Section 445A.420 - Renewal of permit; operation of facility pending issuance of new permit
1. A permit may be renewed by the Department if the holder of the permit submits an application to renew the permit. The application must:
(a) Be filed at least 120 days before the expiration of the existing permit;
(b) Include the renewal fee required by NAC 445A.232;
(c) The name, location and mailing address of the facility, owner, operator and authorized agent;
(d) The legal structure of the applicant, including, without limitation, whether the applicant is a sole proprietorship, partnership or corporation;
(e) The name of the owner of the land or mining claim or claims on which the facility is located;
(f) Documentation that notice of the development has been provided to the local board of county commissioners;
(g) The rate at which the facility chemically processes ore in tons of ore per year; and
(h) Include any new information to update information previously submitted to the Department, including, without limitation, any information previously submitted to the Department pursuant to this section or NAC 445A.394, 445A.414 or 445A.427.
2. A permit for a facility which is inactive because of an unplanned closure may be renewed once if the holder of the permit demonstrates that the conditions under which the permit was issued will continue and the design life of the process components will not be exceeded.
3. If the Department has not issued a new permit as of the expiration of the existing permit, the holder of the permit may continue to operate the facility pursuant to the terms and conditions of the existing permit until a new permit is issued by the Department.

Nev. Admin. Code § 445A.420

Added to NAC by Environmental Comm'n, eff. 9-1-89-Substituted in revision for NAC 445.2434; A by R018-20A, eff. 8/26/2020
NRS 445A.425, 445A.465, 445A.495