Or. Admin. R. 629-625-0440

Current through Register Vol. 63, No. 8, August 1, 2024
Section 629-625-0440 - Stabilization
(1) Operators shall stabilize exposed material which is potentially unstable or erodible by use of seeding, mulching, riprapping, leaving light slashing, pull-back, or other effective means.
(2) During wet periods operators shall construct roads in a manner which prevents sediment from entering waters of the state.
(3) Operators shall not incorporate slash, logs, or other large quantities of organic material into road fills.

Or. Admin. R. 629-625-0440

FB 9-1996, f. 12-2-96, cert. ef. 1-1-97; DOF 7-2022, amend filed 11/21/2022, effective 1/1/2024

Statutory/Other Authority: ORS 527.710