Morris v. North. Co. Han. T. Bd. of S

Commonwealth Court of Pennsylvania
Dec 29, 1978
395 A.2d 697 (Pa. Cmmw. Ct. 1978)

Summary

holding that the filing of serial, inconsistent plans created confusion, and upholding a common pleas court's decision that Section 508's 90-day deemed approval period did not apply

Summary of this case from Philomeno Salamone v. Upper Merion

Opinion

Argued September 28, 1978

December 29, 1978.

Zoning — Subdivision plan — Delay in decision — Pennsylvania Municipalities Planning Code, Act 1968, July 31, P.L. 805 — Inconsistent plans — Legislative purpose.

1. Provisions of the Pennsylvania Municipalities Planning Code, Act 1968, July 31, P.L. 805, requiring action by a governing body upon a proposed subdivision plan within ninety days, are inapplicable where the applicant has submitted two inconsistent plans and has continued to seek approval of the first plan after filing the second plan which was irreconcilable with the first, demonstrating an intention that the second filing not invalidate the first, and the plans will not be deemed approved when no decision is rendered by the governing body within ninety days. [470-1]

2. Provisions of the Pennsylvania Municipalities Planning Code, Act 1968, July 31, P.L. 805, establishing that plans will be deemed approved when the governing body renders no decision upon the submitted plan within ninety days, were intended to remedy indecision, protracted deliberations and deliberate or negligent inaction by governing bodies, and such provisions will not be applied when the protracted proceedings were occasioned by actions of the party seeking plan approval. [471-2]

Argued September 28, 1978, before Judges MENCER, BLATT and CRAIG, sitting as a panel of three.

Appeal, No. 1380 C.D. 1977, from the Order of the Court of Common Pleas of Northampton County in case of Francis P. Morris v. The Northampton County Hanover Township Board of Supervisors and The Northampton County Hanover Township Planning Commission, No. 316 May Term, 1976.

Petition for review in mandamus in the Court of Common Pleas of Northampton County to compel approval of subdivision plan. Motion for summary judgment filed and denied. Evidence submitted. Petition denied and dismissed. GRIFO, J. Petitioner appealed to the Commonwealth Court of Pennsylvania. Held: Affirmed.

B. Ryland Wiggs, for appellant.

John A. Zapf, II, with him T. E. Butterfield, Jr., and Butterfield, Joachim, Brodt and Houser, for appellees.


Francis P. Morris (appellant) appeals here from an order by the Court of Common Pleas of Northampton County which held that the failure of the Hanover Township Board of Supervisors to act within 90 days following the submission of two inconsistent subdivision plans for the same tract could not be deemed to be approval of either plan.

The appellant here submitted two sets of subdivision plans regarding development of the same tract of land to the Hanover Township Board of Supervisors. The first plan, submitted on February 13, 1976, was designated "Bridle Path Woods — Phase II" (first plan) and proposed the development of the property for an apartment complex. Because the property was zoned Residential (R-1), wherein apartment complexes were not permitted, the appellant also submitted a request to rezone the property to Residential (R-2). While this request was still pending, the appellant submitted another subdivision plan on February 27, 1976, which was designated "Hanover Knoll" (second plan), and which proposed development of the same property for forty single-family dwellings. Shortly after the second plan was submitted, the Township's engineering firm notified the appellant by letter that neither of his subdivision applications could be accepted by the Township for preliminary approval until the requirements of the Hanover Township Subdivision and Land Development Regulations had been met and that it would hold both applications and plans until the appellant advised what he wanted to do. Following a meeting of the Board of Supervisors, the engineering firm sent another letter to the appellant stating that in accordance with its earlier letter and in accordance with the decision of the Board of Supervisors at its meeting of March 9, 1976, it was returning both applications and plan copies.

This application was accompanied with a $500.00 check apparently to pay for the fee required with the submission of a subdivision plan.

Following a public hearing in April on the rezoning request, the Board of Supervisors voted not to rezone the appellant's property to R-2. The appellant then submitted to the Hanover Township Zoning Hearing Board (Board) a substantive challenge to the validity of the Township's zoning ordinance on the basis that only 2.5% of the township was zoned for multiple family dwellings and that the ordinance was exclusionary, and, therefore, constitutionally invalid. Following a hearing on the validity challenge to the zoning ordinance, which was held in May, the appellant agreed to an extension of time until July 29, 1976 for the Board's decision on the validity challenge. Prior to that date, however, on July 8, 1976, the appellant filed a suit in mandamus in the lower court contending that his second subdivision plan was deemed approved by virtue of the non-action of the Board of Supervisors within 90 days following its submission and that, under Section 508 of the Pennsylvania Municipalities Planning Code (MPC), it was deemed approved and he was, therefore, legally entitled to approval for that plan. On July 26, 1976, the appellant withdrew his validity challenge before the Board. On the same date he moved for summary judgment on his suit in mandamus, but the lower court dismissed this motion on the ground that the 90-day period of Section 508 of the MPC did not apply when two inconsistent plans for the same tract of land had been submitted. This appeal followed.

Act of July 31, 1968, P.L. 805, as amended, 53 P. S. § 10508.

The appellant maintains that he is legally entitled to approval of his second subdivision plan inasmuch as it was a proper and valid application and the Board of Supervisors failed to render a decision in regard to it within the time and manner required under Section 508 of the MPC, 53 P. S. § 10508. This Section provides in pertinent part as follows:

All applications for approval of a plat (other than those governed by Article VII), whether preliminary or final, shall be acted upon by the governing body or the planning agency within such time limits as may be fixed in the subdivision and land development ordinance but the governing body or the planning agency shall render its decision and communicate it to the applicant not later than ninety days after such application is filed.

(1) The decision of the governing body of the planning agency shall be in writing and shall be communicated to the applicant personally or mailed to him at his last known address not later than five days following the decision;

(2) When the application is not approved in terms as filed the decision shall specify the defects found in the application and describe the requirements which have not been met and shall, in each case, cite to the provisions of the statute or ordinance relied upon;

(3) Failure of the governing body or agency to render a decision and communicate it to the applicant within the time and in the manner required herein shall be deemed an approval of the application in terms as presented unless the applicant has agreed in writing to an extension of time or change in the prescribed manner of presentation of communication of the decision, in which case, failure to meet the extended time or change in manner of presentation of communication shall have like effect. . . . (Footnote omitted.) (Emphasis added.)

The threshold issue here, before we may reach the question as to whether or not the Board of Supervisors rendered its decision in a proper manner, is whether or not the 90-day provision applies when two inconsistent applications have been submitted. The appellant argues that the submission of the second plan constituted a substantial change in his earlier application and in effect voided the earlier plan submission. In support of this proposition he cites the case of DePaul Realty Company v. Borough of Quakertown, 15 Pa. Commw. 16, 324 A.2d 832 (1974) wherein this Court held that the submission of a second plan within the 90-day period voided the original plan and therefore extended the 90-day period for Board action to run from the filing date of the last revised plan. The second plan in that case was submitted as the result of the denial of a parking variance and was therefore submitted as a revision of the first plan in order to bring the application into conformity with the zoning ordinance, and the applicant thereafter sought only the approval of his second plan. The facts here, however, are wholly inapposite. Here the second plan submitted was not a revision of the first plan but a totally new and different plan which was obviously irreconcilable with the first. Furthermore, the appellant here continued to pursue his request for approval of the first plan in seeking rezoning of the property to Residential R-2 and by subsequently attacking the validity of the zoning ordinance as exclusionary of multiple-family dwellings. He could not, therefore, have intended the second plan to invalidate the first. See also Wiggs v. The Northampton County Hanover Township Board of Supervisors, 32 Pa. Commw. 631, 380 A.2d 505 (1977).

We believe that Section 508 of the MPC was enacted to remedy indecision and protracted deliberations on the part of local governing bodies and to eliminate deliberate or negligent inaction on the part of governing officials. Mid-County Manor, Inc. v. The Haverford Township Board of Commissioners, 22 Pa. Commw. 149, 348 A.2d 472 (1975); Township of Montgomery v. Market Center Realty Co., 12 Pa. Commw. 449, 317 A.2d 317 (1974); Gettys v. Dillsburg Borough Council, 7 Pa. Commw. 519, 300 A.2d 805 (1973). Such problems were not present here. Instead, the confusion and protracted proceedings here were occasioned by the actions of the appellant. We conclude, therefore, that the lower court was correct in dismissing the appellant's action in mandamus.

Having so decided, we need not reach the other issues raised here by the appellant.

ORDER

AND NOW, this 29th day of December, 1978, the order of the Court of Common Pleas of Northampton County in the above-captioned matter is hereby affirmed.


Summaries of

Morris v. North. Co. Han. T. Bd. of S

Commonwealth Court of Pennsylvania
Dec 29, 1978
395 A.2d 697 (Pa. Cmmw. Ct. 1978)

holding that the filing of serial, inconsistent plans created confusion, and upholding a common pleas court's decision that Section 508's 90-day deemed approval period did not apply

Summary of this case from Philomeno Salamone v. Upper Merion

holding that automatic approval provision did not apply to two inconsistent plans

Summary of this case from Bender v. Todd County
Case details for

Morris v. North. Co. Han. T. Bd. of S

Case Details

Full title:Francis P. Morris, Appellant v. The Northampton County Hanover Township…

Court:Commonwealth Court of Pennsylvania

Date published: Dec 29, 1978

Citations

395 A.2d 697 (Pa. Cmmw. Ct. 1978)
395 A.2d 697

Citing Cases

Philomeno Salamone v. Upper Merion

The court distinguished cases holding § 508 is inoperative where an applicant creates confusion by submitting…

Twp. of O'Hara et al. v. DiSilvio et ux

Individual interests are protected on the one hand in that MPC Section 508 "was enacted to remedy indecision…