D.C. Mun. Regs. tit. 12, r. 12-K903

Current through Register Vol. 71, No. 35, August 30, 2024
Rule 12-K903 - COMMISSIONING

Strike Chapter 9 of the International Green Construction Code in its entirety and insert new Chapter 9 in the Green Construction Code in its place to read as follows:

903.1

General. Where application is made for construction as described in this section, the registered design professional in responsible charge or approved agency shall perform commissioning during construction as required by Table 903.1 and by Administrative Bulletins. The approved agency shall be qualified and shall demonstrate competence, to the satisfaction of the code official, for the commissioning of the particular type of construction or operation in accordance with the qualification requirements set forth in Administrative Bulletins. The registered design professionalin responsiblecharge and engineers of record involved in the design of the project are permitted to act as the approved agency provided those personnel meet the qualification requirements set forth in the Green Building Program Manual to the satisfaction of the code official.

903.2

Preliminary commissioning report requirement. The approved agency shall keep records of the commissioning required by Table 903.1.

The approved agency shall furnish commissioning reports to the owner and the registereddesign professional in responsible charge and, upon request, to the code official. Reports shall indicate that work was or was not completed in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. Where discrepancies are not corrected, they shall be brought to the attention of the owner,code official and to the registered design professional in responsiblecharge prior to the completion of that phase of the work. Prior to the final inspection, a Preliminary Commissioning Report shall be provided to the owner and a copy shall be made available to the code official upon request.

903.3

Final commissioning report requirement. A Final Commissioning Report shall be provided to the owner within 180 days after the date of issuance of the first certificate of occupancy for occupiable space in a story above grade plane, and a copy shall be made available to the code official upon request.

TABLE 903.1

COMMISSIONING PLAN

CONSTRUCTION OR SYSTEM REQUIRING VERIFICATION

PREOCCUPANCY

METHOD

OCCURRENCE

Preoccupancy

SECTION/ REFERENCED STANDARD

Chapter 4: Site Development and Land Use

Landscape irrigation systems

X

Field-inspection

Installation

Section 614 of the Plumbing Code

Stormwater management system operation

None

Field-inspection

Installation

21 DCMR (Water and Sanitation), Chapter 5 (Water Quality and Pollution)

Site lighting

X

Testing and report

Installation

409

Chapter 6: Energy

Energy consumption, monitoring, targeting and reporting

a. Monitoring system

X

Inspection and verification

During construction and prior to occupancy

603

b. Calibration

X

Testing and review and evaluation or test reports

During commissioning

603

Mechanical systems completion

a. Air system balancing - provide the means for system balancing

X

Inspection and verification

During construction and prior to occupancy

611.1.2.1 and through reference to Energy Conservation Code

b. Hydronic system balancing - provide means for system balancing

X

Inspection and verification

During construction and prior to occupancy

611.1.2.2 and through reference to Energy Conservation Code

c. Mechanical system manuals - construction documents to require O&M manual

X

Verification of construction documents

Plan review

611.1.5.2

Mechanical systems

a. Commissioning required and noted in plans and specifications

X

Verification of construction documents

Plan review

611.1

b. Documentation of required commissioning outcomes

X

Verification with the building owner

Subsequent to completion of all commissioning activities

611.1

c. Preparation and availability of a commissioning plan

X

Verification with the RDP or commissioning agent

Between plan review and commissioning initiation

611.1.1

d. Balance HVAC systems (both air and hydronic)

X

HVAC system installer/contractor or commissioning agent

After installation of HVAC systems and prior to occupancy

611.1.2

e. Functional performance testing of HVAC equipment

X

HVAC system installer/contractor or commissioning agent

After installation of HVAC systems and prior to occupancy

611.1.3

f. Functional performance testing of HVAC controls and control systems

X

HVAC system installer/contractor or commissioning agent

After installation of HVAC systems and prior to occupancy

611.1.3.2

g. Preparation of preliminary commissioning report

None

HVAC system installer/contractor or commissioning agent

None

611.1.4

h. Acceptance of HVAC systems and equipment/system verification report

None

Building owner

None

611.1.4.1

i. Preparation and distribution of final HVAC system completion. Documentation that construction documents require drawings, manuals, balancing reports and commissioning report be provided to the owner and that they have been provided

None

RDP, contractor or commissioning authority

None

611.1.5

Chapter 6: Lighting

Verification of lamp

X

Field inspection

Final inspection

611.3

Verification of ballast

X

Field inspection

Final inspection

611.3

Lighting Controls

a. Installation

X

Field inspection

Final inspection

611.3.2

b. Calibration

X

System installer/Contractor or commissioning agent

Final inspection

611.3

Chapter 7: Water Resource Conservation, Quality and Efficiency

Cooling tower performance

-

-

-

703.7.7

Metering

X

-

-

705.1.1

Chapter 8: Indoor Environmental Quality and Comfort

Air-handling system access

X

Field inspection and verification

During construction and prior to occupancy

802.2

Air-handling system filters

X

Field inspection and verification

During construction and prior to occupancy

802.3

For SI: 1 square foot = 0.0929 m2.

D.C. Mun. Regs. tit. 12, r. 12-K903

Final Rulemaking published at 61 DCR 3356 (March 28, 2014 Part 2); as corrected by Errata Notice published at 61 DCR 5246 (May 23, 2014)
The District of Columbia Green Construction Code (2013) , referred to as the "Green Construction Code," consists of the 2012 edition of the International Green Construction Code published by the International Code Council (ICC), as amended by the District of Columbia Green Construction Code Supplement (2013)(12 DCMR K). The International Green Construction Code is copyrighted by the International Code Council and therefore is not republished here. However, a copy of the text may be obtained at: http://publicecodes.cyberregs.com/icod/igcc/2012/index.htm?bu=IC-P-2012-000023&bu2=IC-P-2012-000019.
Authority: Section 10 of the Construction Codes Approval and Amendments Act of 1986 (Act), effective March 21, 1987 (D.C. Law 6-216; D.C. Official Code § 6-1409 (2012 Repl.)) and Mayor"s Order 2009-22, dated February 25, 2009, as amended.