Rule 20-201-3-3.1 - Required Performance Metrics for MS Works Projects

The State Longitudinal Data System (SLDS) will be used to calculate performance. Performance metrics for projects will at a minimum include:

A. Projects Awarded
B. Jobs Created
C. Jobs Retained
D. Wages / Personal Income
E. Certificates or Credentials Awarded (geo-located)
F. Other Training Funds Leveraged
G. Training Enrollments
H. Training Completion
I. Entered Employment
J. Wages Earned

The Training Providers will be required to input data associated with each MS Works activity using appropriate mechanisms to incorporate that data into SLDS.

20 Miss. Code. R. 201-3-3.1

Miss. Code Ann. § 71-5-353
Adopted 9/9/2016
Amended 9/23/2022