From Casetext: Smarter Legal Research

In re APCO Liquidating Trust

United States Bankruptcy Court, D. Delaware
Jun 29, 2007
370 B.R. 625 (Bankr. D. Del. 2007)

Summary

disallowing as contingent future environmental costs

Summary of this case from Route 21 Associates of Belleville, Inc. v. MHC, Inc.

Opinion

No. 05-12355 (BLS).

June 29, 2007

John H. Knight, Jason M. Madron, Richards, Layton Finger, P.A., Wilmington, DE, Neal H. Weinfield, Matthew F. Prewitt, Greenberg, Traurig, LLP, Chicago, IL, for Debtors.

Jeffrey R. Waxman, Cozen O'Connor, Wilmington, DE, Mark S. Carder, Stinson Morrison Hecker LLP, Kansas City, MO, Joe Allen Lang, Chief Deputy City Attorney, Office of the City Attorney of Wichita, KS, for the City of Wichita.


MEMORANDUM OPINION

This Opinion constitutes the findings of facts and conclusions of law of the Court pursuant to Federal Rule of Bankruptcy Procedure 7052.


Before the Court is the Objection of the Liquidation Trustee to Claim Numbers 22 and 23 Filed by the City of Wichita, Kansas and Motion to Estimate, if Necessary (the "Objection") [Docket No. 233]. For the reasons stated below, the Court will sustain the Objection and disallow the claims pursuant to section 502(e)(1)(B) of the Bankruptcy Code (the "Code").

Claim Numbers 22 and 23 have been amended and superceded by Claim Number 26. This Memorandum Opinion, therefore, addresses Claim Number 26.

BACKGROUND

Almost twenty years prior to the filing of the above-captioned bankruptcy cases (the "Cases"), in 1986, the Kansas Department of Health and Environment ("KDHE") discovered hazardous contaminants in the groundwater at a 3,850 acre industrial area near the city center of Wichita, known as the Gilbert and Mosley site (the "G M Site"). The G M Site contains approximately 8,000 parcels of land, over 400 of which are owned by the City. One parcel within the G M Site, located at 1001 East Lincoln Street ("1001 E. Lincoln"), was owned by APCO Oil Corporation until 1971.

The facts and circumstances of the events surrounding the G M Site contamination recounted herein are substantially derived from the two Memorandum Opinions of the United States District Court for the District of Kansas resolving the City's lawsuit commenced in 1998 against twenty-seven alleged PRPs. The Memorandum Opinions — City of Wichita v. Aero Holdings, Inc., 177 F.Supp.2d 1153 (D.Kan. 2000), and City of Wichita v. Trustees of APCO Oil Corp. Liquidating Trust, 306 F.Supp.2d 1040 (D.Kan. 2003) — are attached as Exhibits A and B to the Supplemental Memorandum of Law in Support of the Liquidation Trustee's Objection to Claim by City of Wichita, Kansas [Docket No. 257] [hereinafter, Memorandum of Law].

APCO Oil Corporation was voluntarily dissolved by its shareholders on September 29, 1978. Shortly thereafter, APCO Liquidating Trust and the APCO Missing Stockholder Trust (the "Debtors") were formed pursuant to an order of the Court of Chancery of the State of Delaware.

Four years after the initial contamination discovery, KDHE completed an investigation into the potential and actual contamination at the G M Site pursuant to the Comprehensive Environmental Response, Comprehension and Liability Act ("CERCLA"), 42 U.S.C. §§ 9601- 9675 (2006). It located multiple sources of groundwater contamination and identified over 500 potentially responsible parties ("PRPs"). Shortly thereafter, on March 26, 1991, the City, which had not been identified as a PRP at that time, voluntarily entered into an agreement with KDHE, entitled "Settlement Agreement for Remedial Investigation and Feasibility Study, and for Certain Remedial Actions to be Determined Following Opportunity for Public Involvement" (the "City/KDHE Agreement"). See generally Memorandum of Law, Ex. C. Pursuant to the City/KDHE Agreement, the City agreed to perform a remedial investigation and feasibility study ("RI/FS") of the G M Site and, ultimately, to undertake the remedial activities identified in the RI/FS necessary to clean up the G M Site.

Seven years later, the City commenced a lawsuit pursuant to sections 9607(a) and 9613(f)(1) of CERCLA in the United States District Court for the District of Kansas seeking to recover its past and future response costs of investigating and cleaning the contamination from twenty-seven alleged PRPs, including the Debtors (the "Wichita Action"). After a lengthy trial, the Debtors were determined to be liable under section 9613(f)(1) for 1.72% of the City's past and future response costs of groundwater remediation for the entire G M Site and for 100% of the City's future source control costs to be incurred at 1001 E. Lincoln. See City of Wichita v. Trs. of APCO Oil Corp. Liquidating Trust, 306 F.Supp.2d 1040, 1046 (D.Kan. 2003) [hereinafter Wichita Judgment]. In 2004, the Debtors partially satisfied the Wichita Judgment, paying $467,273.10 for their 1.72% allocable share of the City's ground-water remediation costs for the entire G M Site.

On August 19, 2005, the Debtors commenced the Cases, seeking protection under chapter 11 of the Code. The City timely filed a proof of claim ("Claim No. 26") based upon the unsatisfied portion of the Wichita Judgment awarding the City 100% of the future source control costs to be incurred at 1001 E. Lincoln. Claim No. 26 estimates the City's future source control costs to be $1,325,527. See Objection, Ex. G. The United States Environmental Protection Agency also filed a proof of claim seeking reimbursement for $32,112.31 in past response costs incurred at the G M Site. See Memorandum of Law, Ex. C. KDHE has not filed a proof of claim against the Debtors based upon the contamination of the G M Site.

On December 12, 2006, John G. McMillian, the liquidation trustee (the "Liquidation Trustee"), filed the Objection, primarily urging this Court to disallow Claim No. 26 because (1) it is a contingent claim for contribution pursuant to section 502(e)(1)(B); and (2) the City cannot maintain a cause of action under CERCLA after the Supreme Court's decision in Cooper Industries, Inc. v. Aviall Services, Inc., 543 U.S. 157, 125 S.Ct. 577, 160 L.Ed.2d 548 (2004). On December 29, 2006, before the City responded to the Objection, the Liquidation Trustee filed a motion to transfer venue of the Objection to the United States District Court for the District of Kansas (the "Motion to Transfer Venue") [Docket No. 237].

A hearing on the Motion to Transfer Venue was held on January 18, 2007, at which time the Court decided to withhold ruling on the Motion to Transfer Venue pending disposition of the legal question of disallowance under section 502(e)(1)(B). To that end, the Court requested further briefing regarding section 502(e)(1)(B) and the Supreme Court's decision in Aviall.

On March 28, 2007, the City responded to the Objection, denying that Claim No. 26 was a contingent claim for contribution. According to the City, the claim arose from a final judgment rendering the Debtors directly liable to the City (and thus, not liable via principles of contribution) for the future source control costs to be incurred at 1001 E. Lincoln. Further, the City opposed any adverse application of Aviall to its claim, arguing that: (1) the principles of stare decisis and res judicata prevent the parties from re-litigating issues resolved by the Wichita Judgment; (2) the standards of Federal Rule of Civil Procedure 60(b)(5) do not apply to allow the Debtors to obtain relief from the Wichita Judgment; and finally, (3) even if the Court were to grant relief from the Wichita Judgment under Rule 60(b)(5) and apply Aviall, the City continues to have causes of action under both section 9613(f)(1) and 9607(a) of CERCLA.

A hearing on the Objection was held on May 5, 2007, at which time the Court took the matter under advisement.

This matter is ripe for decision.

JURISDICTION

The Court has jurisdiction over this matter pursuant to 28 U.S.C. §§ 1334 and 157(a) and (b)(1). Consideration of this matter constitutes a "core proceeding" under 28 U.S.C. § 157(b)(2)(A), (B), and (O).

DISCUSSION

I. Disallowance Pursuant to 11 U.S.C. § 502(e)(1)(B)

The Debtors contend that Claim No. 26 must be disallowed under section 502(e)(1)(B) because it is a contingent claim for contribution. Pursuant to section 502(e)(1)(B), "the court shall disallow any claim for reimbursement or contribution of an entity that is liable with the debtor on or has secured the claim of a creditor, to the extent that . . . such claim for reimbursement or contribution is contingent as of the time of allowance or disallowance of such claim for reimbursement or contribution. . . ." 11 U.S.C. § 502(e)(1)(B). For a claim to be disallowed under this section, three requirements must be satisfied: "(1) the claim must be one for reimbursement or contribution; (2) the entity asserting the claim for reimbursement or contribution must be `liable with the debtor' on the claim; and (3) the claim must be contingent at the time of its allowance or disallowance." In re Provincetown-Boston Airlines, Inc., 72 B.R. 307, 309 (Bankr.M.D.Fla. 1987); accord In re Eagle Picher Indus., Inc., 164 B.R. 265, 268 (S.D.Ohio 1994); In re GCO Servs., LLC, 324 B.R. 459, 465 (Bankr. S.D.N.Y. 2005); In re Drexel Burnham Lambert Group, 148 B.R. 982, 985 (Bankr. S.D.N.Y. 1992). Because the Court concludes that Claim No. 26 satisfies each of these three requirements, the claim must be disallowed.

First, Claim No. 26 is a claim for contribution. "Whether a claim is one for reimbursement or contribution depends on its characterization under state or federal statutory law or common law." 4 COLLIER ON BANKRUPTCY ¶ 502.06[2][a] (Alan N. Resnick et al. eds., 15th ed. rev. 2006); see, e.g., Provincetown-Boston, 72 B.R. at 310 ("[The Debtor's] duty to indemnify [the claimant] if both are found ultimately liable in the class action suit would arise independent of the Underwriting Agreement under the joint and several liability created by federal statute.").

Under CERCLA, two distinct causes of action have been created by Congress: "cost recovery" under 42 U.S.C. § 9607(a), commonly known as section 107(a), and "contribution" under 42 U.S.C. § 9613(f)(1), commonly known as section 113(f)(1). Under a section 107(a) "cost recovery" action, a party, such as a private party landowner or the United States government, who has incurred cleanup and remediation costs at a hazardous waste site, may seek to recover its full response costs from a party or parties who may be potentially responsible for the contamination. See generally United States v. Atl. Research Corp., ___ U.S. ____, 127 S.Ct. 2331, 168 L.Ed.2d 28 (2007). The apportionment of liability under section 107(a) is strict, joint, and several — "without regard to fault or willfulness". H.R. Rep. No. 99-253(I), at 74 (1985), reprinted in 1986 U.S.C.C.A.N. 2835, 2856; New Castle County v. Halliburton NUS Corp., 111 F.3d 1116, 1120-21 (3d Cir. 1997); In re Kaiser Group Int'l, Inc., 289 B.R. 597, 602 (Bankr.D.Del. 2003). Therefore, under section 107(a), "once liability is demonstrated, a [defendant] PRP may be held liable for the entire cost of cleanup, even if multiple PRPs are involved." Wichita Judgment at 1048-49.

Section 107(a) provides, in pertinent part:

Notwithstanding any other provision or rule of law, and subject only to the defenses set forth in subsection (b) of this section — (2) any person who at the time of disposal of any hazardous substance owned or operated any facility at which such hazardous substances were disposed of, shall be liable for —

(A) all costs of removal or remedial action incurred by the United States Government or a State or an Indian tribe not inconsistent with the national contingency plan;

(B) any other necessary costs of response incurred by any other person consistent with the national contingency plan;

(C) damages for injury to, destruction of, or loss of natural resources, including the reasonable costs of assessing such injury, destruction, or loss resulting from such a release; and

(D) the costs of any health assessment or health effects study. . . .

42 U.S.C. § 9607(a).

Under a section 113(f)(1) "contribution" action, a PRP is granted the right to recoup from other PRPs the portion of its cleanup and remediation costs "which exceeds its fair share of the overall liability." New Castle County, 111 F.3d at 1121; see also Atl. Research, 127 S.Ct. at 2331; Kaiser, 289 B.R. at 603. In other words, under section 113(f)(1), "an individual PRP which has been left with the entire cleanup cost . . . may seek contribution from and attempt to apportion liability to other PRPs. . . ." Wichita Judgment at 1049. In contrast to a section 107(a) action in which liability is joint and several, under section 113(f)(1), a court is called upon to allocate the response costs among the PRPs based upon each PRP's percentage of fault and, to do so, may use "such equitable factors as the court determines are appropriate." 42 U.S.C. § 9613(f)(1).

Section 113(f) provides, in pertinent part:

(1) Contribution

Any person may seek contribution from any other person who is liable or potentially liable under section 9607(a) of this title, during or following any civil action under section 9606 of this title or under section 9607(a) of this title. . . . . In resolving contribution claims, the court may allocate response costs among liable parties using such equitable factors as the court determines are appropriate. Nothing in this subsection shall diminish the right of any person to bring an action for contribution in the absence of a civil action under section 9606 of this title or section 9607 of this title.

42 U.S.C. § 9613(f)(1).

In the instant case, Claim No. 26 arises from a declaratory judgment obtained by the City against the Debtors for contribution under section 113(f)(1). See generally Wichita Judgment at 1117-18. Because, as a matter of law, section 113(f)(1) provides only for an express right of contribution, the first requirement of section 502(e)(1)(B) has been satisfied. See, e.g., Syntex Corp. v. Charter Co. (In re Charter Co.), 862 F.2d 1500, 1502-03 (11th Cir. 1989) ("These claims fall within the ambit of § 502(e)(1)(B). All are claims for reimbursement or contribution pursuant to 42 U.S.C. § 9613(f)(1). . . ."); Eagle Picher, 164 B.R. at 268 ("The parties further agreed that the claims in issue are for reimbursement, since the claimants seek payment from [the Debtor] for costs in be incurred and their claims arise under CERCLA § 113(f). . . ."); In re New York Trap Rock Corp., 153 B.R. 648, 651 (Bankr.S.D.N.Y. 1993) ("A contingent CERCLA claim that is not a direct claim between the parties but depends upon the co-liability of the parties . . . is a disallowable claim for reimbursement or contribution"); In re Cottonwood Canyon Land Co., 146 B.R. 992, 996-97 (Bankr.D.Colo. 1992) (holding claim subject to section 502(e)(1)(B) because, while claimant argued it sought allowance of a direct claim under section 107(a) of CERCLA, court determined that claimant clearly sought contribution from the Debtor).

In support of the allowance of Claim No. 26, the City has argued that, because the Wichita Judgment held the Debtors 100% liable for the future source control costs at 1001 E. Lincoln, and not merely for their allocable share, its claim is not one for contribution under section 113(f)(1), but rather, one for a direct cost recovery under section 107(a). The Court cannot agree. First, and perhaps, most importantly, the District Court in Kansas determined that the City was a PRP, and further determined that the City was precluded from maintaining a cost recovery action under section 107(a). Wichita Judgment at 1050-52. Therefore, foreclosed from maintaining a cause of action under section 107(a), the Court held that the City could "only bring a contribution action under CERCLA § 113(f)." Id. at 1052. It was exclusively under this section of CERCLA that the Court premised the Debtors' liability. See generally id. at 1050, 1117-18.

As more thoroughly discussed herein, the Supreme Court recently has held that PRPs may maintain a cost recovery action under section 107(a). See Atl. Research, 127 S.Ct. at 2331.

Second, despite the City's assertions to the contrary, the Debtors were, in fact, held liable for their allocable share of the City's future source control costs to be incurred at the entire G M Site. Following the City/KDHE Agreement, the City became responsible for all of the future source control costs to be incurred at the entire G M Site notwithstanding the City's actual percentage of fault. Because of this inequitable distribution of liability, shortly thereafter, pursuant to section 113(f)(1), the City sought contribution from the Debtors' for their allocable share of these overall costs. Id. at 1117. Rather than declaring the Debtors liable for a percentage of the source control measures to be taken at the approximate 8,000 parcels within the G M Site, the Court determined that the Debtors were liable only for the measures to be taken at one parcel — 1001 E. Lincoln. Id. The future source control costs for this parcel amount to the Debtors' allocable share of the City's overall liability for the future source control costs to be incurred at the entire G M Site. As such, Claim No. 26 arises from a claim for contribution, fulfilling the first requirement of section 502(e)(1)(B).

Because Claim No. 26 arises from a section 113(f)(1) claim for contribution, it is, as a matter of law, a claim for which both the City and the Debtors are responsible, thereby fulfilling the second, and perhaps most important, requirement of section 502(e)(1)(B). See 4 COLLIER ON BANKRUPTCY ¶ 502.06[2][d] ("In addition to codebtor situations created by contract, section 502(e)(1)(B) applies to disallow contingent reimbursement or contribution claims created by statute. For example, a claim for contribution arising under [CERCLA] may be a contingent claim subject to disallowance under section 502(e)(1)(B). In such a case, the government is the primary obligee that may seek satisfaction of its claim against the debtor from third parties who, under the statute, are obligated with the debtor to the government on the same debt. The statute under which the third-party liability is created, however, must provide for a reimbursement or contribution claim against the debtor."); see also Cottonwood Canyon, 146 B.R. at 996 (explaining that a contribution claim under CERCLA "would necessarily be one for liability for which both [the claimant and the debtor] are responsible and would fall within the ambit of 11 U.S.C. § 502(e)."); In re Baldwin-United Corp., 55 B.R. 885, 891 (Bankr.S.D.Ohio 1985) (applying section 502(e)(1)(B) to contribution claims arising under securities laws and noting, "By its very nature a claim for contribution presupposes a sharing of liability and thus a codebtor relationship."); accord GCO, 324 B.R. at 466 (disallowing contribution claims arising under ERISA).

"The co-liability requirement — that the claimant be `liable with' the debtor on the claim of a third party `creditor'-illuminates the central purpose of § 502(e)(1)(B)." Dant Russell, Inc. v. Burlington N. R.R. Co. (In re Dant Russell, Inc.), 951 F.2d 246, 248 (9th Cir. 1991). "The sole purpose served by section 502(e)(1)(B) is to preclude redundant recoveries on identical claims against insolvent estates in violation of the fundamental Code policy fostering equitable distribution among all creditors of the same class." Juniper Dev. Group v. Kahn (In re Hemingway Transp., Inc.), 993 F.2d 915, 923 (1st Cir. 1993); accord Dant Russell, 951 F.2d at 248.

While no "double-dipping" threat applies to claims arising under section 107(a) due to the lack of a third party creditor, claims premised upon section 113(f)(1) do implicate such a threat. This is because a judgment obtained under section 113(f)(1) presupposes co-liability between the plaintiff and the defendant. "A prima facie showing under § 113(f) is simply a determination that the defendant PRP would otherwise be held jointly and severally liable under § 107(a)." Wichita Judgment at 1049. As the court in Farmland Industries, Inc. v. Colorado Eastern Railroad Co. explained:

In Environmental Transp. Systems, Inc. v. ENSCO, Inc., 969 F.2d 503, 509 (7th Cir. 1992) . . ., the Seventh Circuit set forth the elements of a prima facie case for contribution under § 9613(f) as follows: "(1) that the site in question is a `facility' as defined by CERCLA; (2) that the Defendant is a `responsible person' for the spill as defined by CERCLA; (3) there was a release of hazardous substances; and (4) such release caused the Plaintiff to incur response costs." Id. at 506. "If the plaintiff establishes each of these elements and the defendant is unable to establish the applicability of one of the defenses listed in § 9607(b) the plaintiff is entitled to summary judgment on the liability issue." Amoco Oil Co. v. Borden, Inc., 889 F.2d 664, 668 (5th Cir. 1989). A prima facie showing under § 9613 is, therefore, simply a determination that under § 9607 the defendant would be jointly and severally liable.

922 F.Supp. 437, 440 (D.Colo. 1996), remanded by 50 F.3d 1530, 1536 (10th Cir. 1995) ("In our case, Farmland's claim against the CERC parties must be classified as one for contribution. . . . Whatever label Farmland may wish to use, its claim remains one by and between jointly and severally liable parties for an appropriate division of the payment one of them has been compelled to make.").

Here, the City successfully proved the elements of section 113(f)(1) to obtain an award of contribution from the Debtors. Therefore, as a matter of law, the Debtors are co-liable with the City to KDHE for the future source control costs at 1001 E. Lincoln.

The City argues that KDHE's failure to timely file a proof of claim in these Cases vitiates any co-liability the Debtors may have with the City to KDHE. In support, the City relies on the First Circuit's ruling in Hemingway. In Hemingway, a post-petition purchaser of a contaminated parcel of land sought contribution from the Debtors' estate for future costs of cleanup. 993 F.2d at 919-20. The chapter 7 trustee objected, citing to section 502(e)(1)(B). Id. While the purchaser filed a proof of claim against the estate for these costs, the EPA chose to forgo that option. Id. at 925. Instead, the EPA commenced an administrative enforcement action against the purchaser. Id. According to the court, without the EPA's claim, only "a remote double-dipping" prospect existed. Id. at 926. As a result, the court in Hemingway remanded the case to provide the chapter 7 trustee and the purchaser time to file a surrogate claim on the EPA's behalf. Id. at 929. Should the trustee or the purchaser fail to file a surrogate EPA claim, the court held that the purchaser's claim would be allowed since the purchaser would be no longer "liable with" the Debtors to the EPA. Id. at 925-29; see also Norpak Corp. v. Eagle-Picher Indus., Inc. (In re Eagle-Picher Indus. Inc.), 131 F.3d 1185, 1188-89 (6th Cir. 1997) (remanding case so that lower court could determine whether the third party creditors' failure to timely file proofs of claim was the result of excusable neglect); In re A H, Inc., 122 B.R. 84, 86 (Bankr.W.D.Wis. 1990) (noting the possibility that had the codebtor not filed a proof of claim on behalf of the third party creditor, the debtor may not have been co-liable to the third party creditor).

Relying on the court's reasoning in Hemingway, the City has argued that, in the instant case, there is no "double dipping threat". Currently, there is no proof of claim filed by KDHE and the bar date has long since passed. Thus, according to the City, KDHE is unable to seek payment from the Debtors' estate for the same future source control costs currently sought by the City. As such, the City urges this Court to find that it is the sole holder of a claim against the Debtors' estate for these costs.

The Court cannot agree with the City's position. In the instant case, it is undisputed that the bar date for KDHE to file a proof of claim passed more than one year ago and that KDHE has failed to file a claim against the Debtors' estates. Nonetheless, the failure of KDHE to file a claim does not alter the co-liability of the Debtors and the City to KDHE. As other courts have observed, "section 502(e) does not require that a proof of claim be filed in the proceeding to be liable with the debtor. Application of [section 502(e)(1)(B)] `is not premised on the actual filing of multiple claims but, rather, on the existence of such claims.'" In re Lull Corp., 162 B.R. 234, 238 (Bankr.D.Minn. 1993) (quoting Cottonwood Canyon, 146 B.R. at 997).

Moreover, as the court in Eagle-Picher explained, the Hemingway decision does not undermine this Court's determination that the City and the Debtors are co-liable to KDHE, despite KDHE's failure to file a proof of claim:

The appellate decision in Hemingway does not undermine the bankruptcy court's reasoning in the present case. The appellate court simply determined that the harsh results stemming from the application of § 502(e)(1)(B) could be alleviated by the use of the surrogate claim filing procedure of § 501(c). The court recognized that § 501(c) is permissive, not mandatory, and is designed primarily to prevent creditors from depriving debtors of the benefit of a discharge under § 727 of the Bankruptcy Code. The appellate court did not disturb the lower court's determination in Hemingway that the claimant and debtor as PRPs were co-liable and that the EPA was a creditor, even though it had not filed a proof of claim.

164 B.R. at 270. Thus, the Court rejects the City's argument and concludes that Claim No. 26 satisfies the second requirement of section 502(e)(1)(B).

Even were this Court were to follow the reasoning set forth in Hemingway, the City may not prevail. Under the principles of Hemingway, the Court would require the City to file a surrogate claim on behalf of KDHE. If this Court were to disallow the claim of KDHE on grounds of lateness or otherwise, then the City's claim would likewise be disallowed. See 11 U.S.C. § 502(e)(1)(A) ("[T]he court shall disallow any claim for reimbursement or contribution of an entity that is liable with the debtor on or has secured the claim of a creditor, to the extent that . . . such creditor's claim against the estate is disallowed. . . ."); see also In re Bicoastal Corp., 141 B.R. 231, 234 (Bankr.M.D.Fla. 1992) (noting that, even if the court were to permit a codebtor to file a claim against its codebtor's estate, it would be disallowed because their creditor's claim previously had been disallowed).

Finally, because the City has not yet incurred any future source control costs at 1001 E. Lincoln, Claim No. 26 is contingent, thereby, fulfilling the third requirement of section 502(e)(1)(B). "The determination of whether the claim is contingent is made at the time of allowance or disallowance of the claim, which courts have established is the date of the ruling." Drexel Burnham, 148 B.R. at 986. The law is clear that "[t]he contingency contemplated by [section] 502(e)(1)(B) relates to both payment and liability." Id. (emphasis added); accord In re Pacor, 110 B.R. 686, 689 (E.D.Pa. 1990); Kaiser, 289 B.R. at 608; Cottonwood Canyon, 146 B.R. at 997; Windolph Trust v. Leitch (In re Kent Holland Die Casting Plating, Inc.), 125 B.R. 493, 501 n. 4 (Bankr. W.D.Mich. 1991); In re Ace Fin. Co., 59 B.R. 667, 670 (Bankr.N.D.Ohio 1986); Baldwin-United, 55 B.R. at 895. Therefore, a claimant's "claim is contingent until their liability is established . . . and the codebtor has paid the creditor." Drexel Burnham, 148 B.R. at 987 (emphasis added).

In the instant case, the parties' liability has been established. The liability of the City to KDHE has been established by the City/KDHE Agreement, and the Debtors' liability to the City has been established by the Wichita Judgment. However, it is undisputed that the City has not yet incurred any future source control costs. If it had, its claim would not be contingent, and thus, beyond the reach of section 502(e)(1)(B). However, without the incurrence of any future response costs, Claim No. 26 is contingent.

The City argues that this result would preclude the allowance of any type of future claim since by its nature it will never be paid by the time of allowance or disallowance. The Court disagrees, as section 502(e)(1)(B)'s contingency requirement fosters the primary purpose of CERCLA:

to promote expeditious cleanup of hazardous waste sites by authorizing private parties who assume financial responsibility for a cleanup to seek contribution from other responsible parties before a determination of who necessitated the cleanup is made. . . . [Section] 502(e)(1)(B) fosters the primary objective of CERCLA by requiring those who seek contribution to incur the expenses relating to a cleanup before stating an allowable claim.

Eagle Picher, 164 B.R. at 272; see also Bicoastal, 141 B.R. at 233 ("It is well-settled in bankruptcy law that the debtor's estate should not be burdened by estimated claims contingent in nature. The Debtor should be `expeditiously rehabilitated and reorganized' to enable it a fresh start, while at the same time `according fair treatment to creditors by paying ascertain-able claims as quickly as possible.'") (quoting Charter Co., 862 F.2d at 1502).

It may appear that the Court's ruling is a harsh result for the City, and that may be true. Nevertheless, the Court's decision is mandated by the express language of the Code and is entirely consistent with the principles animating CERCLA. At bottom, CERCLA and similar state and federal environmental statutes create a scheme whereby parties are incentivized to promptly clean up contaminated sites. The prospect of the potential disallowance of contingent contribution claims under section 502(e)(1)(B) offers a further incentive to undertake the cleanup: if the work is done (or at least underway), the contribution claim is not contingent as to amounts incurred by the contribution claimant. Thus, if the City had commenced or completed source control remediation at 1001 E. Lincoln in connection with its work on the G M Site as a whole, the City's claim would be allowed to the extent of the amounts incurred. Accord Kaiser, 289 B.R. at 608.

Because the requirements of section 502(e)(1)(B) have been satisfied, the Court concludes Claim No. 26 must be disallowed.

II. Relief From a Final Judgment Pursuant to Federal Rule of Civil Procedure 60(b)(5)

Because the Court has disallowed the City's claim under section 502(e)(1)(B), it may not appear necessary to address additional arguments. Given that each side, however, has requested that the Court consider and give retroactive affect to different, subsequent decisions of the United States Supreme Court, and in the interest of completeness, the Court will address the arguments in turn.

As an alternative to disallowing Claim No. 26 pursuant to section 502(e)(1)(B), the Debtors have urged this Court to apply the Supreme Court's decision in Aviall pursuant to Federal Rule of Civil Procedure 60(b)(5) to nullify portions of the Wichita Judgment. In Aviall, the Supreme Court limited the circumstances under which PRPs can seek contribution under section 113(f)(1). 543 U.S. at 167, 125 S.Ct. 577. The Debtors contend that, applying Aviall, the City could never have established its right to maintain a cause of action for contribution and hence, Claim No. 26 should be disallowed.

On the flip side, the City would argue for the application of the Supreme Court's very recent decision in Atlantic Research, In Atlantic Research, the Supreme Court answered in the affirmative a question left open by Aviall: whether PRPs can maintain a direct cause of action under section 107(a) of CERCLA. Id. The City contends that, applying Atlantic Research, it had the right to prosecute a direct cost recovery action against the Debtors. Thus, the City would seek relief from that portion of the Wichita Judgment limiting it to a contribution claim under section 113(f)(1). With a direct claim, of course, disallowance under section 502(e)(1)(B) of the Code would not be proper due to the lack of co-liability.

At the time the Court took this matter under advisement, the question of whether PRPs who undertake voluntary cleanup efforts can maintain a cause of action under section 107(a) had produced conflicting Circuit decisions and was the subject of a writ of certiorari granted by the Supreme Court. Thus, the City could only argue speculatively that if the Supreme Court rendered its decision favorably in Atlantic Research, PRPs could maintain a section 107(a) cause of action. As discussed more thoroughly herein, the Supreme Court handed down its decision in Atlantic Research on June 11, 2007 and the parties promptly notified the Court of the opinion. Although not thoroughly briefed by the parties, the Court will consider the decision in this Memorandum Opinion.

To summarize, the Debtors wish to apply Aviall to undo the City's contribution claim obtained through the Wichita Judgment. The City, on the other hand, wishes to apply Atlantic Research to assert the direct cost recovery claim expressly precluded by the Wichita Judgment, and thus, avoid disallowance of the contribution claim. The bottom line, however, is that both the Debtors and the City urge the Court, pursuant to Rule 60(b)(5), to apply new Supreme Court precedent to either nullify or expand the final and non-appealable Wichita Judgment rendered almost five years ago. The Court concludes that such an application, in either direction, would be inappropriate.

Rule 60(b)(5) provides, in pertinent part, that "the court may relieve a party . . . from a final judgment, order, or proceeding [if] . . . a prior judgment upon which it is based has been reversed or otherwise vacated, or it is no longer equitable that the judgment should have prospective application. . . ." Motions under Rule 60(b) "may not generally substitute for an appeal." Marshall v. Bd. of Educ., Bergenfield, N.J., 575 F.2d 417, 424 (3d Cir. 1978). "Rather, relief under Rule 60(b) is available only under such circumstances that the `overriding interest in the finality and repose of judgments may properly be overcome.'" Harris v. Martin, 834 F.2d 361, 364 (3d Cir. 1988) (quoting Martinez-McBean v. Gov't of Virgin Islands, 562 F.2d 908, 913 (3d Cir. 1977)).

Because of the "`overriding interest in the finality and repose of judgments'. . . . the `prior judgment' clause of Rule 60(b)(5) `does not contemplate relief based merely upon precedential evolution.'" Id. (quoting Mayberry v. Maroney, 558 F.2d 1159, 1164 (3d Cir. 1977)). Rather, "`the prior judgment upon which [a judgment] is based [must have] been reversed or otherwise vacated. . . .'" Marshall, 575 F.2d at 424 (quoting 7 J. Moore, MOORE'S FEDERAL PRACTICE ¶ 60.26(3), at 325 (2d ed. 1975)); accord Harris, 834 F.2d at 364. It is not sufficient "`that the law applied by the court in making its adjudication has been subsequently overruled or declared erroneous in another and unrelated proceeding.'" Marshall, 575 F.2d at 424 (quoting 7 MOORE'S FEDERAL PRACTICE ¶ 60.26(3), at 325). Thus, for a party to preserve its rights, an appeal is necessary. Harris, 834 F.2d at 364. In the absence of an appeal, the Third Circuit has made it clear that "the party who has suffered an adverse judgment may secure relief only from the prospective aspects of [the] judgment in the event it turns out to rest on an erroneous view of the law." Id. at 365.

In the instant case, neither the Debtors nor the City appealed the Wichita Judgment. Moreover, the Wichita Judgment does not grant any prospective relief. As the Court in Marshall explained:

[A] judgment at law for damages for past wrongs is "inherently final," and remains unaffected by a subsequent change in the law. . . . A "prospective" injunction envisions a restraint of future conduct, not an order to remedy past wrongs when the compensation payment is withheld from the beneficiaries until some subsequent date.

575 F.2d at 425 (internal citations omitted). The Wichita Judgment does not restrain the Debtors' future conduct, but rather, is no more than "an order to remedy past wrongs when the compensation payment is withheld from the beneficiaries until some subsequent date." Id.

Therefore, in the absence of an appeal or any prospective relief, Rule 60(b)(5) cannot be applied to grant the Debtors or the City relief from the Wichita Judgment.

Although not briefed or argued, the only remaining clause of Rule 60(b) that could apply to the instant case is Rule 60(b)(6), which provides that "the court may relieve a party . . . from a final judgment, order, or proceeding for . . . any other reason justifying relief from the operation of the judgment." This clause "`provides for extraordinary relief and may only be invoked upon a showing of exceptional circumstances.'" Marshall, 575 F.2d at 425 (quoting Vecchione v. Wohlge-muth, 558 F.2d 150, 159 (3d Cir. 1977)). In the instant case, the only argument the parties have put forth to satisfy this stringent standard is that if the law were different, they would have prevailed (or obtained a more favorable result) in the Wichita Action. This is not the type of "exceptional circumstance" contemplated by Rule 60(b)(6). See Harris, 834 F.2d at 366 ("While judgments are subject to being opened and retroactively modified in certain extraordinary situations where justice demands, a change in precedent is not one of those extraordinary circumstances.").

CONCLUSION

For the foregoing reasons, the Court concludes that Claim No. 23 constitutes a contingent claim for contribution of an entity that is liable with the debtor to a third party creditor. Therefore, it must be disallowed under section 502(e)(1)(B).

An appropriate Order follows.


Summaries of

In re APCO Liquidating Trust

United States Bankruptcy Court, D. Delaware
Jun 29, 2007
370 B.R. 625 (Bankr. D. Del. 2007)

disallowing as contingent future environmental costs

Summary of this case from Route 21 Associates of Belleville, Inc. v. MHC, Inc.
Case details for

In re APCO Liquidating Trust

Case Details

Full title:In re APCO LIQUIDATING TRUST and APCO Missing Stockholder Trust, Debtors

Court:United States Bankruptcy Court, D. Delaware

Date published: Jun 29, 2007

Citations

370 B.R. 625 (Bankr. D. Del. 2007)

Citing Cases

In re Chemtura Corp.

1995)). See In re APCO Liquidating Trust, 370 B.R. 625 (Bankr.D.Del.2007) (Shannon, J.) (“ APCO ”).…

In re Chemtura Corp.

1995)).See In re APCO Liquidating Trust, 370 B.R. 625 (Bankr. D. Del. 2007) (Shannon, J.) (" APCO").…