Nev. Admin. Code § 502.477

Current through June 11, 2024
Section 502.477 - Permits: Renewal; fee
1. The Department may renew a permit if the holder of the permit:
(a) Submits an application to renew the permit and a completed form to calculate the assessment provided by the Department pursuant to NAC 502.475; and
(b) Is in substantial compliance with the conditions of the existing permit.
2. The application to renew and the completed form to calculate the assessment must:
(a) Be submitted to the Department at least 30 days before the expiration of the existing permit;
(b) Include the fee for the permit required by NRS 502.390 and NAC 502.475; and
(c) Include any new information required to update any information previously submitted to the Department.
3. If the Department fails to renew a permit on or before the date of expiration of the existing permit, the holder of the permit may continue to operate the facility pursuant to the terms and conditions of the existing permit until a new permit is issued by the Department.
4. An application for renewal of a permit must include a completed form to calculate the assessment specified in subsection 1 and any documentation to support the data included in the form, including, without limitation, any engineering plans for the facility.

Nev. Admin. Code § 502.477

Added to NAC by by R014-16A, eff. 9/9/2016
NRS 501.105 and 501.181, as amended by sections 1 and 1.2, respectively, of Assembly Bill No. 78, chapter 202, Statutes of Nevada 2015, at page 956, and NRS NRS 502.390