La. Admin. Code tit. 70 § I-903

Current through Register Vol. 50, No. 9, September 20, 2024
Section I-903 - Causes for Debarment of Contractors
A. The causes for debarment are enumerated in R.S. 48:295.2(C).
B. In addition to the statutory causes for debarment, the department shall follow the following guidelines.
1. A history of failure to perform or history of unsatisfactory performance may include, but is not limited to the following:
a. during one calendar year, two or more formal demands by the department to the contractor that the surety for the contractor complete a job, or
b. determination of disqualification five or more times in a calendar year, or three times during each of two consecutive calendar years.

La. Admin. Code tit. 70, § I-903

Promulgated by the Department of Transportation and Development, Office of Highways/Engineering, LR. 30:1489 (July 2004).
AUTHORITY NOTE: Promulgated in accordance with R.S. 48:295 et seq.