Md. Code Regs. 21.03.01.02

Current through Register Vol. 51, No. 21, October 18, 2024
Section 21.03.01.02 - Contracts Void for Noncompliance
A. Except as provided in Regulation .03 or elsewhere in this title, if a procurement violates this title, the procurement contract is void.
B. If a procurement contract is void under this regulation, the contractor shall be awarded compensation for actual expenses reasonably incurred under the contract, plus a reasonable profit if the contractor:
(1) Has acted in good faith;
(2) Did not directly contribute to a violation of this title; and
(3) Had no knowledge of the violation before the procurement contract was awarded.

Md. Code Regs. 21.03.01.02

Regulation .02A amended effective 41:8 Md. R. 473, eff.4/28/2014