N.D. Admin. Code 43-02-09-03

Current through Supplement No. 394, October, 2024
Section 43-02-09-03 - Notice of intention to begin a workover project

If an exemption from taxation is sought pursuant to subsection 4 of North Dakota Century Code section 57-51.1-03, a notice of intention to begin a workover project must be filed by the well operator with the commission prior to commencement of the project. The notice of intention must be sent to the following address:

North Dakota State Industrial Commission

Oil and Gas Division

600 East Boulevard

Bismarck, ND 58505-0840

The notice of intention must include, but is not limited to, the following:

1. A sundry notice (form 4) upon which it is indicated that it is a notice of intention to perform a workover project.
2. The sundry notice must contain a detailed description of the nature and scope of the workover project. The information provided must include a description of all replacement equipment to be installed that is known to the well operator at the time of filing, and whether such equipment is new or used.
3. The average daily production during the latest six calendar months of continuous production.

If required by the director, the operator of the well to be worked over shall make arrangements to determine the crude oil inventory stored on the well premises immediately before the commencement of the workover and submit all gauge tickets for the month.

Workover projects must be completed within one year after the initial notice of intention to perform a workover is filed. Thereafter such notice is null and void.

N.D. Admin Code 43-02-09-03

Effective May 1, 1990; amended effective May 1, 1994; July 1, 1996; July 1, 2002.

General Authority: NDCC 57-51.1-03

Law Implemented: NDCC 57-51.1-03