Or. Admin. R. 330-069-0030

Current through Register Vol. 63, No. 9, September 1, 2024
Section 330-069-0030 - Obligated Measures
(1) ODOE shall contract with an owner for projects that comply with OAR 330-069-0085. ODOE shall prepare and submit to each IOU a summary report for ECMs approved under such contract.
(2) When the owner and ODOE have signed a contract, the owner must complete the project no later than the date set by the contract, or its amendment in accordance with OAR 330-069-0060.
(3) When ODOE finds that the completed project complies with OAR 330-069-0085, ODOE shall request the funding IOU to pay the owner an amount not to exceed that set in 330-069-0025.

Or. Admin. R. 330-069-0030

DOE 5-1985, f. & ef. 6-17-85

Stat. Auth.: ORS 469

Stats. Implemented: ORS 469