315 Ind. Admin. Code 1-3-5

Current through October 2, 2024
Section 315 IAC 1-3-5 - Request for extension of time for filing pleading, document, or motion

Authority: IC 4-21.5-2-1; IC 4-21.5-7-7

Affected: IC 4-21.5-3-34; IC 4-21.5-3-35

Sec. 5.

Unless prohibited by statute, the presiding ELJ may grant an extension of time for the filing of any pleading, document, or motion as follows:

(1) Upon timely motion of a party to the proceeding.
(2) After notice to all other parties unless the moving party can show good cause why serving notice is impracticable.
(3) After consideration of prejudice to other parties.

315 IAC 1-3-5

Office of Environmental Adjudication; 315 IAC 1-3-5; filed Jun 2, 1998, 3:47 p.m.: 21 IR 3735; readopted filed Aug 11, 2004, 12:04 p.m.: 28 IR 323; filed Sep 16, 2005, 1:40 p.m.: 29 IR 473; readopted filed May 18, 2010, 1:45 p.m.: 20100602-IR-315100174RFA
Readopted filed 4/25/2016, 2:08 p.m.: 20160518-IR-315160051RFA
Readopted filed 7/19/2022, 2:01 p.m.: 20220817-IR-315220160RFA