5 Colo. Code Regs. § 1002-61.6

Current through Register Vol. 47, No. 20, October 25, 2024
Section 5 CCR 1002-61.6 - ISSUED PERMITS
(a) Following the close of public comment pursuant to section 61.5 , the Division may make such modifications in the terms and conditions of permits as may be appropriate, and shall transmit copies of the proposed permit to the Regional Administrator. Following the period for EPA's review of the permit specified in the Memorandum of Agreement between EPA and the Division, the Division shall issue or deny the permit.
(b) If a permit is issued, it shall be issued to the applicant who shall be responsible for compliance with conditions of the permit.
(c) The Division shall provide a notice of such issuance or denial to the applicant, to any person who participated in the public meeting and to appropriate persons on the mailing list established under sections 61.5 . Such notice shall briefly indicate any significant changes which have been made from terms and conditions set forth in the draft permit.
(d) Any permit issued shall become effective and final thirty (30) days after the permit is issued by the Division, or on such later date as specified by the Division, except as allowed in section 61.7 . Until the permit becomes effective, operation per the conditions of the issued permit is unauthorized.
(e) Except as provided in this subsection, if the Division has not issued or denied a permit within one hundred eighty (180) days after receipt of the permit application, unless this time limit has been waived or extended by the applicant, a temporary permit shall be issued or, in the case of a renewal permit, the previous permit shall be extended pursuant to section 61.8(3)(o) of these regulations.
(f) The deadlines established pursuant to paragraph (e) of this section shall be extended by:
(i) The number of days which an applicant takes to submit information requested by the Division pursuant to section 61.5 plus the fifteen (15) days provided for the Division to evaluate each additional information submittal; and
(ii) Thirty (30) days, for a public meeting which is held pursuant to section 61.5(3).

5 CCR 1002-61.6

38 CR 01, January 10, 2015, effective 1/30/2015
38 CR 11, June 10, 2015, effective 6/30/2015
39 CR 17, September 10, 2016, effective 12/31/2016
39 CR 21, November 10, 2016, effective 12/31/2016
40 CR 07, April 10, 2017, effective 4/30/2017
41 CR 23, December 10, 2018, effective 12/30/2018
43 CR 10, May 25, 2020, effective 6/14/2020