Md. Code Regs. 20.58.02.06

Current through Register Vol. 51, No. 26, December 27, 2024
Section 20.58.02.06 - Review by the Chief Engineer

If an operator objects to the proposed compliance order or civil penalty and submits a written explanation, information, or other material in response to an NOPV, the chief engineer shall review the submission and determine whether to:

A. Negotiate further, modify, or withdraw the NOPV; or
B. File a complaint under Public Utilities Article, § 3-102, Annotated Code of Maryland.

Md. Code Regs. 20.58.02.06