Authority: IC 12-15-44.5-9
Affected: IC 12-15-44.5
Sec. 5.
Gateway to Work Phase-in Period Requirements | |
Gateway to Work Phase-in Period | Required Community Engagement Hours Per Week |
January 1, 2019 - June 30, 2019 | 0 |
July 1, 2019 - September 30, 2019 | 5 |
October 1, 2019 - December 31, 2019 | 10 |
January 1, 2020 - June 30, 2020 | 15 |
July 1, 2020, and beyond | 20 |
405 IAC 10-12-5