Authority: IC 13-14-8; IC 13-17-3-4; IC 13-17-3-11
Affected: IC 13-15; IC 13-17
Sec. 6.
This section concerns particulate matter control equipment operation and maintenance requirements. A continuous compliance plan shall provide that the following control equipment related information will be maintained at the source's property and will be available for inspection by department personnel:
(1) Startup, shutdown, and emergency shutdown procedures.(2) Sources shall notify the department fifteen (15) days in advance of startup of either new control equipment or control equipment to which major modifications have been made.(3) Manufacturer's recommended inspection procedures, preventive and corrective maintenance procedures, and safety devices and procedures, such as sensors, alarm systems, and bypass systems. If manufacturer's recommendations are not available, procedures shall be developed by the source.(4) Contents of the operator's training program and the frequency with which the training is held.(5) A list of spare parts available at the facility.(6) A list of control equipment safety devices, for example: (A) high temperature sensors and alarm systems;(B) exhaust gas stream bypass system; or(C) safety interlock system.(7) Monitoring and recording devices or instruments, or both, to monitor and record control equipment operating parameters specified in section 3(4) of this rule.Air Pollution Control Board; 326 IAC 6.8-8-6; filed Aug 10, 2005, 1:00 p.m.: 28 IR 3537