From Casetext: Smarter Legal Research

T.J.D. Constr. Co. v. City of N.Y

Appellate Division of the Supreme Court of New York, First Department
Jun 13, 2002
295 A.D.2d 180 (N.Y. App. Div. 2002)

Summary

concluding that "the poor planning and scheduling of which plaintiff complains `amounted to no more than inept administration' within the scope of the no-damages-for-delay clause"

Summary of this case from Travelers Casualty Surety Company v. Dasny

Opinion

1393

June 13, 2002.

Order, Supreme Court, New York County (Charles Ramos, J.), entered March 2, 2001, which, in an action for delay damages by a contractor against defendant City, granted defendant's motion for summary judgment dismissing the complaint, unanimously affirmed, without costs.

THOMAS DILLON, for plaintiff-appellant.

GRACE GOODMAN, for defendant-respondent.

Before: Williams, P.J., Andrias, Lerner, Rubin, Friedman, JJ.


Plaintiff's argument that the delay caused by defendant's testing and correction of equipment design defects was not contemplated, and that the contract's no-damages-for-delay clause therefore does not apply, is refuted by contract provisions that, as correctly construed by the IAS court, called for the work to be done in two stages and for successful testing between the stages, so that a portion of the plant would always be in operation (see, Phoenix Contr. Corp. v. New York City Health Hosps. Corp., 118 A.D.2d 477, lv denied 68 N.Y.2d 606). Nor is an issue of fact raised as to whether the complained of delay was caused by defendant's bad faith or gross negligence in planning the project and scheduling the work, or that the seven-month delay was so unreasonable as to connote defendant's abandonment of the contract (see, Corinno Civetta Constr. Corp. v. City of New York, 67 N.Y.2d 297, 309, 312-313). If anything, the delay connoted an active and good-faith attempt by defendant to rectify defects in the equipment used in the first stage of the upgrade that were first revealed by tests performed in the middle of the contract. Even if defendant should have anticipated such unsatisfactory test results by reason of information it had prior to the contract, and failed to take adequate account thereof, at worst the poor planning and scheduling of which plaintiff complains "amounted to no more than inept administration" within the scope of the no-damages-for-delay clause (S.N. Tannor, Inc. v. A.F.C. Enters., 276 A.D.2d 363).

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.


Summaries of

T.J.D. Constr. Co. v. City of N.Y

Appellate Division of the Supreme Court of New York, First Department
Jun 13, 2002
295 A.D.2d 180 (N.Y. App. Div. 2002)

concluding that "the poor planning and scheduling of which plaintiff complains `amounted to no more than inept administration' within the scope of the no-damages-for-delay clause"

Summary of this case from Travelers Casualty Surety Company v. Dasny

affirming summary judgment for owner who failed to repair defective machinery despite prior bad test results, causing seven month delay

Summary of this case from Mafco Electrical Contractors, Inc. v. Turner Constr. Co.
Case details for

T.J.D. Constr. Co. v. City of N.Y

Case Details

Full title:T.J.D. CONSTRUCTION CO., INC., PLAINTIFF-APPELLANT, v. THE CITY OF NEW…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Jun 13, 2002

Citations

295 A.D.2d 180 (N.Y. App. Div. 2002)
743 N.Y.S.2d 111

Citing Cases

Eaton Elec. v. Dormitory Auth. of State of York

DASNY does not offer any evidence to refute Eaton's assertions regarding the causes of these delays, but,…

Travelers Casualty Surety Company v. Dasny

See Premier, 2008 WL 2676800, at *12; Gottlieb Contracting, Inc. v. City of N.Y., 446 N.Y.S.2d 311, 312 (App.…