From Casetext: Smarter Legal Research

PBJ Development Co. v. Holben

Supreme Court of Georgia
Nov 22, 1989
259 Ga. 594 (Ga. 1989)

Summary

In PBJ Dev. Co. v. Holben, 259 Ga. 594 (3) (385 S.E.2d 658) (1989), this court utilized a remedy it found to be a more efficient use of judicial resources: it first concluded that the evidence was sufficient to find the appellant in contempt beyond a reasonable doubt, then remanded the case to the trial court to either indicate that it had already used the correct standard, in which case the judgment was affirmed, or to apply the correct standard.

Summary of this case from Mathis v. Corrugated Gear

Opinion

46872.

DECIDED NOVEMBER 22, 1989.

Equity. Fulton Superior Court. Before Judge Jenrette.

Weekes Candler, Mark G. Burnette, for appellants.

Decker Hallman, Richard P. Decker, Marlene J. Griffith, R. Patrick White, for appellees.


This appeal stems from an order finding the appellants in criminal contempt of an interlocutory injunction that directed the appellants to take certain erosion-control steps to prevent the discharge of silt and mud from their construction site onto the appellees' residential property. On appeal the appellants raise three issues. We find no merit to two of the appellants' contentions, but find it necessary to affirm on condition with regard to the third argument.

1. The appellants complain of the lack of specificity concerning the trial court's findings of fact and conclusions of law. This argument has no merit, however, because findings of fact and conclusions of law are not even necessary in contempt cases. Hopkins v. Hopkins, 244 Ga. 66, 67-68 (2) ( 257 S.E.2d 900) (1979).

2. The appellants next argue that the evidence is insufficient to support the court's finding of criminal contempt. However, viewing the evidence in the light most favorable to the appellees, we conclude that any rational trier of fact could have found the appellants in contempt beyond a reasonable doubt. See In re Irvin, 254 Ga. 251, 256 (2) ( 328 S.E.2d 215) (1985).

3. The appellants' final argument is that the trial court erred in failing to apply the beyond-a-reasonable-doubt standard that is now applicable to criminal-contempt cases. See In re Crane, 253 Ga. 667, 669-670 (2) ( 324 S.E.2d 443) (1985). The record does not indicate that the trial court applied the correct standard, but we conclude that the proper remedy is to affirm the finding of contempt on the condition that the trial court state whether it applied the correct standard. See Lee v. Precision Balancing c., Inc., 134 Ga. App. 762, 764 ( 216 S.E.2d 640) (1975); Berry v. State, 254 Ga. 101, 104 (1) ( 326 S.E.2d 748) (1985). If the court states that it did so, the appellants are entitled to no further appeal.

Compare Smith v. Orkin Exterminating Co., 258 Ga. 705 ( 373 S.E.2d 740) (1988), and Life for God's Stray Animals v. New North c., 256 Ga. 338 (2) ( 349 S.E.2d 184) (1986). In those cases we vacated the judgments of contempt and remanded to the trial courts for them to apply the beyond-a-reasonable-doubt standard. The remedy we use in the present case is a more efficient use of judicial resources.

If the court states that it did not apply the correct standard, then the trial court is to proceed to apply the correct standard. If the trial court then concludes the evidence is sufficient under the correct standard, the appellants are entitled to no further appeal. If the trial court concludes the evidence does not meet the beyond-a-reasonable-doubt standard, the appellees can appeal that judgment if they so desire.

Judgment affirmed on condition. All the Justice concur.

DECIDED NOVEMBER 22, 1989.


Summaries of

PBJ Development Co. v. Holben

Supreme Court of Georgia
Nov 22, 1989
259 Ga. 594 (Ga. 1989)

In PBJ Dev. Co. v. Holben, 259 Ga. 594 (3) (385 S.E.2d 658) (1989), this court utilized a remedy it found to be a more efficient use of judicial resources: it first concluded that the evidence was sufficient to find the appellant in contempt beyond a reasonable doubt, then remanded the case to the trial court to either indicate that it had already used the correct standard, in which case the judgment was affirmed, or to apply the correct standard.

Summary of this case from Mathis v. Corrugated Gear
Case details for

PBJ Development Co. v. Holben

Case Details

Full title:PBJ DEVELOPMENT COMPANY et al. v. HOLBEN et al

Court:Supreme Court of Georgia

Date published: Nov 22, 1989

Citations

259 Ga. 594 (Ga. 1989)
385 S.E.2d 658

Citing Cases

McKenna v. Gray

The trial court was not required to, and did not, make findings of fact. See PBJ Dev. Co. v. Holben, 259 Ga.…

Mathis v. Corrugated Gear

Life for God's StrayAnimals v. New North c., 256 Ga. 338 (2) ( 349 S.E.2d 184) (1986). In PBJ Dev. Co. v.…