D.C. Mun. Regs. tit. 19, r. 19-4327

Current through Register Vol. 71, No. 50, December 13, 2024
Rule 19-4327 - TIME AND MATERIALS CONTRACT
4327.1

The CCO shall use a time and materials contract only when it is not possible to estimate accurately the extent or duration of the work or the anticipated costs with any degree of confidence.

4327.2

A time and materials contract shall include direct labor hours at specified fixed hourly rates that include wages, overhead, general and administrative expenses, profit and materials required at cost.

4327.3

The CCO shall ensure supervision of contractor performance when a time and materials contract is used.

D.C. Mun. Regs. tit. 19, r. 19-4327

Final Rulemaking published at 55 DCR 493 (January 18, 2008)