After July 18, 1997, the RWQCB shall require construction for all liner systems and final cover systems to be carried out in accordance with a CQA plan certified by an appropriately registered professional to satisfy the requirements of § 20324. If the RWQCB finds that any construction of the liner system or final cover system was undertaken in the absence of a CQA plan that satisfies the requirements of § 20324, the RWQCB shall require the discharger to undertake any corrective construction needed to achieve such compliance.
Cal. Code Regs. Tit. 27, § 20323
Note: Authority cited: Section 1058, Water Code. Reference: Sections 13172 and 13360, Water Code; and Section 43103, Public Resources Code.