Or. Admin. Code § 141-122-0040

Current through Register Vol. 63, No. 10, October 1, 2024
Section 141-122-0040 - Easement Application Requirements
(1) Except as provided by OAR 141-122-0010(4) (Purpose and Applicability) and 141-122-0100 (Easements Issued on Common School Forest Land), any person wanting to use state-owned land for any of the purposes described in OAR 141-122-0010(2) and (3) must:
(a) Apply to the Department for the easement using a form provided by the Department; and
(b) Submit a non-refundable application fee as provided in OAR 141-122-0040(3) payable to the Department to cover the administrative costs of processing the application and issuing the authorization. When applying for an easement for a structure or facility necessary for the use of water as described in OAR 141-122-0105, a person may submit to the Department a copy of their application to the Department of Water Resources for a right to use water in lieu of using the Department's easement application form.
(2) Unless otherwise exempt under the provisions of OAR 141-122-0010(4) (Purpose and Applicability), each individual use of, or development placed on state-owned land must be authorized by a separate easement specifically authorizing only that use or development.
(a) With regard to a conduit, regardless of the number of innerducts or fiber optic cables contained within the conduit, each cable or innerduct is considered an individual use subject to authorization by an easement.
(b) With regard to electric power transmission lines, one transmission line with one or more circuits will constitute an individual use subject to authorization by an easement. Additional parallel transmission lines owned by the same entity with one or more circuits may be included in the same individual use so long as such parallel lines are located within the designated boundaries of the easement.
(3) The application fee for all easements is as follows:
(a) Utility Easements $750
(b) All Other Trust Land Easements: $1,500.00
(c) Application fee for all structures or facilities necessary for the use of water on submerged land subject to an easement is $125.
(4) A single easement application form may be used to request:
(a) Multiple easements required for a single pipeline, cable, or similar use or development which cross one or more parcels of state-owned land
(b) An easement for all state, county or city-owned bridges within a single county, or
(c) An easement for one or more identical uses or developments which cross the same parcel of state-owned land or state-owned waterway, for example, two parallel pipelines.
(6) An easement application for a conduit must include a cross-sectional drawing that shows the proposed use and the remaining conduit space available for future use.
(7) A fully completed application must be submitted to the Department at least 90 calendar days prior to the proposed use or placement of a development subject to a term easement on state-owned land, unless otherwise allowed by the Director in writing
(8) A fully completed application must be submitted to the Department at least 120 calendar days prior to the proposed use or placement of a development that is eligible for a permanent easement on state-owned land, unless otherwise allowed by the Director in writing.
(9) Any person holding a valid easement (other than a permanent easement) granted by the Department prior to the adoption of these rules who wants to continue holding the authorized area following the expiration of the easement for a use subject to easement must:
(a) Apply to the Department for a new easement and pay the required application fee 180 calendar days prior to the expiration of the easement as provided in OAR 141-122-0040(1), unless otherwise allowed by the Director in writing; and
(b) Pay the compensatory payment required by OAR 141-122-0060 at such time that the Department has reviewed and approved the easement application request pursuant to OAR 141-122-0050(9) and (10).

Or. Admin. Code § 141-122-0040

DSL 6-2000, f. 8-11-00, cert. ef. 9-1-00; DSL 7-2002, f. 12-23-02, cert. ef. 1-1-03; DSL 4-2008, f. & cert. ef. 10-15-08; DSL 1-2019, amend filed 01/08/2019, effective 1/8/2019

Statutory/Other Authority: ORS 273.045

Statutes/Other Implemented: ORS 273.761, 274.040, 274.720, 376.620, 530.050, 530.490 & 758.010