If an exemption from taxation is sought pursuant to subsection 4 of North Dakota Century Code section 57-51.1-03, a notice of intention to begin a workover project must be filed by the well operator with the commission prior to commencement of the project. The notice of intention must be sent to the following address:
North Dakota State Industrial Commission
Oil and Gas Division
600 East Boulevard
Bismarck, ND 58505-0840
The notice of intention must include, but is not limited to, the following:
If required by the director, the operator of the well to be worked over shall make arrangements to determine the crude oil inventory stored on the well premises immediately before the commencement of the workover and submit all gauge tickets for the month.
Workover projects must be completed within one year after the initial notice of intention to perform a workover is filed. Thereafter such notice is null and void.
N.D. Admin Code 43-02-09-03
General Authority: NDCC 57-51.1-03
Law Implemented: NDCC 57-51.1-03