Rule 19-4351 - RELEASE OF INFORMATION
4351.1

After final selection has taken place under Section 4350 the CCO may release information identifying the highest rated architect-engineer firm with which a contract will be negotiated.

4351.2

If negotiations are terminated without awarding a contract to the highest rated firm, the CCO may release that information and state that negotiations will be undertaken with another named architect-engineer.

4351.3

Awards made for architect-engineer services shall be publicized in accordance with Section 4302.