety Rules that poses an imminent danger to life or property must be repaired, disconnected, or isolated by the Operator immediately after discovery.
(2) Except as otherwise provided by this rule, the Operator must correct violations of Commission Safety Rules no later than two years after discovery.
(3) An Operator may elect to defer correction of violations of the Commission Safety Rules that pose little or no foreseeable risk of danger to life or property to correction during the next major work activity.
(a) In no event shall a deferral under this section extend for more than ten years after discovery.
(b) The Operator must develop a plan detailing how it will remedy each such violation.
(c) If more than one Operator is affected by the deferral, all affected operators must agree to the plan. If any affected operators do not agree to the plan, the correction of violation(s) may not be deferred.
(4) After December 31, 2027, the only allowable conditions for deferrals as set forth in section (3) are as follows: repairs that accommodate schedules for permitting issues, repairs impacted by planned public works projects, and/or repairs that cannot be performed within the two-year correction timeframe due to circumstances outside the Operator's reasonable control. Plans for correction for deferrals due to these conditions must be submitted to Commission Staff for review and tracking.

Or. Admin. R. 860-024-0012

PUC 9-2006, f. & cert. ef. 9-28-06; PUC 6-2011, f. & cert. ef. 9-14-11; PUC 6-2022, amend filed 09/22/2022, effective 9/22/2022

Statutory/Other Authority: ORS 183, ORS 756, ORS 757 & ORS 759

Statutes/Other Implemented: ORS 757.035