Current through Register Vol. 50, No. 9, September 20, 2024
Section III-129 - Other ConditionsA. Insurance. Prior to the signing of the contract between owner and the designer, the designer shall furnish to the owner proof of coverage for the following. 1. Insurance. Professional liability insurance shall be required as per the owner's requirements on a project by project basis. Refer to Exhibit B of the contract for the extent of coverage required. Insurance will be required at the time of contract execution between the owner and the designer. Proof of coverage will be required at that time. No deductible shall be in excess of 5 percent of the amount of the policy.2. Comprehensive general liability with minimum limits of $500,000 per accident/occurrence.3. Comprehensive automobile liability insurance with minimum limits of $300,000 per accident/occurrence.4. The designer shall provide a certificate of insurance as proof of workmen's compensation coverage.B. Affidavit. The designer, on signing the contract, shall submit to the owner, on such form as the owner shall designate, a noncollusion affidavit.C. When the time schedule has been established by the owner and designer, a completion date shall be set up for delivery of 100 percent completed, coordinated and ready to bid construction documents to the owner. If the designer is delayed through no fault of his/her own, then the completion date shall be extended accordingly, provided the designer makes such request in writing before starting the subsequent phase and the owner approves such as justified. The designer shall continue to work during this process.D. Non-Binding Mediation 1. In an effort to resolve any conflicts that arise during or following the completion of the project, the owner and the designer agree that all disputes between them arising out of or relating to this agreement shall be submitted to non-binding mediation unless the parties mutually agree otherwise. If non-binding mediation is not successful, then arbitration is the only remedy available to all parties of the contract. Arbitration, mediation and/or any legal action resulting from this contract shall take place in East Baton Rouge Parish.2. The owner and designer further agree to include a similar mediation provision in all agreements with independent contractors and consultants retained for the project and to require all independent contractors and consultants to likewise include providing for mediation as the primary method for dispute resolution between the parties to those agreements.3. If this non-binding mediation fails to resolve any conflicts, then the following arbitration clause shall take effect. All claims, disputes and other matters arising from the contract shall, at the option of the owner, be decided by arbitration. To the extent possible, such arbitration proceedings shall be conducted in accordance with the construction industry association rules of the American Arbitration Association. Any such arbitration proceeding shall, at the option of the owner, be consolidated with or joined to other arbitration proceedings between the owner and other persons or entities under contract with the state for the construction, repair or alterations of the project in question.E. Fault. Time delays, cost overruns, design inadequacies or other problems with performance of the designer may result in the designer being held "at fault." The owner shall determine if the designer is to be held at fault as provided in R.S. 38:2313.B.(5).La. Admin. Code tit. 34, § III-129
Promulgated by the Office of the Governor, Division of Administration, Facility Planning and Control, LR 8:478 (September 1982), amended LR 11:855 (September 1985), LR 13:656 (November 1987), LR 31:1081 (May 2005), Amended by LR 461571 (11/1/2020).AUTHORITY NOTE: Promulgated in accordance with R.S. 39:1410.