48 C.F.R. § 42.1302

Current through November 30, 2024
Section 42.1302 - Suspension of work

A suspension of work under a construction or architect-engineer contract may be ordered by the contracting officer for a reasonable period of time. If the suspension is unreasonable, the contractor may submit a written claim for increases in the cost of performance, excluding profit.

48 C.F.R. §42.1302