234 Neb. Admin. Code, ch. 6, § 002

Current through June 17, 2024
Section 234-6-002 - Direct Supervision of Work

In order to exercise full professional knowledge of and control over work, a registered professional land surveyor in direct supervision of land surveying work must have ordinary and direct oversight and guidance of a subordinate performing land surveying work including client survey requirements at the time the work occurs, and the supervisor/registrant's acceptance of responsibility for the work.

002.01. Have and exercise the authority to review and to change, reject, or approve both the work in progress and the final work product, through a continuous process of examination, evaluation, communication, and direction throughout the development of the work.
002.02. Be personally aware of the project's scope, needs, parameters, limitations, and special requirements.
002.03. Be capable of answering Questions relevant to the land surveying decisions made as part of the services provided, in sufficient detail to demonstrate knowledge of and proficiency in the work.
002.04. Be reasonably satisfied with the product of the services rendered and accept full responsibility for the work.
002.05. Requires at a minimum that the supervisor and the subordinate are employed by the same entity/employer. The Examining Board has final authority regarding the determination of whether technical documents were actually prepared under the direct supervision of a registrant.

234 Neb. Admin. Code, ch. 6, § 002

Amended effective 9/28/2022