Septic Tank Criteria | |
Number of Bedrooms | Minimum Septic Tank Capacity Below Outlet |
3 or less | 1,000 gallon |
4 | 1,250 gallons |
For each additional bedroom, add 250 gallons |
Maximum Loading Rates for Systems with Design Flow Less than 5,000 Gallons per Day | |
Percolation Rate in Minutes for 1-Inch Drop After Prewetting | Maximum Loading Rate (Gallons per Day per Square Foot) |
2 - 5 | 1.2 |
6 - 15 | 0.8 |
16 - 30 | 0.6 |
Maximum Loading Rates for On-Site Disposal by Sewage Disposal Systems with Design Flow Greater Than or Equal to 5,000 Gallons Per Day | |||
Percolation Rate in Minutes for 1-Inch Drop After Prewetting | Maximum Loading Rate (Gallons / Day/ft2) | Maximum Loading Rate for effluent with BODs and TSS 30 mg/l or less * (Gallons / Day/ ft2) | Maximum Loading Rate for MBR effluent** (Gallons / Day/ ft2) |
2-5 | 0.8 | 1.6 | 2.0 |
6-15 | 0.6 | 1.2 | 1.6 |
16-30 | 0.4 | 0.8 | 1.2 |
* An individual groundwater discharge permit is required and advanced pretreatment employed. ** MBR effluent is defined as BOD5 <3 mg/L, TSS <1 mg/L, and TN <3 mg/L. An individual groundwater discharge permit is required and advanced pretreatment employed. |
Where:
a = The absorptive area required for the desired use by reference to regulation .05M.
w = Width of trench in feet;
Where:
w = Width of trench in feet;
d = Depth of usable sidewall area on the basis of percolation tests, observation of the soil profile at various soil depths, and other hydrogeologic data as may be required by the Approving Authority; and
a = The absorptive area required for the desired use by reference to regulation .05M.
Md. Code Regs. 26.04.02.05
Regulations .05 adopted effective November 18, 1985 (12:23 Md. R. 2218)
Regulation .05 amended effective November 3, 1986 (13:22 Md. R. 2398)
Regulation .05O and Q amended effective April 27, 1992 (19:8 Md. R. 806)
Regulations .05 adopted effective 41:9 Md. R. 522, eff.5/12/2014 ; amended effective 46:7 Md. R. 371, eff. 4/8/2019