Summary
applying the APA to review a claim under the Water Supply Act
Summary of this case from State ex rel. Bailey v. United States Dep't of InteriorOpinion
CIVIL ACTION FILE NO. 1:18-MI-43-TWT
2021-08-11
OPINION AND ORDER
THOMAS W. THRASH, JR., United States District Judge
This action is before the Court on the Plaintiff State of Alabama's Motion for Summary Judgment and Amended Motion for Summary Judgment [Doc. 164, 220], the Plaintiff National Wildlife Federation, Florida Wildlife Federation, and Apalachicola Bay and River Keeper's Motion for Summary Judgment and Amended Motion for Summary Judgment [Doc. 165, 219], the Defendant U.S. Army Corps of Engineers’ Cross-Motions for Summary Judgment [Doc. 202, 203], the Defendant State of Georgia's Cross-Motions for Summary Judgment [Doc. 211, 213], and the Defendant Georgia Water Supply Providers’ Cross-Motions for Summary Judgment [Doc. 216, 218]. For the reasons set forth below, the Court DENIES the Plaintiff State of Alabama's Motion for Summary Judgment and Amended Motion for Summary Judgment [Doc. 164, 220], DENIES the Plaintiff National Wildlife Federation, Florida Wildlife Federation, and Apalachicola Bay and River Keeper's Motion for Summary Judgment and Amended Motion for Summary Judgment [Doc. 165, 219], GRANTS the Defendant U.S. Army Corps of Engineers’ Cross-Motions for Summary Judgment [Doc. 202, 203], GRANTS the Defendant State of Georgia's Cross-Motions for Summary Judgment [Doc. 211, 213] and GRANTS the Defendant Georgia Water Supply Providers’ Cross-Motions for Summary Judgment [Doc. 216, 218].
I. Background
On April 5, 2017, the State of Alabama filed its Complaint against Defendants U.S. Army Corps of Engineers; Robert M. Speer in his official capacity as Acting Secretary of the U.S. Army; Douglas Lamont in his official capacity as senior official exercising the functions of the Assistant Secretary of the U.S. Army for Civil Works; Todd T. Semonite in his official capacity as Commander and Chief of Engineers for the U.S. Army Corps of Engineers; C. David Turner in his official capacity as Division Commander for the South Atlantic Army Corps of Engineers; and James A. DeLapp in his official capacity as the District Commander for Mobile District of U.S. Army Corps of Engineers. Ala. Compl. Alabama brings this action under the Administrative Procedure Act, 5 U.S.C. §§ 701 et seq. , the Water Supply Act of 1958, 43 U.S.C. §§ 390b et seq. , and the National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321 - 4347, to set aside the U.S. Army Corps of Engineers’ adoption in 2017 of the Final Environmental Impact Statement ("Final EIS") for the Apalachicola-Chattahoochee-Flint ("ACF") River Basin Water Control Manual and Water Supply Storage Assessment. Id.
Similarly, on April 27, 2017, the National Wildlife Federation, the Florida Wildlife Federation and Apalachicola Bay and River Keeper, Inc. filed their Complaint against Defendants U.S. Army Corps of Engineers; Douglas Lamont in his official capacity as senior official exercising the functions of the Assistant Secretary of U.S. Army for Civil Works; Todd T. Semonite in his official capacity as Commander and Chief of Engineers for U.S. Army Corps of Engineers; and C. David Turner in his official capacity as Division Commander for South Atlantic Army Corps of Engineers. NWF Compl. The Plaintiffs bring this action under the Administrative Procedure Act, 5 U.S.C. §§ 701 et seq. , the Water Resources Development Act of 2007, 33 U.S.C. § 2283(d), the National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321 - 4347, and the Fish and Wildlife Coordination Act, 16 U.S.C. §§ 661 - 667e to set aside the Corps’ Updated ACF River Basin Water Control Manual. The State of Georgia, Atlanta Regional Commission, City of Atlanta, Cobb County-Marietta Water Authority, DeKalb County, Forsyth County, Fulton County, City of Gainesville, and Gwinnett County have intervened as Defendants in both cases.
These actions arise from the U.S. Army Corps’ operations of five reservoirs within the ACF River Basin, formed by the Apalachicola, Chattahoochee, and Flint rivers, their tributaries, and their drainage areas. Ala. Compl., at ¶ 11. The Chattahoochee River forms a large portion of the eastern border between Alabama and Georgia. Id. at ¶ 12. The Chattahoochee River starts in northeast Georgia, and flows southwest toward Alabama, where it flows south before emptying into Lake Seminole at the Florida-Georgia line. Id.
The Corps operates five reservoirs on the Chattahoochee River. The uppermost and largest of the reservoirs is Buford Dam, which impounds the Chattahoochee River to create Lake Lanier approximately fifty miles north of Atlanta. Below Lake Lanier, the Corps operates three dams along the Chattahoochee River on the Alabama border, including West Point Dam (associated with West Point Lake), Walter F. George Lock and Dam (associated with Walter F. George Lake), and George Andrews Lock and Dam (associated with Lake George W. Andrews). Ala. Compl., at ¶ 13. Approximately 2,800 square miles of the ACF River Basin lie within Alabama's borders. Id. at ¶ 14. The Corps’ southernmost project within the ACF River Basin is the Jim Woodruff Lock and Dam which impounds Lake Seminole on the Florida-Georgia line. Final Environmental Impact Statement ("Final EIS"), 1-1 to 1-2. Water released from the Woodruff Dam forms the Apalachicola River in Florida. Id.
The U.S. Army Corps operates the ACF projects pursuant to "specific" and "general" authorities established by Congress. Final EIS, 2-59 to 2-60. Specific authorities are established in the original legislation authorizing construction of a certain project. Final EIS, ES-1, 2-59 to 2-60. The authorizing statutes usually refer to and incorporate "reports" that the Corps presents to Congress as part of the authorization process to provide recommendations regarding the benefits of the projects. For the ACF reservoirs, specific authorities include navigation, hydropower, flood control, water supply, and fish and wildlife conservation. Final EIS, ES-1, 2-59 to 2-60. General authorities supplement these specific authorities and apply to all federal agencies or Corps reservoirs, including the Endangered Species Act and the Fish and Wildlife Coordination Act.
Because authorized purposes often conflict, the Corps is required to develop a Master Manual to describe how it will operate the system to balance conflicting purposes. 33 U.S.C. § 709 ; Final EIS, ES-1 to ES-2. The Master Manual governs the operation of the five Corps reservoirs on the Chattahoochee River in the ACF Basin. Ala. Compl., ¶ 18. The Corps’ last official Master Manual for the ACF system was adopted in 1958. Id. at ¶ 19. While the Corps was conducting its ACF operations under the 1958 Manual, Congress passed, and the President signed, the National Environmental Policy Act, 42 U.S.C. §§ 4321 et seq. , ("NEPA"). Id. at ¶ 20. The National Environmental Policy Act requires the Corps to issue an Environmental Impact Statement ("EIS") concerning any significant changes to its ACF operations. Id.
The Buford Project is at the center of this litigation. The Buford Project consists of the reservoir Lake Lanier north of Atlanta formed by Buford Dam. Congress gave the U.S. Army Corps authority to build and operate the Buford Project in two statutes: the Rivers and Harbors Act of 1945 and the Rivers and Harbors Act of 1946. Ala. Amend. Motion for Summary Judgment, at 6. In 1939, the Corps submitted a report to Congress recommending development of the ACF Basin for multiple purposes, including navigation, hydroelectric power, national defense, commercial value of riparian lands, recreation, and industrial and municipal water supply. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 4. Congress approved the Corps’ plan in the Rivers and Harbors Act of 1945. Id.
In 1946, the Corps recommended in another report submitted to Congress, known as the Newman Report, several changes to the original plan, including reducing the proposed number of locks, dams, and reservoirs from twelve to four and moving one of the proposed hydropower generating dams and reservoirs further upstream from Atlanta to its eventual location in Buford, Georgia. Id. The explanation for doing so included "water supply" downstream, as well as to include sufficient storage in the reservoir for extensive flood control for the basin, which would free up storage in downstream projects for other uses. Id. If hydropower releases of water did not meet Atlanta's water-supply demands, the Newman Report recommended that the Corps make continuous releases from the Buford Project during "off-peak periods" to secure a flow of 650 cubic feet per second to Atlanta. Ala. Amend. Motion for Summary Judgment, at 8. The report mentioned that the releases "may have to be increased somewhat as the area develops" but stated that they "would not materially reduce the power returns." Id. In the Rivers and Harbors Act of 1946, Congress authorized the Corps to build and operate the Buford Project "in accordance with the report of the Chief of Engineers, dated May 13, 1946." Id. The Chief's Report recommended the "plans of division engineer" set forth in the Newman Report "with such changes therein as in the discretion of the Secretary of War and the Chief of Engineers may be advisable." Id.
Behind Buford Dam is Lake Lanier, which covers about 38,000 acres and has 692 miles of shoreline. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 9. The Corps divides Lake Lanier into three "pools." Id. The top one is the "flood control pool" that generally remains empty, so it can take on water when inflows are too high. Id. The bottom one is the "inactive storage pool" and stays full. Id. The middle one is the "conservation storage pool" and is most pertinent to this litigation. Id. The Corps fulfills the hydropower and navigation purposes authorized by the Rivers and Harbors Acts of 1945 and 1946 by releasing water from the "conservation storage pool" to flow to downstream locations in Alabama and elsewhere. Ala. Amend. Motion for Summary Judgment, at 10. To produce hydropower, the Corps releases water though two large turbines and a third smaller one. Id. These water releases generate electricity at Buford Dam and allow the Corps’ downstream facilities at West Point and W.F. George to use the flows to generate electricity on their own. Id. To fulfill the navigation purposes, the Corps sends water through Buford Dam, which "provide[s] navigable depths" downstream and allows vessels to travel at certain locations in the Chattahoochee and Apalachicola. Id.
To fulfill the water-supply purpose, the Corps releases water from the "conservation storage pool." Id. When the Corps makes releases for hydropower generation and downstream withdrawals during times of peak demand, typically weekdays, the hydropower generated is most valuable. Id. at 11. To meet Atlanta's water supply needs, the Corps also makes releases during off-peak hours, typically weekends, when the hydropower generated is less valuable. Id. Alabama argues that the reports underlying the Rivers and Harbors Acts did not envision that Georgia entities would make withdrawals directly from Lake Lanier ("direct withdrawals") but envisioned that the Corps would make releases from Lake Lanier for the purpose of downstream withdrawals, which are withdrawals that Georgia entities make from non-Corps’ facilities located at various points along the Chattahoochee. Id. Alabama maintains that any direct withdrawals from Lake Lanier serve only the single purpose of water supply because the Corps retains water in the reservoir, rather than releasing it through the dam turbines and on to locations downstream. Id. at 11-12.
As mentioned, federal law requires that the Corps issue manuals governing operations of its projects. See 33 U.S.C. § 709. The 1958 Reservoir Regulation Manual for the Buford Project and the 1959 Buford Manual provided for hydropower and navigation which "generally yielded sufficient downstream flows to meet Atlanta's water supply needs" through withdrawals from the Chattahoochee. Ala. Amend. Motion for Summary Judgment, at 15. The 1959 Manual provided that the Buford Project generally would be operated to produce hydropower during periods of peak demand, with sufficient releases during off-peak hours to provide Atlanta with a minimum flow of 600 cubic feet per second. Id. at 14. In 1960, the Corps committed to ensuring minimum flows at Atlanta of 650 cubic feet per second. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 11. In 1973, in response to Atlanta's growing area and expected need for larger municipal and industrial water supply, the Senate Public Works Committee commissioned the Metropolitan Atlanta Area Water Resources Management Study. Id. at 12. During that time, the Corps entered interim water-supply contracts with local water-supply providers. Id.
In 1982, the Study's final report recommended meeting Atlanta's needs through a new "reregulation" dam below Buford Dam that could capture the varying hydropower releases and rerelease the water at a steadier rate. Id. In 1986, Congress authorized construction of the reregulation dam but did not appropriate any funds to build it. Id. In 1986, the Corps entered a temporary water-supply contract with the Atlanta Regional Commission, which provided the Atlanta Regional Commission with releases sufficient to allow greater downstream withdrawals "with no impact" on the project. Id. Interim water-supply agreements for direct withdrawals were also reached with the City of Gainesville, City of Cumming, and Gwinnett County. Id.
By 1989, the Corps decided to reallocate storage in the Buford Project permanently rather than build the reregulation dam. Id. at 13. The Corps prepared a draft Post Authorization Change ("PAC") report which would amend the Master Manual. Id. The draft PAC report recommended allocating 207,000 acre-feet of conservation storage in the Buford Project to water supply, which would allow roughly 151 million gallons per day to be withdrawn directly from Lake Lanier and 378 million gallons per day from the river downstream. Id. The draft PAC report also included a draft updated Master Manual to govern operations in the ACF Basin. Id. The Corps maintained that the reallocation of storage to water supply recommended in the draft PAC report was made under the authority of the Water Supply Act of 1958, 43 U.S.C. § 390b. Id. at 14. The draft PAC report referenced the Water Supply Act but did not determine whether Congress would need to authorize the proposed reallocation to water supply. Id.
When the Corps issued the draft PAC report, Alabama immediately filed suit to prevent the Corps from carrying out the draft PAC report's recommendations. After Florida and Georgia intervened, the parties agreed to a stay of the litigation, in which the Corps agreed it would not execute any contracts for water storage under the Water Supply Act without the written permission of Alabama and Florida as long as the stay remained in effect. Id. at 14. In 1992, a Memorandum of Agreement was signed by the Corps, Georgia, and Alabama that set up a "Comprehensive Study" of the water issues in the ACF Basin. Id. at 14-15. In the Agreement, the Corps agreed to withdraw the draft PAC report to facilitate negotiations among the States. Id. at 15. Thus, the parties agreed that "during the term of the Comprehensive Study, it is premature for the Army to commit, grant or approve any reallocation, allocation or apportionment of water resources to service long-term future water supply." Id. The Agreement allowed parties to continue withdrawing water for water supply and to make reasonable increases in those withdrawals but specified that it "shall [not] be construed as changing the status quo as to the Army's authorization of water withdrawals." Id. The parties referred to that provision as the "live-and-let-live" agreement. Id.
In 1997, the 1992 Memorandum of Agreement was replaced by the ACF Compact, which set up a framework for negotiating an equitable allocation of water among the three states signed by the same parties and passed into law by Congress. Id. The ACF Compact contained a live-and-let-live provision allowing for the continued withdrawal of water, with reasonable increases. Id. The ACF Compact remained in place until August 31, 2003. Id. The Alabama case remained stayed throughout that period. Id. The interim water-supply contracts between the Corps and the Georgia Parties expired in 1990, but under the live-and-let-live agreement the Corps provided for continued water-supply withdrawals without any formal contractual relationship with the Georgia Parties. Id. at 16.
In 2000, the State of Georgia asked the Corps to modify its operation of the Buford Project to meet projected water-supply needs until the year 2030, including withdrawal of 408 million gallons per day from the river and 297 million gallons per day directly from Lake Lanier. Id. The Corps determined that meeting Georgia's request would require it to reallocate 370,930 acre-feet of conservation storage in the Buford Project to water supply. Id. At that time, the Corps rejected Georgia's request, because it concluded that it did not have sufficient authority under the 1946 Rivers and Harbors Act and the Water Supply Act to make such a large reallocation of storage without congressional approval. Id. Georgia sued challenging that denial.
In another suit regarding the Buford Project's water storage, the Southeastern Federal Power Customers, a group which buys power generated at Buford Dam, sued claiming that water-supply withdrawals and the increased shift to non-peak hydropower production meant it was paying more for hydropower generation than it should have been. Southeastern Federal Power Customers v. Geren , 514 F.3d 1316 (D.C. Cir. 2008). The Corps, Southeastern Federal Power Customers, and the Georgia Parties negotiated an agreement to settle which provided for a ten or twenty year "temporary" reallocation of over twenty percent of the water storage in the Lake Lanier Reservoir. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 17. In that agreement, the Georgia Parties agreed to a process in which they would pay substantially more for interim storage for water supply from the Buford Project than they had been paying for withdrawals under the live-and-let-live agreement. Id. This interim storage would convert to permanent storage contracts under certain conditions. Id. The payments made under those contracts would then be used to offset the loss of hydropower generation caused by the shift to water supply storage, making Southeastern Federal Power Customers whole. Id. Alabama and Florida objected to this settlement agreement in two courts. Id. Ultimately, the D.C. Circuit held that the agreement violated the Water Supply Act because it made a reallocation of storage that would cause a major operational change without congressional approval. Geren , 514 F.3d at 1325.
By 2009, various lawsuits regarding the Corps’ rejection of Georgia's request to reallocate 370,930 acre-feet of conservation storage in the Buford Project to water supply were consolidated by the Judicial Panel on Multidistrict Litigation in the Middle District of Florida. The district court held that the Corps exceeded its authority in its "de facto" reallocation of storage to accommodate water supply withdrawals. In re MDL-1824-Tri-State Water Rights Litigation , 639 F. Supp. 2d 1308 (M. D. Fla. 2009). On appeal, the Eleventh Circuit reversed the district court. In re MDL-1824-Tri-State Water Rights Litigation , 644 F.3d 1160 (11th Cir. 2011). The Eleventh Circuit found that the district court lacked jurisdiction over the claims filed by Alabama, Florida, and Southeastern Federal Power Customers challenging the Corps’ ongoing operation of Buford Dam. Id. at 1181. A challenge under the Administrative Procedure Act requires "final agency action," and the Eleventh Circuit concluded that the Corps had not taken any such final action to reallocate storage in the Buford Project or completed the necessary environmental analyses under NEPA and other statutes. Id. at 1182, 1184.
The Eleventh Circuit also held that Georgia's 2000 request for a reallocation of storage in the reservoir to water supply must be remanded to the Corps. Id. at 1186-97. The Corps had previously concluded that the 1946 Rivers and Harbors Act did not establish water supply as an authorized purpose of the project, but instead made downstream water supply only an incidental benefit of operating the project for other purposes. Therefore, it rejected Georgia's 2000 request to allow municipal and industrial withdrawals from Lake Lanier to increase as necessary. The Eleventh Circuit disagreed, holding that Congress had unambiguously provided that the reservoir would be operated to accommodate downstream water-supply demands and therefore allowed an allocation of storage in the reservoir for that purpose. Id. The Eleventh Circuit held that "Sections 79 and 80 [of the Newman Report incorporated into the RHA] clearly indicates that Congress intended for water supply to be authorized, rather than incidental, use of the water stored in Lake Lanier." Id. at 1188-89.
The court concluded that the Corps’ interpretation of the 1946 Rivers and Harbors Act was not entitled to deference because it had been inconsistent over time. Id. at 1193. The court held that the Corps must reconsider the Georgia water supply request that it had erroneously denied based on lack of authority. Id. at 1192-93. The court did not define the precise scope of the Corps’ authority to accommodate water supply, concluding that the "authorizing legislation is ambiguous with respect to the extent of the Corps’ balancing authority – i.e., the extent of the Corps’ authority under the RHA to provide water supply for the Atlanta area." Id. at 1200. The court gave the Corps one year on remand to arrive at a "well-reasoned, definitive, and final judgment" as to its authority under the 1946 Rivers and Harbors Act and the Water Supply Act. Id. at 1205.
In 2012, the Corps’ Chief Counsel issued a legal opinion concluding that the Corps was fully authorized to grant Georgia's request, but that an Environmental Impact Statement ("EIS") would need to be prepared before any decision could be made. NWF's Compl., at ¶ 89. The Corps prepared a Memorandum for the Chief of Engineers, known as the 2012 Stockdale Memo, considering the Corps’ legal authority and an accompanying analysis of the impacts of providing storage at the Buford Project for water supply. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 19-20. The Corps concluded that the 1946 Rivers and Harbors Act provides sufficient authority for the Corps to meet Georgia's request as it pertains to releases from the Buford Project to support downstream water supply. Id. The Corps also concluded that the Water Supply Act provides sufficient authority for a reallocation of storage in the reservoir to water supply for direct withdrawals from the reservoir. Id.
In 2015, the Corps prepared a draft updated Master Manual and individual manuals. Ala.’s Compl., at ¶ 24. It also prepared the draft Environmental Impact Statement under NEPA and a Water Supply Storage Assessment allocating space at Lake Lanier for Georgia's water supply in which the Corps ultimately concluded that it could accommodate Georgia's request for storage at the Buford Project to facilitate withdrawals both downstream and from the reservoir itself. Some potential effects of increasing the amount for water supply included reduced flows downstream and an adverse impact on dissolved oxygen, nitrogen and chlorophyll. Id. at ¶¶ 32, 45, 59. During the public comment period on the draft manual, Alabama and the Environmental Protection Agency objected to the aspects of the proposal concerning the impairment of applicable water quality standards. Id. at ¶¶ 25, 28.
Contrary to Alabama's and the EPA's concerns, the Corps issued a Final Environmental Impact Statement which analyzed the effects of the Corps’ updated operations and concluded that the updated Master Manual would have a "negligible" effect on the Apalachicola River and Bay. NWF's Compl., at ¶ 172; Final EIS, ACF-18_00054074 (Executive Summary, at 42). The EIS also acknowledges that the updated Master Manual could have "substantially adverse" effects on riverine fish and aquatic resources in reaches of the Chattahoochee River and "slightly adverse" to "substantially adverse" impacts on the phosphorous, nitrogen, and dissolved oxygen content in the Chattahoochee River. NWF's Compl., at ¶ 210. The Corps ultimately concluded that it could provide 254,170 acre-feet of storage for direct withdrawals at the Buford Project without a major change to operations and without seriously affecting the other project purposes. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 34. On March 30, 2017, the Corps issued a Record of Decision adopting the updated Master Manual through the guidance and support of the Final EIS. NWF's Compl., at ¶ 23. The Record of Decision (ACF-18_00000149) is attached as Appendix A to this Opinion and Order.
Now, the National Wildlife Federation, the Florida Wildlife Federation, Apalachicola Bay and River Keeper, Inc. and the State of Alabama jointly challenge the updated Master Manual, alleging that the Corps struck the wrong balance by giving too much weight to purposes such as water supply and hydropower generation and not enough to fish and wildlife conservation and that the Corps violates the Water Supply Act by allowing Georgia to make direct withdrawals of water from the Buford Dam.
On May 22, 2020, this Court granted judgment in favor of the Defendants as to Counts III and portions of Count V of Alabama's Complaint which are based on the Clean Water Act. Thus, the State of Alabama now alleges that the Master Manual should be set aside for four reasons: (1) Count I, alleging a violation of the Water Supply Act, 43 U.S.C. § 390b(e) ; (2) Count II, alleging unlawful abandonment and reordering of authorized project purposes under the Rivers and Harbors Acts; (4) Count IV, alleging violation of the National Environmental Policy Act, 42 U.S.C. §§ 4321 et seq. ; and (5) Count V, alleging violations of the Administrative Procedure Act, 5 U.S.C. § 706(2)(A), not based on violations of the Clean Water Act. On April 6, 2021, the Plaintiff the State of Alabama filed its Amended Motion for Summary Judgment as to all remaining counts. The Defendants the U.S. Army Corps, the State of Georgia, and the Georgia Water Supply Providers each filed Responses and Cross-Motions for Summary Judgment [Doc. 202, 211, 216].
Similarly, on May 22, 2020, this Court granted the Defendants’ Motion for Judgment on the Pleadings as to Counts II and III of the National Wildlife Federation's Complaint. Thus, only Count I remains. Under Count I, the National Wildlife Federation's Complaint alleges that the Master Manual should be set aside because the Final EIS is legally insufficient under the National Environmental Policy Act of 1969, 42 U.S.C. §§ 4321 -4327 ("NEPA"). On April 5, 2021, the Plaintiff National Wildlife Federation filed its Motion for Summary Judgment as to Count I. The Defendants U.S. Army Corps, the State of Georgia, and the Georgia Water Supply Providers filed their Responses and Cross-Motions for Summary Judgment [Doc. 203, 214, 217].
II. Legal Standard
When a case comes before the court pursuant to judicial review standards of the Administrative Procedure Act ("APA"), "the normal rules of summary judgment do not apply." St. Johns Riverkeeper, Inc. v. U.S. Army Corps of Eng'rs , 462 F. Supp. 3d. 1256, 1270 n.6 (M.D. Fla. 2020). Instead, summary judgment "serves as the mechanism for deciding, as a matter of law, whether the agency action is supported by the administrative record and otherwise consistent with the standard of review." See Black Warrior Riverkeeper, Inc. v. U.S. Army Corps of Eng'rs , 354 F. Supp. 3d 1253, 1267 (N.D. Ala. 2018). Under the APA, a court must set aside agency action, findings, and conclusions that it finds to be "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. § 706(2)(A). The court also must ensure that the agency acted within the scope of its statutory authority, 5 U.S.C. § 706(2)(C), and must determine whether the Corps’ decision "was reasonably supported by the information before it." Envtl. Coal. of Broward Cnty. v. Myers , 831 F.2d 984, 986 (11th Cir. 1987). "This does not require that all of the data support the agency's decision, rather It is enough that the Corps considered all relevant factors and that there is credible evidence in the record to support its action." Id. "[T]he agency must examine the relevant data and articulate a satisfactory explanation for its action including a rational connection between the facts found and the choice made." Motor Vehicle Mfrs. Ass'n of U.S. v. State Farm Mut. Auto. Ins. Co. , 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (internal quotations and citations omitted). The court must examine whether the agency "relied on factors which Congress has not intended it to consider," "entirely failed to consider an important aspect of the problem," or "offered an explanation" either contrary "to the evidence before the agency" or "so implausible that it could not be ascribed to a difference in view or the product of agency expertise." Id.
The burden is on the plaintiff to demonstrate that the agency acted arbitrarily and capriciously. See Legal Envtl. Assistance Found. Inc. , 276 F.3d at 1265 (11th Cir. 2001) (internal quotations and citations omitted) ("[A] party seeking to have a court declare an agency action to be arbitrary and capricious carries a heavy burden indeed."). Courts typically resolve APA challenges on summary judgment, and "[t]he factfinding capacity of the district court is thus typically unnecessary." Fla. Power & Light Co. v. Lorion , 470 U.S. 729, 744, 105 S.Ct. 1598, 84 L.Ed.2d 643 (1985). "[C]ourts are to decide, on the basis of the record the agency provides, whether the action passes muster under the appropriate APA standard of review." Id.
III. Discussion
The Court will address the State of Alabama's Amended Motion for Summary Judgment [Doc. 220] and National Wildlife Federation's Amended Motion for Summary Judgment [Doc. 219] in turn, along with the Defendants’ corresponding cross-motions for summary judgment.
A. Alabama's Amended Motion for Summary Judgment [Doc. 220]
The State of Alabama brings this suit to challenge the U.S. Army Corps’ adoption of the updated Master Manual for its system of dams and reservoirs in the ACF Basin. The State of Alabama and the State of Georgia have not been able to agree on how to divide the waters of the ACF Basin between them. The State of Alabama's Complaint is centered on the Corps’ management of the federal dams and reservoirs in the ACF Basin, particularly water supply in the Buford Project.
Following the Eleventh Circuit's decision in In re MDL-1824 Tri-State Water Rights Litig. , 644 F.3d 1160 (11th Cir. 2011), the Corps completed an Environmental Impact Statement for a revised Master Manual for the ACF Basin and concluded that it could accommodate Georgia's request for storage at the Buford Project to facilitate withdrawals both downstream of the Project and from the reservoir itself. Alabama now argues that the Master Manual should be set aside under the Administrative Procedure Act for it is "not in accordance with the law," outside the Corps’ "statutory ... authority," and "arbitrary and capricious." In its Response to the Defendants’ Cross-Motions for Summary Judgment, the State of Alabama also requests that the Court rule on Alabama's supplemental complaint concerning the Corps’ January 20, 2021 execution of a Water Storage Agreement with the State of Georgia for the reallocated water storage space in Lake Lanier.
Alabama argues that the Court should deem the updated Master Manual unlawful for four reasons. In Count I of its Complaint, Alabama alleges that the Corps violated the Water Supply Act of 1958 by allocating 254,170 acre-feet (23.7%) of the Buford Project's conservation pool for Georgia's direct withdrawals of 222 million gallons of water per day from Lake Lanier. Ala. Amend. Motion for Summary Judgment, at 28. The Defendants refute this contention, arguing that the Corps’ authoritative conclusion to accommodate Georgia's water-supply request in the Water Supply Storage Assessment, the final Environmental Impact Statement, and the Record of Decision for the new Master Manual, which has now been embodied in a water-supply contract, is valid under the Water Supply Act and is entitled to significant deference from this Court.
In considering the Corps’ interpretation of its statutory authority to reallocate 254,170 acre-feet of the Buford Project's conservation pool to Georgia's water supply for direct withdrawals, the Court applies the familiar two-step analysis under Chevron, U.S.A., Inc. v. Natural Resources Defense Council, Inc. , 467 U.S. 837, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984).
[Where] Congress has directly spoken to the ... issue ... that is the end of the matter; for the court, as well as the agency, must give effect to the unambiguously expressed intent of Congress ... if the statute is silent or ambiguous with respect to the specific issue, the question for the court is whether the agency's answer is based on a permissible construction of the statute."
Id. at 842-43, 104 S.Ct. 2778. The Court begins the inquiry by determining "whether Congress had a specific intent on the precise question before us." Friends of the Everglades v. S. Fla. Water Mgmt. Dist. , 570 F.3d 1210, 1223 (11th Cir. 2009). When an agency is "charged with administering a statute, part of the authority it receives is the power to give reasonable content to the statute's textual ambiguities — in other words, the authority to fill gaps." Miami-Dade County v. U.S. EPA , 529 F.3d 1049, 1062 (11th Cir. 2008) (internal quotations and citation omitted). "Where Congress has committed the enforcement of a statute to a particular executive agency, Congress has sufficiently indicated its intent that statutory gaps be filled by the executive agency." Gonzalez v. Reno , 212 F.3d 1338, 1349 n.11 (11th Cir. 2000). Importantly, " Chevron applies equally to statutes designed to curtail the scope of agency discretion." See Arlington v. F.C.C. , 569 U.S. 290, 303, 133 S.Ct. 1863, 185 L.Ed.2d 941 (2013).
The Court agrees with the Defendants that Congress gave the Corps supplemental authority in the Water Supply Act to modify Corps’ projects to provide storage for municipal and industrial water supply, so long as adding the modifications would not cause a "major structural or operational change" from the structures and operations authorized by Congress or "seriously affect" the congressionally authorized project purposes. 43 U.S.C. § 390b(e). The Water Supply Act provides:
Modifications of a reservoir project heretofore authorized, surveyed, planned, or constructed to include storage as provided in subsection (b) of this section which would seriously affect the purposes for which the project was authorized, surveyed, planned, or constructed, or which would involve major structural or operational changes shall be made only upon the approval of Congress as now provided by law.
43 U.S.C. § 390b(e). Although the statute specifies that the Corps should seek congressional authorization before approving a modification that involves major operational changes to or seriously affects the purposes of a federal project, the statute does not define those key terms. Terms like "major" and "seriously affect" are vague, expansive terms that are subject to any number of reasonable constructions. See Teva Pharmaceuticals USA, Inc. v. U.S. Food and Drug Administration , 514 F.Supp.3d 66, 97–101 (D.D.C. 2020) (deferring to the agency's interpretation of the term "protein" because the term was undefined and open to multiple definitions).
In U.S. v. Mead Corp. , 533 U.S. 218, 229, 121 S.Ct. 2164, 150 L.Ed.2d 292 (2001), the United States Supreme Court recognized that the ability to speak with the force of law can exist absent an express delegation. Where a statute is ambiguous, the agency's interpretation is entitled to "controlling weight" as long as that interpretation is reasonable. National Ass'n of State Utility Consumer Advocates v. F.C.C. , 457 F.3d 1238, 1253 (11th Cir. 2006) (internal quotations omitted). This lenient standard requires deference "even if the agency's reading differs from what the court believes is the best statutory interpretation." Arevalo v. U.S. Atty. Gen. , 872 F.3d 1184, 1195 (11th Cir. 2017) (internal quotations and citations omitted). To be reasonable, an interpretation need only be "rational and consistent with the statute." In re Gateway Radiology Consultants, P.A. , 983 F.3d 1239, 1256 (11th Cir. 2020) (internal quotations and citations omitted).
Deference is especially appropriate where, as here, a statute contains significant gaps calling for an agency's technical judgment. In these situations, "a full understanding of the force of the statutory policy depends upon more than ordinary knowledge" of the situation confronting the agency. E.P.A. v. EME Homer City Generation L.P. , 572 U.S. 489, 513, 134 S.Ct. 1584, 188 L.Ed.2d 775 (2014) (internal quotations and citations omitted). Agencies are in a far better position to address questions than courts are, where those questions are technical, complex, and dynamic. See Nat'l Cable and Telecoms. Ass'n v. Brand X Internet Servs. , 545 U.S. 967, 1002-03, 125 S.Ct. 2688, 162 L.Ed.2d 820 (2005). "Particular deference is accorded to the informed discretion of the responsible federal agencies where issues of science, technical expertise or complex environmental statutes are involved." Fla. Keys Citizens Coal., Inc. v. U.S. Army Corps of Eng'rs , 374 F. Supp. 2d 1116, 1127 (S.D. Fla. 2005). Courts must be "extremely deferential when an agency's decision rests on the evaluation of complex scientific data within the agency's technical expertise." Defenders of Wildlife v. Bureau of Ocean Energy Mgmt. , 684 F.3d 1242, 1250 (11th Cir. 2012) (internal quotations and citations omitted).
Thus, "the administering agency's construction is to be accorded controlling weight unless ... arbitrary, capricious, or manifestly contrary to the statute." E.P.A. v. EME Homer City Generation, L.P. , 572 U.S. 489, 513, 134 S.Ct. 1584, 188 L.Ed.2d 775 (2014) (internal quotations and citations omitted). The analysis of agency action under Chevron step two and arbitrary and capricious review is often "the same, because under Chevron step two, [the court asks] whether an agency interpretation is arbitrary or capricious in substance." Judulang v. Holder , 565 U.S. 42, 52 n.7, 132 S.Ct. 476, 181 L.Ed.2d 449 (2011) (internal quotations and citations omitted). "The scope of review under the ‘arbitrary and capricious’ standard is narrow and a court is not to substitute its judgment for that of the agency." Motor Vehicle Mfrs. Ass'n of U.S. , 463 U.S. at 43, 103 S.Ct. 2856.
Here, the Plaintiff fails to show that the Corps’ decision under the Water Supply Act was either arbitrary or capricious. And even if the Corps’ decision was not entitled to substantial deference from this Court, the Corps’ determination was also correct and reasonable on its own terms. Alabama argues that the Water Supply Act barred the Corps from reallocating the direct withdrawal storage without congressional approval because the reallocation "involve[s] major structural or operational changes" to an existing reservoir and "seriously affect[s] the purposes for which the project was authorized." 43 U.S.C. § 390b(e). The Defendants refute this contention, arguing that the Corps’ conclusion that it can accommodate Georgia's water supply request under the Water Supply Act without congressional approval is well-reasoned and correct. The Court agrees.
In the U.S. Army Corps’ Cross-Motion for Summary Judgment, the Corps thoroughly outlines exactly how it arrived at its decision as follows. In In re MDL-1824 Tri-State Water Rights Litigation , 644 F.3d 1160 (11th Cir. 2011), the Eleventh Circuit held that water supply was an authorized use of the Buford Project. The Eleventh Circuit then instructed the Corps to reconsider the Georgia water supply request that it had erroneously denied based on lack of authority. Id. at 1192-97. In 2012, the Corps’ Chief Counsel issued a legal opinion concluding that the Corps was fully authorized to grant Georgia's request, but that an Environmental Impact Statement would need to be prepared before any decision could be made. NWF's Compl., at ¶ 89. The Corps prepared a Memorandum for the Chief of Engineers, known as the 2012 Stockdale Memo, considering the Corps’ legal authority and an accompanying analysis of the impacts of providing storage at the Buford Project for water supply. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 19-20.
In the 2012 Stockdale Memo, the Corps considered the meaning of "major" and "seriously" and concluded that those terms are a matter of degree and refer to changes and impacts that fundamentally depart from congressional intent for a project. Id. at 40-41. The Corps concluded that it would determine whether a change fundamentally departs from congressional intent by first considering the actual withdrawals from the reservoir and returns to the reservoir that are projected in the request and then considering how those actual withdrawals and returns will impact operations and project purposes. Id. at 41. After this determination, the Corps calculated the storage necessary to fulfill the request. Id. The Corps acknowledged that the size of a reallocation in terms of acre-feet of storage or percent of reservoir storage is not the proper measure for determining whether modifying a project for water supply storage will require major operational changes or seriously affect project purposes. Id. The Corps decided that calculations of storage are independent from the impacts to operations and purposes from the actual withdrawals and returns. Id.
Rather, the Corps focused on the actual changes and impacts that the withdrawals and returns necessitating the storage would involve. Id. The Corps determined that there are three operational principles at the Buford Project required under the Rivers and Harbors Acts of 1945 and 1946. Id. First, the Project was proposed and approved as one component in a system of projects and therefore must be operated as an integral part of the ACF system with system-wide operations in mind. Id. at 42. Second, the Buford Project must be operated to serve the system-wide purposes articulated by Congress. Id. Third, the authorizing legislation allows the full drawdown of the Buford Project's conservation pool to serve those system-wide authorized purposes. Id. The Corps concluded that it may add storage for water supply under the authority of the Water Supply Act so long as it makes no major change to those congressionally contemplated operations. Id.
The Corps then prepared a technical report concluding that granting Georgia's request for storage to supply up to 277 million gallons per day from the reservoir, with projected returns of 107 million gallons per day, would not result in major operational changes. Id. at 42-43. Storage to supply that yield of water would come from the existing conservation storage at the Project while leaving sufficient conservation storage to maintain operations for all other authorized purposes even during the record drought. Id. at 43. Because the storage would come entirely from the conservation pool, the Corps found that flood control operations would be unaffected. Id. at 43. Thus, in times of drought, operations would involve drawing down the pool to five feet above the minimum pool elevation for efficient hydropower operations which is a drawdown contemplated in the Newman Report. Id. at 43.
After concluding that a relocation of storage would not involve any major operational change, the Corps then considered whether any project purpose would be seriously affected by providing storage to accommodate Georgia's request. Id. at 43. Those purposes include flood control, navigation, recreation, and hydropower generation. Id. The Corps determined that flood control would be unaffected, navigation improved, and recreation impacted "within the range of drawdown" contemplated by the authorizing legislation. Id. at 43-44. Regarding hydropower, the system-wide dependable capacity for hydropower generation would be reduced by less than 1% and the value of that hydropower by 4.44% on an average annual basis. Id. at 44. The Corps determined that because the remaining capacity and value would still greatly exceed Congress’ expectations when it authorized the Buford Project, impacts to hydropower are not serious because they do not fundamentally depart from congressional expectations. Id. at 44.
After the 2012 Stockdale Memo, Georgia revised its request downward and sought a reallocation sufficient to allow the withdrawal of 222 million gallons per day from the reservoir. Id. at 44. The Corps then prepared a Water Supply Storage Assessment to "fully evaluate the potential impacts to the authorized purposes" of reallocating the requested storage amount. Id. at 44. The Water Supply Storage Assessment adopted and incorporated the 2012 Stockdale Memo's analysis of Georgia's then larger request. Id.
The Corps concluded that the proposed reallocation of 254,170 acre-feet of conservation storage in Lake Lanier to accommodate 222 million gallons per day from the reservoir is the most cost effective and timely means of satisfying the State of Georgia's projected water demands and would not involve any structural changes or major operational changes nor would it seriously affect any authorized purpose of the ACF system. Id. The Corps also found that granting Georgia's request would not require major changes to hydropower operations in the Basin. The Corps decided that it could both grant the request and conduct hydropower operations that greatly exceed the actual figures presented to Congress in the Newman Report in terms of system capacity and value. Id. at 27. The Corps then issued the Record of Decision adopting the reallocation as part of the new Master Manual. Id. at 45.
Section 301 of the Water Supply Act plainly states that a major operational change to a project falling within its scope requires prior congressional approval. Consistent with this plain text, the Corps has long recognized that its discretion to alter a project's operations without congressional approval is limited to non-major matters. Alabama argues that the Corps’ interpretation of "major operational change" and "seriously affects" is wrong. Alabama mainly supports it argument for major operational change based on the size of the reallocation, D.C. Circuit precedent, a 1970 Congressional Research Service Report, and the extensiveness of the Master Manual that accompanies the change.
Alabama's main arguments for a major operational change stem from the sheer size, 254,170 acre-feet, of the reallocation and the reallocation percentage, 23.7%, of Lake Lanier's conservation pool. Alabama focuses on Southeastern Federal Power Customers, Inc. v. Geren , 514 F.3d 1316 (D.C. Cir. 2008) where the D.C. Circuit held that a reallocation of a little over 22% of Lake Lanier's storage space constituted a major operational change for which the Water Supply Act required prior congressional approval. However, the Court agrees with the Eleventh Circuit's interpretation of the case. The Eleventh Circuit held that "it is clear that the question of whether percent reallocation of storage is the correct or sole measure of operational change was not actually litigated." In re MDL-1824 Tri-State Water Rights Litigation , 644 F.3d at 1203. Southeastern Federal Power Customers, Inc. v. Geren involved a proposed settlement agreement, with no administrative record or technical examination by the Corps of the operational changes that the agreement would necessitate. "The parties assumed, but did not put at issue, the question of whether percent reallocation of storage is the correct or sole measure of operational change." Id. Thus, the " Geren court made the same assumption in its opinion, without any discussion of the issue." Id. Nothing precluded the Corps from later determining the appropriate measure of operational change based on its own expertise.
When the Corps considered the question on remand, the Corps concluded that neither the size in acre-feet nor the percentage of storage capacity is an appropriate measure of operational change. In the 2012 Stockdale Memo, the Corps expressly rejected the proposition that the size of a reallocation is an appropriate measure of operational change under the Water Supply Act. U.S. Army Corps’ Cross-Motion for Summary Judgment, at 46. Rather, the Corps focuses on the actual, net removal of water from the reservoir including any withdrawals as well as any returns that affect operations for other authorized purposes, instead of the amount or percent of storage to which the Corps grants rights in a Water Supply Act contract. Id. The Court agrees with the Defendants that Alabama does not sufficiently show why the size of a storage reallocation in isolation gives any useful information about the operational changes of the reallocation. The Court defers to the U.S. Army Corps’ expertise in determining how to measure a major operational change.
Aside from size, Alabama mentions purported changes to the guide curve, release restriction to support recreation, and to the action zones. But the Court agrees with the Defendants that the Water Supply Act's limitations only should apply to changes to required operations by Congress in the authorizing legislation. These are not operations specified in the original project authorizations passed by Congress, and Alabama does not explain how any of the changes it points to would meet the threshold nor how the alleged changes were adopted to accommodate Georgia's water supply request.
Next, Alabama argues that the Corps’ reallocation would "seriously affect the purposes for which the project was authorized" and thus requires prior congressional approval. 43 U.S.C. § 390b(e). Alabama solely focuses on hydropower reduction, arguing that the reallocation would seriously diminish the Corps’ ability to use the Buford Project to generate power. Alabama contends that the Corps would be holding back 222 million gallons per day for Georgia's direct withdrawal, resulting in 126.5 million gallons per day less that is released through the dam's turbines and on to the other hydropower-generating projects in the basin.
Relying on a declaration of its own expert and not the projections made by the Corps, Alabama argues that hydropower generation at the Buford Project would drop by 14.48%, while system-wide generation would be down more than 4%. However, the Corps concluded that the dependable hydropower capacity throughout the system would be reduced by less than 1%, and the overall system hydropower value would decrease by 4.44%. Alabama does not contest these numbers on their own terms, but instead presents its own model.
The Court agrees with the Defendants that Alabama errs by focusing on the individual projects rather than the entire system as whole, which contradicts congressional intent for the ACF Basin. Alabama also assumes that there is a one-to-one correspondence between water withdrawn from the system and water available for other system purposes. The Corps’ analysis is both reasonable and reasonably explained. "Once we find a rational connection between the evidence and the decision, we must defer to the agency's expertise." Tackitt v. Prudential Ins. Co. of America , 758 F.2d 1572, 1575 (11th Cir. 1985).
As the Defendants explain, the numbers suggested by Alabama would still not seriously affect the hydropower purposes Congress established because the remaining hydropower generation would still far outpace congressional expectations for the project in the authorizing legislation. A reallocation cannot cause a serious effect on the hydropower purpose established by Congress where the project will still be generating significantly more hydropower than Congress expected even after the reallocation. Based on the Corps’ extensive administrative and technical record, the Court must give great deference to the Corps’ decision. The Court finds that the Corps’ decision regarding Georgia's request without congressional approval is not arbitrary or capricious, it is reasonable and reasonably explained, and deserves significant deference from this Court.
In Count II of its Complaint, Alabama alleges that the U.S. Army Corps violated the Rivers and Harbors Acts of 1945 and 1946 through unlawful abandonment and improperly elevating water supply over other project purposes. Alabama argues that the Corps has offered no assurance that the changes will not transform the Buford Project from a project Congress authorized for multiple purposes – hydropower, navigation, flood control, and downstream water supply – into a project that emphasizes the water supply purpose above the others. Alabama contends that the changes would not be in accordance with the Buford Project's original authorization under the Rivers and Harbors Acts of 1945 and 1946, would be in excess of the Corps’ authority under those statutes, and would be due to be set aside under the APA. The Court disagrees.
The Corps reasonably concluded that it can make releases to facilitate the downstream withdrawal of 379 million gallons per day from the Buford Project under the authority of the Rivers and Harbors Acts of 1945 and 1946. The Corps reasonably interpreted that the Rivers and Harbors Act of 1946 as authorizing it to make releases sufficient to meet Georgia's request for downstream water supply. The Corps’ interpretation of the extent of its discretion to operate the Buford Project for downstream water supply is entitled to deference. In In re MDL-1824-Tri-State Water Rights Litigation , 644 F.3d 1160, 1200 (11th Cir. 2011), the Eleventh Circuit held that the "authorizing legislation is ambiguous with respect to the extent of the Corps’ balancing authority – i.e., the extent of the Corps’ authority under the RHA to provide water supply for the Atlanta area." The Eleventh Circuit remanded to the Corps to reconsider Georgia's request in light of the holding that the Corps has authority to accommodate downstream water supply as an authorized purpose of the Buford Project. Thus, the Eleventh Circuit left the contours of that authority to "the agency authorized by Congress to implement and enforce" the Rivers and Harbors Act of 1946. Id.
The Corps thoroughly outlines how it arrived at its decision by examining the Newman Report and modeling the extent to which the Corps can serve downstream water supply consistent with the original authorizing legislation. See U.S. Army Corps’ Cross-Motion for Summary Judgment, at 54-55. As the Corps states, Congress did not order the priorities of the project purposes in the Rivers and Harbors Act, nor did it provide specific allocations of storage within the conservation pool to particular purposes or mandate a particular navigation channel depth. The Corps has significant discretion to balance the often competing purposes at its multi-purpose reservoirs. The Court agrees with the Defendants that Alabama makes no showing that providing for downstream withdrawals in the manner modeled by the Corps is either inconsistent with the Newman Report or will have any significant impact on any project purpose. Alabama fails to sufficiently show that the operations under the Master Manual to facilitate downstream withdrawals, by themselves, exceed the Corps’ authority under the Rivers and Harbors Acts of 1945 and 1946.
In Count IV of its Complaint, Alabama alleges violations of the National Environmental Policy Act of 1969 ("NEPA"). NEPA requires agencies to issue a detailed statement concerning the environmental impact of their significant actions. 42 U.S.C § 4332(2)(C)(i). Alabama argues that the Corps’ Environmental Impact Statement concealed the Master Manual's and Water Supply Storage Assessment's full impacts, by comparing them to the conditions that had been present under the 1989 draft manual which was not subject to NEPA review, instead of the environment as it existed when the 1958 and 1959 manuals were adopted. Alabama contends that this alleged concealment renders the Corps’ decision not "in accordance with" NEPA, and due to be "set aside" under the APA. 5 U.S.C. §§ 706(2)(A),(C).
The Court agrees with the Defendants that there is no basis for the Plaintiff's claim under NEPA. The Council on Environmental Quality's NEPA regulations require an agency to evaluate reasonable alternatives including "no action alternative." 40 C.F.R. § 1502.14(c). The Corps evaluated the updated ACF Manual against a "no action" alternative as the environment as it existed at the time that the Corps updated the manual in 1989. 40 C.F.R. § 1502.14(c). The "no action" alternative represents no change from the current management direction or level of management intensity. The "no action" alternative also represents continuation of the current water management operations of each of the Corps’ projects in the ACF Basin. The management practices are drawn from the Corps’ original 1958 master manual, project Water Control Manuals, and the 1989 Draft Water Control Plan. The Corps’ "no action" alternative considered current reservoir operations and the current level of direct withdrawals.
Congress enacted NEPA "to promote efforts which will prevent or eliminate damage to the environment and biosphere." Pub. L. 91-190, § 2, 83 Stat. 852, 852 (1970). NEPA's procedures are triggered when agencies engage in "major Federal actions significantly affecting the quality of the human environment." 42 U.S.C. § 4332(2)(C). The Court agrees with the Defendants that an agency cannot know if its proposal will significantly affect the quality of the human environment if it considers hypotheticals as opposed to realities. As the State of Georgia concludes, an agency could not fulfill NEPA's policy of preventing or eliminating damage to the environment if it can satisfy the statute by demonstrating that its projects will not cause any detriment to environmental conditions that no longer exist. Alabama also does not point to a single environmental impact that the Corps overlooked or did not disclose.
The Court agrees with the Tenth Circuit's reasoning in Custer County Action Ass'n v. Garvey , 256 F.3d 1024, 1040 (10th Cir. 2001), where the court held that the Council on Environmental Quality's intention was that agencies compare the potential impacts of the proposed federal action to the known impacts of maintaining the status quo. In Alabama's proposal, the Corps would have to describe an environment that has not existed for decades and analyze the management practice not as they actually exist but as a hypothetical set of conditions. Like many other districts, the Court holds that the interpretation of the "no action" alternative as the current level of activity used as a benchmark is correct. See Hells Canyon Alliance v. U.S. Forest Service , 227 F.3d 1170 (9th Cir. 2000) ; Northwest Envtl. Defense Center. v. U.S. Army Corps of Eng'rs , 817 F. Supp. 2d 1290 (D. Or. 2011) ; Natural Resources Defense Council, Inc. v. Hodel , 624 F. Supp. 1045, 1054 (D. Nev. 1985).
In Count V of its Complaint, Alabama alleges violations of the Administrative Procedure Act ("APA"). Alabama argues that the Master Manual and Water Supply Storage Assessment should be set aside because of the Corps’ failure to acknowledge and offer a reasoned explanation for its departure from its own water-quality policy. The Corps has maintained a policy to ensure that its project operations do not degrade water quality. The Court agrees with the Defendants that even if the Corps did not follow its guidance as Alabama alleges, the Corps adequately explained the reasons for its decision to select the preferred alternative despite potential impacts to water quality. Alabama argues that the Environmental Impact Statement revealed that the Corps’ selected alternative would degrade water quality in the Chattahoochee, and the Corps did not acknowledge that this result amounts to a deviation from its water quality policy or offer a reasoned explanation for it. Alabama argues that this failure violated the APA's mandate of reasoned decision-making, which requires an agency abandoning its precedents to at the very least acknowledge the change and to offer a reasoned explanation.
But Alabama admits that the Corps acknowledged its guidance and that the guidance had been applied in the update process. Alabama also admits that the Corps fully considered and disclosed all the relevant impacts to water quality. And Alabama admits that the Corps explained in the Environmental Impact Statement and the Record of Decision that it was adopting the preferred alternative despite the potential impact to water quality because the "substantial benefits to water supply ... outweigh the potentially adverse water quality impacts associated with increased water supply uses" and the impacts could be addressed by state regulators.
Thus, even if the Corps’ action was a departure from its guidance, the Corps adequately explained the reasons for its substantive action. The Court defers to "an agency's ultimate findings as well as drafting decisions like how much discussion to include on each topic ...." Black Warrior Riverkeeper, Inc. v. U.S. Army Corps of Eng'rs , 833 F.3d 1274, 1285 (11th Cir. 2016) (internal quotations and citations omitted). Courts even must uphold a decision of less than ideal clarity if the agency's path may be reasonably discerned. Id. Here, the Court agrees with the Defendants that the Corps adequately explained its conclusions with respect to water quality and the reasons it chose to proceed despite potential impacts to water quality.
In addition to Counts I, II, IV, and V, Alabama also requests that the Court rule on Alabama's Supplemental Complaint concerning the Corps’ January 20, 2021 execution of a Water Storage Agreement for the reallocated water storage space in Lake Lanier with the State of Georgia. Supp. Compl., [Doc. 205]. The Plaintiff's request the Court to hold the Lanier Contract unlawful or to direct the Defendants to revise or prepare a new Lanier Contract consistent with the congressionally authorized purposes of projects in the ACF Basin and with the Water Supply Act and the Corps’ regulations. Because the Court finds the Corps’ decision to be consistent with the congressionally authorized purposes of the ACF Basin and defers to the Corps’ decision under the Water Supply Act and the Rivers and Harbors Acts of 1945 and 1946, the Court denies the Plaintiff's request regarding the Lanier Contract.
Thus, the Court denies the State of Alabama's Motion for Summary Judgment [Doc. 220] and the State of Alabama's Supplemental Complaint [Doc. 205] and grants the Defendant U.S. Army Corps’ Cross-Motion for Summary Judgment [Doc. 202], the Defendant State of Georgia's Cross-Motion for Summary Judgment [Doc. 211], and the Defendant the Georgia Water Supply Providers’ Cross-Motion for Summary Judgment [Doc. 216].
B. National Wildlife Federation, Florida Wildlife Federation and Apalachicola Bay and River Keeper's Amended Motion for Summary Judgment [Doc. 219]
In the National Wildlife Federation's Complaint, the Plaintiffs move for summary judgment on Count I, alleging violations of the National Environmental Policy Act of 1969 ("NEPA"), 42 U.S.C. §§ 4321 - 4347. The Plaintiffs have "the burden of showing by a preponderance of the evidence that the agency did not comply with NEPA's procedures." Citizens for Smart Growth v. Secretary of Dep't of Transp. , 669 F.3d 1203, 1211 (11th Cir. 2012). The Council on Environmental Equality's regulations provide guidance on the steps that agencies should take to fulfill NEPA's procedural requirements. First, an agency must "briefly specify the underlying purpose and need for the proposed action." 40 C.F.R. § 1502.13. Second, if the agency considers a potential alternative but does not rigorously analyze that alternative in its environmental impact statement, the agency must briefly discuss the reasons for eliminating it "from detailed study." 40 C.F.R. § 1502.14(a). Third, the agency must discuss remaining alternatives, including the no-action alternative, "in detail ... so that reviewers may evaluate their comparative merits." 40 C.F.R. §§ 1502.14(b), (c).
The Plaintiffs allege that the Corps unreasonably narrowed the fish and wildlife conservation project purpose to limit the consideration of alternatives. First, "NEPA's only requirement regarding the Purpose and Need Statement is that it briefly specify the underlying purpose and need to which the agency is responding in proposing the alternatives including the proposed action." Citizens for Smart Growth , 669 F.3d at 1212 (internal quotations and citations omitted); C.F.R. § 1502.13. The purpose and need statement "is left to the agency's expertise and discretion, and [courts] defer to the agency if the statement is reasonable." Citizens for Smart Growth v. Peters , 716 F. Supp. 2d 1215, 1223 (S.D. Fla. 2010) (internal quotations and citations omitted). Section 1.2 of the Environmental Impact Statement states, "the purpose and need for the federal action is to determine how [Corps] projects in the ACF Basin should be operated for their authorized purposes, in light of current conditions and applicable law, and to implement those operations through updated water control plans and manuals." The Court agrees with the Defendants that the Plaintiffs have not shown the purpose and need statement is itself too narrow or otherwise arbitrary and capricious.
Next, the ACF Project's purposes are different than the "purpose and need" of the Environmental Impact Statement. The ACF Project's purposes are defined by Congress, while the purpose and need statement is developed by the agency to define the scope of a proposed action. The Plaintiffs provide no support for their argument that fish and wildlife conservation is a coequal purpose of the ACF Basin. Regardless, the Corps made reducing adverse effects on system operations on endangered species an express objective of the water management phase of the process. The Corps’ screening criteria included "Fish and Wildlife" as one of the factors used to evaluate which potential water management alternatives would be evaluated in the Environmental Impact Statement. Even if the Plaintiffs wanted the Corps to grant fish and wildlife conservation even more consideration, courts afford "considerable deference to the agency's expertise and policy-making role" in defining its objectives and grant agencies discretion to determine which purpose need they will consider. Theodore Roosevelt Conservation Partnership v. Salazar , 661 F.3d 66, 73 (D.C. Cir. 2011) (internal quotations and citations omitted).
The Plaintiffs also allege that the Corps obscured the damaging impacts of its current operations on the ACF Basin by subsuming those into a "baseline" against which to measure the impacts of its proposed action. The Plaintiffs challenge the Corps’ description of the environmental baseline regarding the "no action" alternative analyzed in the Environmental Impact Statement, arguing that the Corps’ "no action" alternative should not encompass management practices under the 1989 draft manual that was not subject to NEPA review. As previously mentioned, the Corps detailed the status of the affected environment as it existed when the Environmental Impact Statement was prepared. The Corps correctly defined the "no action" alternative as the current operations of the ACF Basin, rather than a hypothetical set of conditions that may have existed 63 years ago, and that do not represent the current status quo or management practices. The Court rejects the Plaintiffs’ proposition to require the Corps to utilize an artificial, historical baseline. Once again, the Corps’ judgment and selection of a baseline that represented no change from current management is deserving of deference, consistent with NEPA, and neither arbitrary nor capricious.
Next, the Plaintiffs allege that the Corps restricted its environmental impact analysis to largely "all-or-nothing" alternatives. The Plaintiffs argue that additional alternatives should have been considered and that the Corps’ assessment of return rates was arbitrary. NEPA requires the agency to "study, develop, and describe appropriate alternatives to recommended courses of action in any proposal which involves unresolved conflicts concerning alternative uses of available resources." 42 U.S.C. § 4332(2)(E). However, "NEPA provides little guidance in determining what alternatives must be considered." North Buckhead Civic Ass'n v. Skinner , 903 F.2d 1533, 1541 (11th Cir. 1990). The scope of alternatives is "bounded by some notion of feasibility, and consideration need be given only to reasonable, non-speculative alternatives." Id. (internal quotations and citations omitted). "Common sense ... teaches us that a detailed statement of alternatives cannot be found wanting simply because the agency failed to include every alternative device and thought conceivable by the mind of man." Citizens for Smart Growth , 716 F. Supp. 2d at 1227-28 (internal quotations and citations omitted).
An "EIS is satisfactory if the treatment of alternatives, when judged against a rule of reason, is sufficient to permit a reasoned choice among the various options." Id. (internal quotations and citations omitted). The Corps was not required to adopt or bring forward for fuller consideration the Plaintiffs’ preferred alternatives or management measures, nor was the Corps required to analyze any specific number or scope of alternatives. The Court agrees with the Defendants that the Corps’ detailed discussion of alternatives as it relates to this highly technical series of decisions, so long as it is not arbitrary and capricious, should be upheld. The Plaintiffs have not shown by a preponderance of the evidence that the Corps has not met that standard.
The Court agrees with the Defendants that the ten alternatives that the Corps considered enabled reasoned choices considering the objectives the Corps had identified. The Plaintiffs do not identify any unexamined alternative that could accomplish the Corps’ competing goals, in light of the extensive explanations that the Corps provided for its screening decisions. The Plaintiffs make no showing that the Corps’ selection of alternatives was arbitrary or capricious.
Finally, the Plaintiffs allege that the Corps failed to analyze the direct, indirect, and cumulative impacts of its actions. The Court disagrees. Agencies preparing environmental impact statements analyze among other things the indirect impacts of proposed actions. See Citizens for Smart Growth , 669 F.3d at 1212. These are defined to include the "reasonably foreseeable long-term effects of the proposed action." Id. at 1214. NEPA entrusts each agency with the task of determining both the scope of impacts addressed and the depth at which they will be addressed. This task, assigned to the special competency of the agency, "can only be overturned by a showing of arbitrariness or capriciousness." Id. at 1215.
The Corps exhaustively detailed the direct, indirect, and cumulative impacts of its proposed action. The Plaintiffs have not demonstrated that the Corps failed to sufficiently analyze any discrete environmental impact that is subject to the Corps’ control nor have they shown that the agency's discussion of impacts was arbitrary or capricious. The Corps considered indirect impacts by analyzing indirect impacts of water quality and lake levels. The Plaintiffs do not explain any further reasonably foreseeable long-term effects that the Corps should have analyzed here. The Corps considered cumulative impacts, including the ones the Plaintiffs complain about. See State of Georgia's Cross-Motion for Summary Judgment, at 47-49. To the extent that the Plaintiffs would prefer a more extensive discussion of these issues, that is not a reason to overturn the Environmental Impact Statement.
The Corps also considered mitigating measures. In addition to considering actions that the Corps could take to mitigate incidental harms throughout the Basin, the Corps considered exactly the "measures ... outside its jurisdiction." The Plaintiffs fault the Corps for punting mitigation to Georgia, but agencies can recognize that other entities are in the best position to take appropriate action. The agency need not delay adopting its preferred alternatives while those other entities choose "what mitigating measures they consider necessary." Robertson v. Methow Valley Citizens Council , 490 U.S. 332, 353, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989).
The Corps’ years-long analysis of the ACF Basin clearly meets NEPA's procedural requirement. The record does not support the Plaintiffs’ arguments for NEPA violations. The Corps reasonably defined objectives for its proposed federal action, screened potential alternatives, subjected remaining alternatives to a thorough analysis, and considered potential environmental issues and impacts on competing ACF Basin purposes. The Corps subjected its decision to public notice and comment and exercised its discretion to choose a substantive outcome. The Defendants show that each of the concerns that the Plaintiffs identify with the Corps’ process was carefully considered by the Corps and validly rejected as part of the Corps’ screening process. While the Plaintiffs may disagree with the Corps’ analysis or methodological choices, courts "can overturn an administrative decision only if there are substantial procedural flaws, and not simply because we may disagree with the decision." Druid Hills Civic Ass'n, Inc. v. Federal Highway Admin. , 772 F.2d 700, 712 (11th Cir. 1985).
Thus, the Court denies the Plaintiffs National Wildlife Federation, Florida Wildlife Federation, and Apalachicola Bay and River Keeper's Motion for Summary Judgment [Doc. 219] and grants the Defendant U.S. Army Corps’ Cross-Motion for Summary Judgment [Doc. 203], the Defendant State of Georgia's Cross-Motion for Summary Judgment [Doc. 213], and the Defendant the Georgia Water Supply Providers’ Cross-Motion for Summary Judgment [Doc. 218].
IV. Conclusion
The ACF Basin Master Water Control Manual Update assures a dependable supply of water from Lake Lanier and the Chattahoochee River to the Atlanta Metropolitan region through the year 2050. It does so without significant sacrifices to environmental standards, and recognizes the need to maintain other uses of the ACF system such as flood control, hydropower generation, fish and wildlife conservation, navigation and recreation. The effect upon the Apalachicola River and Bay will be negligible. The decision was not arbitrary or capricious. The Plaintiffs have not met their burden of showing that this delicate balance should be upset. In the absence of an agreement among Georgia, Florida and Alabama, there is no better alternative. Decades of deferral and delay due to litigation should end. For the reasons stated above, the Court DENIES the Plaintiff State of Alabama's Motion for Summary Judgment and Amended Motion for Summary Judgment [Doc. 164, 220], DENIES the Plaintiff National Wildlife Federation, Florida Wildlife Federation, and Apalachicola Bay and River Keeper's Motion for Summary Judgment and Amended Motion for Summary Judgment [Doc. 165, 219], GRANTS the Defendant U.S. Army Corps of Engineers’ Cross-Motions for Summary Judgment [Doc. 202, 203], GRANTS the Defendant State of Georgia's Cross-Motions for Summary Judgment [Doc. 211, 213] and GRANTS the Defendant Georgia Water Supply Providers’ Cross-Motions for Summary Judgment [Doc. 216, 218].
SO ORDERED, this 11 day of August, 2021.
APPENDIX A
APPENDIX A
RECORD OF DECISION
Apalachicola-Chattahoochee-Flint River Basin Master Water Control Manual Update and Water Supply Storage Assessment Alabama, Florida, and Georgia
The Final Environmental Impact Statement (FEIS) dated December 16, 2016, for the Apalachicola-Chattahoochee-Flint (ACF) River Basin Master Water Control Manual (WCM) Update and Water Supply Storage Assessment (WSSA) addresses the operation of the five federal dam and reservoir projects in the ACF Basin, comprising 19,573 square miles in Alabama, Florida, and Georgia, authorized by the Rivers and Harbors Act of 1946, Section 1 Public Law (P.L.) No. 79-525, 60 Stat. 634 (1946) (1946 RHA) and subsequent legislation. The Proposed Action Alternative (PAA) is contained in the FEIS, dated December 16, 2016. Based on the FEIS, the ACF River Basin Master WCM Update, the WSSA, the reviews by other Federal, State, and local agencies, Native American Tribes, input from the public, and the review by my staff, I find the plan recommended by the Chief of Engineers through the Director of Civil Works, Alternative 7K, to be technically feasible, in accordance with environmental and other applicable statutes, and the alternative that best serves the overall public interest.
The FEIS, incorporated herein by reference, evaluated various alternatives that would meet the purpose and need of determining how the U.S. Army Corps of Engineers (USACE) projects in the ACF Basin should be operated for their authorized purposes, in light of current conditions and applicable law, and to implement those operations through updated water control plans and manuals. The original Master WCM for the ACF system was published in 1958. WCMs for individual projects were developed later, as the federal ACF projects were constructed. However, due to disputes and litigation spanning several decades involving the ACF Basin States of Alabama, Florida, and Georgia, the Master WCM has not been updated since its original publication. Additionally, USACE has not made a final decision regarding the allocation of storage in Lake Lanier to accommodate current and future water supply withdrawals, the subject of multiple requests by the State of Georgia and a 2011 ruling by the U.S. Court of Appeals for the Eleventh Circuit (the Eleventh Circuit). USAGE has operated the ACF system of projects in accordance with the status quo reflected in a draft 1989 Master WCM update, and with interim operating plans pursuant to section 7 consultation of the Endangered Species Act (ESA) of 1973 (P. L. 93-205) with respect to releases from Jim Woodruff Dam. The FEIS evaluates the impacts throughout the ACF Basin, including the Apalachicola River and Apalachicola Bay, of system operations under an updated master WCM for purposes including flood risk management, hydropower, navigation, fish and wildlife conservation, recreation, water quality, and water supply.
The PAA (Alternative 7K) would update the Master WCM and individual project water control plans to operate the federal projects as a balanced and integrated system to meet all authorized project purposes in the ACF Basin, and would formally accommodate current and projected water supply uses of Lake Lanier in response to the 2011 Eleventh Circuit decision and the State of Georgia's revised (2015) request. It would also conform to the terms and conditions of a Biological Opinion issued by the U.S. Fish and Wildlife Service (USFWS) on September 14, 2016, in compliance with the ESA. The PAA (Alternative 7K) includes the following key water management measures and other features:
• Maintains current guide curves for the storage reservoir projects (Lake Lanier, West Point Lake, and Walter F. George Lake), without structural changes to any project.
• Revises action zones—specific elevation ranges of reservoir pools that govern operational decisions when surface elevations are within each zone—to promote more effective use of conservation storage throughout the system to meet authorized purposes in consideration of numerous factors, including the ability of the reservoirs to refill (considering hydrology, watershed size, and physical constraints of each reservoir), recreation impacts and hazard levels, and the proportionality of zone drawdown between projects.
• Updates and formally incorporates into the WCM a basin-wide drought operations plan that would be initiated in response to declining levels of composite conservation storage in the ACF system, enabling USACE to operate the system more effectively under drought conditions such as those that have been experienced in the basin since the original Master WCM was issued. Specific minimum releases from Jim Woodruff Lock and Dam would be determined in relation to levels of composite conservation storage in the ACF Basin projects, and normal minimum release and maximum fall rate provisions could be suspended until composite conservation storage in the basin could be replenished to a level that could support them. Plans and priorities would be established for project operations requiring the use of available inactive storage in the projects should composite conservation storage be fully depleted during an exceptional drought in the future.
• Maintains current flood risk management operations, with no reduction in flood control storage at any project.
• Updates hydroelectric power generation operations to provide for a more flexible generation schedule in all action zones under non-drought conditions and a more constrained generation schedule under drier conditions.
• Provides a predictable, navigation channel with a minimum depth of seven feet in the Apalachicola River from Apalachicola, Florida to Columbus, Georgia, for four to five consecutive months each year (January— April/May), subject to hydrologic conditions in the ACF Basin.
• Maintains the current basin inflow computation method to inform water management operations.
• Prescribes operations at Jim Woodruff Lock and Dam to support federally-listed species in the Apalachicola River (Gulf sturgeon and three mussel species) in accordance with the 2016 Biological Opinion. Operations include minimum releases from Jim Woodruff Dam of 5,000 cubic feet per second (cfs) and maximum ramping rates (vertical changes in water surface elevation over time) downstream of Jim Woodruff Lock and Dam. Ramping rates would be suspended, and minimum flows reduced to 4,500 cfs, during drought operations and under prolonged low flow conditions, in accordance with the drought operations plan and Biological Opinion.
• Continues current reservoir and river fish spawn standard operating procedures.
• Continues current fish passage lockage procedures at Jim Woodruff Lock and Dam.
• Continues current operations and opportunities for recreation.
• Maintains existing releases to help meet minimum flow requirements for water quality from Buford Dam and West Point Dam, including minimum releases of 675 cfs from West Point Dam, and releases from Buford Dam, in conjunction with Georgia Power Company operations at Morgan Falls Dam and the Atlanta Regional Commission, to support a continuous seasonal minimum flow of 650 cfs (November — April) and 750 cfs (May — October) in the Chattahoochee River at Atlanta, just upstream of the confluence with Peachtree Creek.
• Accommodates current levels of water supply withdrawals from Lake Lanier under existing agreements (20 million gallons per day (mgd)).
• Allows for the reallocation of 254,170 acre-feet of conservation storage in Lake Lanier sufficient to accommodate gross water supply withdrawals of 222 mgd from Lake Lanier as requested by the State of Georgia by the year 2050, in response to the 2011 Eleventh Circuit decision. This reallocation would be contingent on executing a water supply storage agreement, by which the State of Georgia would agree to pay for the cost of storage in Lake Lanier, and by which USACE would agree to accommodate both current and future uses of that storage pursuant to the Water Supply Act of 1958.
• Provides for releases from Buford Dam sufficient to support downstream water supply withdrawals between the Dam and Peachtree Creek up to the estimated year 2050 need of 379 mgd, while also meeting other downstream release requirements, pursuant to the 1946 RHA.
Background and Alternative Formulation Process
The Federal ACF system, extending from the headwaters of Lake Lanier in the upper ACF basin to the intersection of the Apalachicola River and the Gulf Intracoastal Waterway (GIWW) 5.9 miles upstream of Apalachicola Bay, comprises five federal dam and reservoir projects: Buford Dam/Lake Lanier, West Point Dam and Lake, Walter F. George Lock and Dam and Lake, George W. Andrews Lock and Dam and Lake, and Jim Woodruff Lock and Dam/Lake Seminole. As noted above, the ACF Master WCM has not been formally updated since its issuance in 1958, and USACE has been operating the federal projects in the ACF system pursuant to a draft 1989 WCM and interim operational plans for ESA purposes. Additionally, water supply withdrawals from Lake Lanier have continued since 1990, when previous water supply contracts (with the exception of two relocation agreements, entered into as compensation for the relocation of existing facilities during dam construction) expired and litigation regarding water supply uses commenced. The present effort to update the ACF WCM began at the direction of the Secretary of the Army in January 2008, following the expiration of the congressionally-authorized ACF River Basin Compact (P.L. 105-104). After soliciting comment and holding a series of public meetings, USACE issued a Final Scoping Report in January 2009 stating the purpose of bringing the WCM up to date to reflect then-current operations and conditions. This included ongoing water supply uses of Lake Lanier that were considered, as explained in a 2009 legal opinion from the USACE Chief Counsel (2009 Chief Counsel Opinion), to be within USACE authority to approve under the Water Supply Act of 1958, 43 U.S.C. § 390b.
In July 2009, the United States District Court for the Middle District of Florida issued an opinion concluding that then-current water supply withdrawals and releases from Lake Lanier were unauthorized by either the 1946 RHA or the Water Supply Act, and issued an injunction ordering cessation of those withdrawals and releases within three years. Accordingly. USACE sought public comment and released a revised scoping report in March 2010, acknowledging the requirement to comply with the court order in any updated WCM. In 2011, the Eleventh
Circuit reversed the district court decision and instructed USACE to reevaluate its authority to accommodate water supply under the combined authority of the 1946 RHA, a 1956 statute (P.L. 84-841, July 30, 1956) ("1956 Act") amending the 1946 RHA, and the Water Supply Act. The 2011 Eleventh Circuit decision led to reconsideration of the Department of the Army's denial of an earlier request by the State of Georgia for storage in Lake Lanier to meet future water supply needs. The USACE's Chief Counsel prepared a legal and technical analysis and submitted a legal opinion (2012 Chief Counsel Opinion) to the court in June 2012, setting forth the USACE view that it has authority under the aforementioned statutes to accommodate the State of Georgia's current and requested future water supply uses of Lake Lanier. Specifically, the 2012 Chief Counsel Opinion, in consideration of the 2011 Eleventh Circuit decision, concluded that USACE is authorized under the 1946 RHA to make increasing releases from Buford Dam (Lake Lanier) to accommodate increasing water supply withdrawals downstream at Atlanta, and that USACE has additional, discretionary authority under the Water Supply Act to reallocate storage for additional withdrawals from Lake Lanier. Accordingly, USACE once again sought public comment and issued an Updated Scoping Report in March 2013, clarifying that the WCM update process would include consideration of the State of Georgia's water supply request under the 1946 RHA, the Water Supply Act, and other applicable laws, consistent with the 2011 Eleventh Circuit decision and 2012 Chief Counsel Opinion.
Although the scope of the water supply alternatives that may practically be considered has changed several times due to court decisions and legal opinions since 2008, throughout the WCM update process, USACE has consistently identified the goal of updating its operations to reflect current conditions and comply with applicable law, including the ESA. As discussed below, the FEIS evaluated a range of alternatives that reflect the best USACE engineering judgment applied to the operations of the ACF system, and encompasses a range of water supply operations responsive to the State of Georgia's request. The FEIS fully evaluates the reasonably expected effects of each alternative on authorized purposes and the human environment. The FEIS responds to many specific issues raised by the public during the public review process. USACE recognizes that there is continued disagreement among the States of Alabama, Florida, and Georgia regarding the allocation of waters in the ACF Basin, and USACE has continually asserted its preparedness to implement, in accordance with federal law, any comprehensive water allocation formula that the States of Alabama. Florida, and Georgia could agree upon. Updating the Master WCM would not preclude USACE from adjusting its operations in response to such an agreement. Following implementation of the updated WCM, the WCMs could be revised, and additional analysis conducted pursuant the National Environmental Policy Act of 1969 (NEPA) (P.L. 91-190) and other documentation prepared as necessary, in the event the States reach agreement or Congress or the federal courts take action that could implicate the USACE operation of the ACF system.
The alternative formulation process for the ACF Master WCM Update consisted of two phases, responsive to the need to update operations to reflect current conditions under the project authorization and other applicable laws, as well as the need to evaluate the State of Georgia's request that USACE exercise its discretionary authority to formally accommodate current and future water supply withdrawals from Lake Lanier and downstream at Atlanta. The first phase focused on updating and improving overall system operations, and the second phase focused on alternatives related to the State of Georgia's water supply request. In both phases, only alternatives that were considered feasible in light of current conditions and facilities, and compliant with existing law, were carried forward for full consideration.
In the first phase, water management measures—that is, guidelines for storing or releasing water to meet individual water management goals—were developed, screened, and subsequently combined to form system-wide water management alternatives, each meeting the authorized purposes of the ACF system. (See FEIS Volume 1, Table ES-2; FEIS Volume
1, Section 4.3.) In developing these water management measures, USACE relied upon its technical staff expertise, as well as input from the public received in response to scoping reports, at stakeholder workshops, and in other communications, to update operations to better accomplish the purposes of the ACF system in light of current conditions. Water management measures that were incompatible with USACE authority or the physical limitations of existing infrastructure were not carried forward, as they would not meet the purpose and need of updating the operations of the ACF system in light of current conditions and applicable law. USACE identified seven different sets of water management measures— current water management operations, and six alternatives—that it believed would achieve the authorized purposes of the ACF system within existing authorities and physical infrastructure, comply with legal requirements including ESA obligations, avoid increased risk to public safety, and respond to contemporary water resource needs in the basin to the extent practicable. These water management alternatives were evaluated using the USACE Hydrologic Engineering Center-Reservoir System Simulation (HEC ResSim) modeling software and ranked based on performance metrics aligned with ACF project purposes of navigation, hydropower, recreation, fish and wildlife conservation, and water supply. In this modeling, only current water supply withdrawals from Lake Lanier under existing relocation agreements (20 mgd) and current water supply withdrawals from the Chattahoochee River downstream at Atlanta (277 mgd) were considered, in order to identify water management operations that would best serve authorized purposes before consideration of additional water supply storage in Lake Lanier. Water Management Alternative 7, including revised action zones, a new drought operations plan, modified hydropower generating schedules, and a more dependable navigation channel, along with maintaining current guide curves and other operations for minimum flows and support to federally listed threatened and endangered species, had the highest composite ranking with respect to the authorized purposes.
In the second phase of the alternative formulation process, water supply options were developed and screened to address current and future water supply withdrawals from Lake Lanier and from the Chattahoochee River downstream at Atlanta, up to and including future needs set forth in the State of Georgia's revised (2015) request. The consideration of water supply involved two separate objectives, reflecting different statutory authorities recognized in the 2011 Eleventh Circuit decision and 2012 Chief Counsel opinion: (1) accommodating current and future water supply withdrawals downstream of Buford Dam as provided under the 1946 RHA, and (2) determining whether and in what amount to reallocate storage to accommodate current and future water supply withdrawals from Lake Lanier. This second phase of the alternative formulation process identified an array of water supply options that were then combined with either Water Management Alternative 1 (current water management operations) or Water Management Alternative 7 (revised water management operations) to produce water management/water supply alternatives for detailed evaluation and impact analysis in the Draft Environmental Impact Statement (DEIS) and FEIS. The evaluation of water supply alternatives proceeded from a baseline of 20 mgd withdrawn from Lake Lanier and 277 mgd withdrawn from the Chattahoochee River at Atlanta: that is, withdrawals that are both authorized under existing relocation contracts at Lake Lanier (20 mgd), and that are currently made with the support of releases from Lake Lanier under the authority of the 1946 RHA (277 mgd). The baseline of 20 mgd from Lake Lanier and 277 mgd at Atlanta was incorporated into the "no action" alternative (Alternative 1A) and Alternative 7B, described below. Every other alternative developed in the second phase included varying assumed amounts of withdrawals from Lake Lanier, withdrawals at Atlanta, and return flows into Lake Lanier and downstream, all within ranges previously determined by the 2012 Chief Counsel Opinion to be within the USACE authority to accommodate under the 1946 RHA, the 1956 Act, and the Water Supply Act, based on estimated impacts to authorized purposes. By developing this broad range of alternatives, USACE was able to fully evaluate the impacts to
the human environment of updating ACF system operations and of granting, denying, or granting in part the State of Georgia's water supply request.
USACE also prepared a WSSA to more fully evaluate the potential impacts to the authorized purposes of the ACF system of reallocating storage in Lake Lanier under the authority of the Water Supply Act. (See FEIS Volume 3, Appendix B.) This WSSA examined in greater detail the water supply withdrawals to be accommodated under the PAA; more specifically, 242 mgd in withdrawals from Lake Lanier, including a reallocation of 254,170 acre-feet of storage in Lake Lanier to accommodate 222 mgd beyond the 20 mgd currently withdrawn under relocation contracts, and 379 mgd in withdrawals downstream at Atlanta, for a total of 621 mgd by 2050. The PAA was specifically compared to the "future without project condition" alternative, Alternative 7J, which projected future withdrawals from Lake Lanier (20 mgd) and downstream at Atlanta (379 mgd) if USACE did not reallocate storage for either current or future withdrawals from Lake Lanier. This comparison enabled USACE to document the specific effects of reallocating storage under the supplemental authority of the Water Supply Act. As documented in the FEIS and the WSSA, USACE also considered other potential means of addressing the State of Georgia's projected water supply needs, including conservation, groundwater, desalination, new nonfederal reservoirs, existing surface water sources (other than Lake Lanier), and reallocation of flood risk management storage or inactive storage in Lake Lanier. The WSSA concluded that the proposed reallocation of 254,170 acre-feet of conservation storage in Lake Lanier is the most cost effective and timely means of satisfying the State of Georgia's projected water demands. The WSSA and FEIS demonstrate that the PAA would not involve any structural changes or major operational changes, nor would it seriously affect any authorized purpose of the ACF system, whether compared against the "no action" alternative (Alternative 1A) or the future without project condition alternative modeled for purposes of the WSSA (Alternative 7J).
However, since the early 1970s, the Gainesville contract has been understood to place a limitation on net, rather than gross, daily withdrawals, recognizing that Gainesville returns treated wastewater to Lake Lanier along with withdrawals it makes for water supply.
Summary of Alternatives Considered in the FEIS
Including the "no action" alternative and the PAA, a total of 10 alternatives underwent detailed evaluation in the FEIS, as follows:
• Alternative 1A (the no action alternative): This alternative consists of the continuation of current water management operations (i.e., operations under the 1989 draft manual and 2012 Revised Interim Operations Plan) and the status quo of water supply in the Atlanta region, including withdrawals from Lake Lanier under relocation contracts (20 mgd); continuation of gross water supply withdrawals of 108 mgd from Lake Lanier (with no reallocation of storage to formally support the withdrawals); and releases from Buford Dam to support current downstream withdrawals from the Chattahoochee River of 277 mgd.
This alternative assumed the continuation of current water supply return rates to Lake Lanier of 29 percent and to the Chattahoochee River of 82 percent.
• Alternative 1L: This alternative consists of the continuation of current water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); reallocation of storage in Lake Lanier sufficient to provide gross water supply withdrawals of 108 mgd from Lake Lanier; and releases from Buford Dam to support downstream withdrawals of the estimated 2050 need of 379 mgd. This alternative assumed water supply return rates to Lake Lanier of 29 percent and to the Chattahoochee River of 95 percent.
• Alternative 7A: This alternative consists of improved water management operations (i.e., revised water management operations under Water Management Alternative 7); withdrawals from Lake Lanier under relocation contracts (20 mgd); reallocation of storage in Lake Lanier sufficient to provide gross water supply withdrawals of 108 mgd from Lake Lanier, and releases from Buford Dam to support current downstream withdrawals of 277 mgd. This alternative assumed water supply return rates to Lake Lanier of 29 percent and to the Chattahoochee River of 82 percent.
• Alternative 7B: This alternative consists of improved water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); and releases from Buford Dam to support current downstream withdrawals of 277 mgd. This alternative assumed water supply return rates to Lake Lanier of 50 percent and to the Chattahoochee River of 82 percent.
• Alternative 7H: This alternative consists of improved water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); reallocation of storage in Lake Lanier sufficient to provide gross water supply withdrawals of 165 mgd from Lake Lanier; releases from the proposed Glades Reservoir to provide 40 mgd of the State of Georgia's 2013 request; and releases from Buford Dam to support downstream withdrawals of the estimated 2040 need of 408 mgd. This alternative assumed water supply return rates to Lake Lanier of 40.4 percent and to the Chattahoochee River of 94 percent. This alternative was the proposed action alternative identified in the DEIS. This was the only alternative carried forward to the FEIS that included the proposed Glades Reservoir. Although the Glades Reservoir was subsequently removed from the State of Georgia's water supply proposal and eliminated from the FEIS as no longer reasonably foreseeable, Alternative 7H was carried forward to clearly illustrate the different environmental impacts between this previously proposed alternative and the PAA for the FEIS.
• Alternative 7I: This alternative consists of improved water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); reallocation of storage in Lake Lanier sufficient to provide gross withdrawals of 205 mgd from Lake Lanier, and releases from Buford Dam to support downstream withdrawals of the estimated 2050 need of 379 mgd. This alternative assumed water supply return rates to Lake Lanier of 40.4 percent and to the Chattahoochee River of 95 percent.
• Alternative 7J: This alternative consists of improved water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); and releases from Buford Dam to support downstream withdrawals of the estimated 2050 need of 379 mgd. This alternative assumed water supply return rates to Lake Lanier of 50 percent and to the Chattahoochee River of 95 percent. This alternative was the future without project condition alternative that served as the basis for comparison to the PAA in the WSSA.
• Alternative 7K (the PAA): This alternative consists of improved water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); reallocation of storage in Lake Lanier sufficient to provide gross water supply withdrawals of 222 mgd from Lake Lanier; and releases from Buford Dam to support downstream withdrawals of the estimated 2050 need of 379 mgd. This alternative assumed water supply return rates to Lake Lanier of 43 percent and to the Chattahoochee River of 95 percent.
• Alternative 7L: This alternative consists of improved water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); reallocation of storage in Lake Lanier sufficient to provide gross water supply withdrawals of 108 mgd from Lake Lanier; and releases from Buford Dam to support downstream withdrawals of the estimated 2050 need of 379 mgd. This alternative assumed water supply return rates to Lake Lanier of 29 percent and to the Chattahoochee River of 95 percent.
• Alternative 7M: This alternative consists of improved water management operations; withdrawals from Lake Lanier under relocation contracts (20 mgd); reallocation of storage in Lake Lanier sufficient to provide gross water supply withdrawals of 165 mgd from Lake Lanier; and releases from Buford Dam to support downstream withdrawals of the estimated 2050 need of 379 mgd. This alternative assumed water supply return rates to Lake Lanier of 40.4 percent and to the Chattahoochee River of 95 percent.
Each of the alternatives to the "no action" alternative, other than Alternative 1L, would include improved water management operations for authorized purposes, including revised action zones to more effectively manage storage throughout the system, a new drought operations plan to respond to adverse hydrologic conditions, more flexible hydropower operations during non-drought conditions, and a more reliable, seasonal navigation channel. None of the alternatives would reduce current levels of flood risk management, and all would conform to an applicable Biological Opinion to comply with the ESA. The alternatives do not differ substantially in their overall environmental impacts. Specifically, none of the alternatives would have more than negligible overall effects on flow conditions, salinity, or fish and aquatic resources in the Apalachicola River and Bay. Instead, the principal difference among the alternatives is the amount of water supply withdrawals and wastewater returns that would be made at Lake Lanier and downstream at Atlanta, and the effects of the alternatives differ most notably in the upper Chattahoochee reach of the system.
Alternative 7K was selected as the PAA. Alternative 7K would satisfy the purpose and need by improving system water management operations, and responding to the State of Georgia's water supply request by accommodating current and future withdrawals from Lake Lanier and from the Chattahoochee River downstream at Atlanta. (See FEIS Volume 1, Section 1.2.) The PAA would provide balanced support to all authorized purposes and manage the basin as an integrated system, without major structural or operational changes and without seriously affecting ACF authorized purposes. The PAA would implement a new drought operations plan to improve the resilience of the system during drought, including additional operational restrictions to conserve storage during extended low flow conditions. Although drought operations would be triggered earlier, and would therefore occur more frequently under the PAA, this would have no effect on the climatologic drought conditions, and would reduce the severity of extended low flow conditions resulting from the climatological drought condition compared to the "no action" alternative. The PAA would incorporate the terms and conditions and reasonable and prudent measures set forth in the 2016 Biological Opinion to minimize take and avoid jeopardy to listed threatened and endangered species in the Apalachicola River and Bay, and the PAA would have no more than negligible effects overall on flow conditions in the
Apalachicola River, or water quality, salinity, and fish and aquatic resources in the River or Bay. Compared to the "no action" alternative, the PAA would have substantially beneficial effects on navigation, and impacts to hydroelectric power generation would be negligible. Recreation would experience slightly adverse effects at Lake Lanier and Walter F. George Lake and slightly beneficial effects at West Point Lake. The PAA would result in slightly adverse to adverse effects on lake levels and land use at Lake Lanier and Walter F. George Lake, and slightly beneficial effects on lake levels at West Point Lake. Effects on flow conditions below Buford Dam would be slightly beneficial, and effects on flow conditions between Morgan Falls Dam and Walter F. George Dam and between Walter F. George and Jim Woodruff Lock and Dam would be slightly adverse.
Some water quality and riverine and aquatic resources parameters indicated slightly adverse to substantially adverse effects, primarily in the upper reach of the Chattahoochee River, associated with increased wastewater discharges that were projected to occur along with increased water supply withdrawals in the upper Chattahoochee River reach under the PAA. Specifically, the effects on the water quality measures of median total dissolved oxygen, phosphorus, and nitrogen, would be slightly to substantially adverse in certain reaches of the ACF Basin under the PAA, and effects on riverine fish and aquatic resources in the upper and middle Chattahoochee reaches would be slightly to substantially adverse, due to the water quality changes. (See FEIS Volume 1, Section 6.5.3 and Tables 6.1-18, 6.1-21, and 6.1-22.) The water quality impacts projected in the upper and middle Chattahoochee reaches would not be expected to extend to the Apalachicola River and Bay, where effects on riverine and estuarine fish and aquatic resources would be negligible. Although the FEIS projected adverse water quality impacts associated with increased wastewater returns, it is likely that dischargers would be required to reduce pollutant loads under new National Pollutant Discharge Elimination System (NPDES) permits that would be required for such discharges, to avoid degradation under the Clean Water Act (CWA) (P.L. 92-500). As noted by the Georgia Environmental Protection Division (GaEPD) in a letter dated February 1, 2017, GaEPD would require reductions in concentrations of pollutants when necessary to maintain compliance with water quality standards, and so the adverse water quality effects presented in the FEIS may be overstated. Even taking into account the adverse impacts to water quality projected under the FAA, the overall impacts to the biological and physical environment and to historic, cultural, and natural resources would not be substantially adverse, nor would those impacts differ substantially from any of the alternatives evaluated in the FEIS. (See FEIS, Volume 1, Table ES-6.) Of all the alternatives that fully met both the water management and water supply objectives, the PAA would have the least overall adverse effects on lake levels, stream flow conditions, water quality, and other natural resource and socioeconomic resource considerations.
Alternative 7A consisting of improved water management operations and current levels of water supply withdrawals, has been identified as the "environmentally preferable" alternative since it would, for a limited time, meet the water management and water supply objectives while causing the least damage to the biological and physical environment. However, Alternative 7A would not meet the purpose and need with respect to future water supply needs, which would not be accommodated. Under Alternative 7A, only current water supply withdrawals of 128 mgd from Lake Lanier and 277 mgd from the Chattahoochee River downstream would be accommodated, without provision for increased withdrawals over time. Alternative 7A would be expected to have fewer adverse impacts than those associated with the PAA due to the lesser amount of wastewater returns that were modeled in the upper Chattahoochee River reach. (See FEIS, Volume 1, Section 6.) Apart from water quality in specific reaches, environmental impacts to the remainder of the ACF Basin did not differ substantially between Alternative 7A and the PAA. Moreover, as noted above, those adverse water quality impacts may not fully materialize with increased withdrawals under the PAA, since new NPDES permits may result in
reduced concentrations of pollutants. Alternative 7A was not chosen as the PAA because, although it would satisfy the water management objectives and meet current water supply needs with lesser projected adverse water quality impacts, it would not satisfy the objectives for meeting future water supply needs. (See FEIS, Volume 1, Sections 5.1 and 6.5.1.) Specifically, Alternative 7A would not accomplish the authorized purpose of accommodating future, increased downstream water supply withdrawals as provided for under the 1946 RHA, nor would it address the State of Georgia's future water supply needs from Lake Lanier, in response to the 2011 Eleventh Circuit decision. The substantial benefits to the water supply purpose under the PAA were determined to outweigh the potentially adverse water quality impacts associated with increased water supply uses, in the upper Chattahoochee reaches where those impacts were projected to occur.
All practicable means to avoid or minimize adverse environmental effects and environmental harms were analyzed and incorporated into the recommended plan. Best management practices (BMPs) as detailed in the FEIS will be implemented to minimize impacts. The only substantially adverse effects of the PAA would be due to potential increased wastewater discharges by municipal wastewater treatment facilities in the Atlanta region. These increased wastewater discharges are directly related to increased withdrawals for water supply in the Atlanta region. The FEIS identifies these potential substantial adverse effects, but recognizes that increased wastewater discharges may result in dischargers being required to reduce pollutant loads under new NPDES permits to avoid degradation under the CWA, The increased wastewater discharges would not be made by USACE and would not be caused by reservoir operations, and concentrations of pollutants would likely be reduced in future NPDES permits issued by GaEPD to maintain compliance with water quality standards. Other adverse effects identified in the FEIS for the PAA and other alternatives on flow conditions, land use, socioeconomic considerations, and other resource areas are generally slight or negligible. None of those effects rise to a level of significance compared to the "no action" alternative that would warrant specific mitigation measures or a degree of uncertainty that would warrant extensive new monitoring activity. Therefore, substantial adverse effects are not likely to occur as a result of the federal action and do not require implementation of specific compensatory mitigation measures by USACE. No specific mitigation commitments are included in the PAA or other alternatives. However, all the alternatives incorporate measures known to benefit fish and wildlife such as current fish spawning and passage procedures and ramping rates and minimum releases from Jim Woodruff Dam to comply with ESA requirements, in accordance with the 2016 Biological Opinion. (See FEIS, Volume 1, Section 6.10.)
Statutory Compliance
Following consultation pursuant to section 7 of the ESA, USFWS issued a Biological Opinion, dated September 14, 2016, that determined the recommended plan will not jeopardize the continued existence of the following federally listed species or adversely modify designated critical habitat: fat threeridge mussel (Amblema neislerii ); purple bankclimber mussel (Elliptiodeus sloatianus ); Chipola slabshell mussel (Elliptio chipolaensis ); and Gulf sturgeon (Acipenser oxyrinchus desotoi ). The Biological Opinion specified a number of terms and conditions and reasonable and prudent measures that would minimize take of endangered species and avoid jeopardizing the species. USACE submitted a letter to the USFWS on February 21, 2017 to further clarify the terms and conditions in the biological opinion, and USFWS provided its concurrence by email dated March 1, 2017. The PAA implements all the terms and conditions and reasonable and prudent measures. The Biological Opinion is included in Appendix J of Volume 6 of the FEIS.
Pursuant to section 106 of the National Historic Preservation Act of 1966, as amended (P.L. 89-665), USACE determined that the recommended plan has no effects on historic
properties. USACE consulted the appropriate State Historic Preservation Officers and Tribal Historic Preservation Officers and interested parties in the area of potential effect. The Alabama Historical Commission, Florida Division of Historical Resources, and Georgia Historic Preservation Division all sent letters in response to the FEIS expressing concurrence with the no effect determination.
In accordance with federal tribal policy and tribal treaty obligations, USACE consulted early and often with 25 federally recognized Tribes and/or Tribal Historic Preservation Officers representing Tribes with ancestral ties and interest in the action area in order to ensure cultural properties and usual and accustomed areas important to Tribal people were not impacted.
Pursuant to section 307 of the Coastal Zone Management Act (CZMA) of 1972 (P.L. 92-583), a determination of consistency of the alternative identified in the DEIS as the proposed action alternative (Alternative 7H) with the Florida Coastal Zone Management Program (FCZMP) was provided to the State of Florida Department of Environmental Protection (FDEP) in the DEIS released for agency and public review on December 9, 2015. In a letter dated January 29, 2016, FDEP provided comments on the DEIS determining that the proposed action alternative was inconsistent with the FCZMP and objecting to the USACE consistency determination, which failed to take into account recent statutory revisions to the FCZMP. After reviewing FDEP's comments and other comments on the DEIS, USACE revised the proposed action alternative to the PAA (Alternative 7K). On September 16, 2016, USACE resubmitted by letter a revised and updated FCZMP consistency determination addressing the procedural issues with the initial consistency determination and explaining, with additional detailed supporting documentation and technical information, the USACE position that the PAA is consistent to the maximum extent practicable with the FCZMP. USACE also included detailed responses to FDEP's DEIS comments in the FEIS. On December 9, 2016, FDEP replied to the revised USACE consistency determination and again found that the PAA was inconsistent with the enforceable policies of the FCZMP, repeating earlier assertions that USACE management of its facilities in the ACF Basin favors the State of Georgia's consumption of water, which in turn harms resources in the Apalachicola River and bay. USACE disagrees with FDEP's conclusions. Specifically, as explained in USACE's September 16, 2016 consistency determination—and further documented in the FEIS—the PAA would be expected to have no appreciable incremental effect on flow conditions (quantity or timing) in the Apalachicola River or on salinity and hydrodynamic conditions in the Apalachicola Bay estuary, and negligible or no effects on oyster populations or the oyster industry in Apalachicola Bay, compared to the "no action" alternative. While FDEP did not concur with USACE's consistency determination, USACE has concluded that the PAA complies with the enforceable policies of the FCZMP to the maximum extent practicable, and therefore meets the requirements of the CZMA, for the reasons set forth in the September 16, 2016 letter and supporting documentation.
Pursuant to section 305(b) of the Magnuson-Stevens Fishery Conservation and Management Act of 1976, as amended (P.L. 94-265), USACE determined that the PAA may adversely affect designated Essential Fish Habitat (EFH). The Department of Commerce. National Marine Fisheries Service (NMFS) provided a conservation recommendation in a letter dated January 15, 2016, that the Master WCM include a minimum flow of 5,000 cfs from Jim Woodruff Dam at all times. After release of the FEIS, NMFS submitted a letter dated January 20, 2017, repeating this recommendation and also recommending that USACE should develop comprehensive biological monitoring plans for eastern oyster and white shrimp in multiple locations in Apalachicola bay and estuary, develop an adaptive management plan to offset or mitigate lost ecological resources for any occurrences of flows in the Apalachicola River less than 5,000 cfs. The PAA and Biological Opinion contemplate that flows from Jim Woodruff Dam could be reduced to 4,500 cfs during drought and prolonged low flow conditions. USACE considered NMFS's minimum flow recommendation in both the DEIS and FEIS and concluded
that there would be little to no effect on biological resources in Apalachicola Bay and estuary with the implementation of the PAA, even if flow conditions in the Apalachicola River downstream of Jim Woodruff Lock and Dam declined below 5,000 cfs for a brief period of time (up to 90 days) over the modeled period of record (73 years). In a letter dated March 7, 2017, USACE provided a formal response to the NMFS letter as required by law, reiterating its view that the PAA is consistent with the 5,000 cfs conservation recommendation to the maximum extent practicable. USACE also noted that monitoring will take place at several locations downstream of Jim Woodruff Lock and Dam including at the USGS 02359170 Apalachicola River NR Sumatra, Florida gage, which will monitor for dissolved oxygen, temperature, and specific conductivity approximately 20 miles above the mouth the Apalachicola River. Finally, USACE noted in its March 7, 2017 letter that although USACE believes that the PAA will not significantly change conditions in the estuary, in compliance with the USFWS Biological Opinion, an adaptive management technical team is being organized to provide recommendations for improved monitoring and water management in the ACF based on the data collected.
Additional Comments Submitted in Response to FEIS
By letter dated September 23, 2015, the DEIS was filed with the U.S. Environmental Protection Agency (EPA). The EPA notice of availability of the DEIS for public review and comment was published in theFederal Register on October 2, 2015, initiating a 60-day comment period that was subsequently extended by an additional 45 days, to January 15, 2016. Copies of the DEIS were provided to agencies, tribes, and members of the public who had specifically requested a copy. In addition, copies of the DEIS were provided to local libraries in locations throughout the ACF Basin. All comments submitted during the public comment period were considered, and responses to substantive issues raised in comments were included in the FEIS. The FEIS was published in the Federal Register on December 16, 2016, commencing a minimum 30-day state and agency review period that was subsequently extended by 16 days to February 1, 2017. A number of federal, state, local, and non-governmental entities submitted comments during and after the review period. Many of these comments repeated information that had previously been submitted and have already been addressed in the DEIS and/or FEIS. New issues raised in the comments are addressed below. The comments received in response to the FEIS did not result in any changes to the FEIS.
EPA submitted comments on the FEIS on February 14, 2017, acknowledging that the FEIS includes revisions and further analysis responsive to EPA's comments on the DEIS, but expressing new or continued concern with regard to several issues. First, EPA expressed uncertainty regarding the alternatives analysis, specifically the impacts to action zones in relation to different water supply withdrawal rates assumed during alternatives development (20 mgd during the first phase versus 128 mgd under the "no action" alternative). As explained above and in the FEIS, USACE developed alternatives through a two-step process that first included evaluation of water management operations for the system as a whole, and then added various permutations of water supply withdrawals in response to the State of Georgia's water supply request. USACE first evaluated water management operations that could best manage the ACF system for its authorized purposes, before considering the reallocation of storage for water supply under supplemental authority. Thus, when initially modeling revised water management operations in the first phase of alternative development, USAGE included current withdrawals of 20 mgd from Lake Lanier under existing agreements, and 277 mgd that are currently withdrawn downstream at Atlanta. In the second phase of alternatives development, USACE included different water supply withdrawal and return scenarios under either current or revised water management operations. The "no action" alternative reflected both current water management operations and current water supply withdrawals, including 128 mgd that are currently withdrawn from Lake Lanier and 277 mgd that are withdrawn from the
Chattahoochee River downstream. While increased lake withdrawals may result in lower reservoir levels, as reflected in the different alternatives evaluated in the FEIS, the operational rules remain consistent. The action zones are designed to meet the basin requirements in a balanced manner under multiple hydrologic conditions, with or without increased water supply withdrawals.
Currently, as explained in the DEIS and FEIS—and consistent with information provided by the State of Georgia in response to an information request from USACE
EPA also expressed concerns regarding nonattainment of state water quality standards and associated modeling implications under the PAA, and limited discussion in the FEIS of the effect of the PAA on the NPDES permits and Total Maximum Daily Loads downstream of Lake Lanier. EPA suggested that USACE provide an updated list of NPDES permittees. The State of Alabama, through its Office of Water Resources, the Alabama Department of Environmental Management (ADEM), and others also expressed concerns related to water quality and the cost of updating NPDES-permitted facilities under the PAA.
As discussed above, the adverse impacts to water quality that are identified in the FEIS under the PAA would be directly caused by the anticipated increased effluent discharges in the Atlanta region. (See FEIS, Volume 1, Section 6.1.2.) Pursuant to the 1946 RHA, the PAA would accommodate increased downstream water supply withdrawals below Buford Dam in the Atlanta region. As a result of increased water supply withdrawals it is reasonably foreseeable that treated wastewater discharges to the Chattahoochee River in the Atlanta region will also increase. If the authorized pollutant levels in the current NPDES permits are maintained but the amount of permitted discharges increases, then substantial adverse water quality impacts could occur, and those effects were assumed for analytic purposes in the FEIS. However, because the CWA anti-degradation provision prohibits the current reach from being degraded below state use standards, it is likely that the pollutant levels permitted in each NPDES permit will be reduced. USACE does not administer the NDPES permit program. The State of Georgia, which has requested the additional water supply withdrawals and has been delegated authority for NPDES permitting, is responsible for evaluating the impacts of future NPDES permits. Until the increased water supply permits are authorized and the new NPDES permits are devised, any cost analysis by USACE would be speculative and misleading. In response to EPA's comment on the FEIS, USACE has requested and received updated NPDES permit information from EPA, and USACE will post that updated information on the Mobile District website.
In coordination with GaEPD, USACE has made releases from Buford Dam to maintain minimum flows of 650 to 750 cfs and would continue to do so under the PAA. Recent seasonal reductions to 650 cfs have been made at the request of GaEPD, which has conducted water quality monitoring and adaptive management during implementation. The adaptive management called for a return to 750 cfs should the water quality monitoring indicate adverse impacts, but this provision was never triggered. USACE considered this along with the water quality modeling in its analysis of water quality impacts for this reach of the Chattahoochee River. Based on this information and the modeling for the PAA, USACE does not believe that water quality monitoring or adaptive management is required to prevent impacts to water quality standards. In addition to the minimum flow at Peachtree Creek, the WCMs also provide for special releases from Buford Dam sluice to improve dissolved oxygen immediately below Buford Dam, if necessary. Aside from the dissolved oxygen events, GaEPD has not notified USACE of water quality issues that would necessitate increased flows in the reach of river between Buford
Dam and Morgan Falls Dam. GaEPD also commented in its February 1, 2017 letter that it believes flows could be reduced to 550 cfs at Peachtree Creek at times without adverse effects on water quality. USACE has not modeled that scenario but could consider it as a deviation, If circumstances warrant, subject to additional analysis as may be appropriate at that time.
The Southeastern Power Administration (SEPA) and Southeastern Federal Power Customers (SeFPC) submitted comments on the FEIS reasserting objections to the use of 2007 water demands as the "no action" alternative baseline, based on a concern that utilizing the 2007 water demand and operating rules in the "no action" alternative obscured impacts to hydropower. The "no action" alternative represents continuation of the current water management operation at each of the USACE projects in the ACF Basin. System drought operations that were formulated and occurred in 2007 have evolved to what is now included in the May 2012 USFWS Biological Opinion. The FEIS did not use the actual hydropower generation numbers from 2007 in order to cap or constrain hydropower generation. To further limit any potential anomalies that might result from using a low hydropower generation year as the baseline comparison, USACE examined the entire 73-year period of record to ensure that the hydropower generation numbers used were within an acceptable range, and concluded that the hydropower purpose would not be seriously affected by the proposed action. Both SEPA and SeFPC also commented that USACE should reexamine cost allocations to ensure that hydropower does not bear an undue share of the costs of operating and maintaining the federal ACF projects. Although USACE has not revised the ACF system cost allocation study as part of the WCM update process. USACE has calculated a credit that would be applied to the hydropower account upon the reallocation of storage to water supply under the proposed action, effectively adjusting costs allocated to the hydropower purpose.
—Gainesville withdraws
The State of Alabama, through its Office of Water Resources, Alabama Power Company (APC), Columbus Water Works (Georgia), and Tri-Rivers Water Development Association repeated concerns that the PAA fails to establish minimum flow targets in the Middle Chattahoochee reach of the river below West Point dam of, for example, 2,000 cfs at the APC Plant Farley and 1,350 cfs at Columbus, Georgia. Some of these commenters suggested that authority could be found for such flow requirements in the authorizing legislation for West Point Dam, similar to the authority provided for water supply releases from Buford Dam under the 1946 RHA. After further consideration of comments from these entities and others and reviewing all relevant authorizing statutes, USACE does not interpret the authorizing legislation to require that USACE operations ensure specific minimum flows at Columbus, Georgia, or Columbia, Alabama. However, USACE notes that the flows that various parties have requested for this reach are in fact currently met, and would continue to be met under the PAA as modeled, more than 94 percent of the time. Moreover, the master and individual project WCMs allow for temporary operational deviations, as appropriate and as hydrologic conditions allow.
Such deviations are done on a case-by-case basis, and do not require the establishment of mandatory flow targets. (See FEIS, Volume 2, WCM Chapter 7.) Current ACF system operations and the PAA do incorporate a minimum, continuous flow of 675 cfs from West Point Dam, based on language in a report of the Chief of Engineers (See House Document No. 87-570 (September 24, 1962)), which was adopted in the Congressional authorization for the West Point Dam in the Flood Control Act of 1962, P.L. 87-874, § 203, 76 Stat. 1182 (Oct. 23, 1962), recognizing a need for minimum flows of 670 cfs at West Point, Georgia, for the purpose of maintaining water quality below the dam.
GaEPD and the Georgia Water Supply Providers provided comments on the FEIS, including a new substantive comment that USACE has not considered or applied the 1956 Act (P.L. 84-841) when determining the USACE authority to meet the State of Georgia's water supply request. The 1956 Act authorizes the Secretary of the Army to enter into a contract with Gwinnett County, "upon such terms and for such period not to exceed fifty years as he may deem reasonable for the use of storage space" in Lake Lanier to provide "a regulated water supply in an amount not to exceed eleven thousand two hundred acre-feet of water annually." USACE has considered the 1956 Act and recognizes that—as determined by the 2011 Eleventh Circuit and noted in the 2012 Chief Counsel Legal Opinion—it remains a viable authority for authorizing water supply uses of up to 11,200 acre-feet annually (equivalent to 10 mgd) at Lake Lanier by Gwinnett County alone, independent of the Water Supply Act. However, USACE has evaluated a request by the State of Georgia to meet all current and projected water supply needs of the Atlanta region, including Gwinnett County. Responding to that request, the PAA would incorporate the full amount of the State of Georgia's request for withdrawals from Lake Lanier, including withdrawals by Gwinnett County, by executing one or more agreements with the State of Georgia, which submitted the request. The later-enacted, broader authority conferred under the Water Supply Act is sufficient to encompass all of the State of Georgia's requested withdrawals, whereas the 1956 Act is limited to 10 mgd by Gwinnett County alone.
Periodic review of the water control plan will provide opportunities to make adjustments as conditions in the basin may change. Appropriate public coordination to satisfy environmental, economic and technical issues will occur prior to any modifications. This Record of Decision completes the NEPA process.
Moreover, according to information provided by the State of Georgia, Gwinnett County withdraws more than 80 mgd at present, and will have a need for more than 140 mgd by the year 2050, both figures well above the 11,200 acre-feet annually that could be authorized under a contract pursuant to the 1956 Act. (See FEIS Volume 3, WSSA, Appendix A. the State of Georgia 2015 Water Supply Request, Enclosure, Tables 3 and 4.) Thus, as a practical matter. while the 1956 Act does provide additional support for the conclusion that USAGE has the authority to accommodate the State of Georgia's requested withdrawals, it is not necessary to contract separately under that authority in order to implement the PAA. Instead, a Water Supply Act storage agreement with the State of Georgia could accommodate all of the current and projected withdrawals by Gwinnett County. If USAGE were to contract separately with Gwinnett County under the authority of the 1956 Act, it would likely do so on terms consistent with its Water Supply Act storage agreements, and would reduce the amount of storage it would allocate to water supply under an agreement with the State of Georgia by a corresponding amount. In the FEIS and WSSA, USACE has taken into account the current and projected needs of Gwinnett County, as well as the 20 mgd currently withdrawn without charge under relocation agreements with Buford and Gainesville. The PAA would accommodate all of these withdrawals through the existing relocation agreements and through an additional storage agreement or agreements with the State of Georgia.
GaEPD, Representative Doug Collins, the City of Gainesville, Georgia and the Georgia Water Supply Providers provided comments on the FEIS questioning whether statements in the
/div>
FEIS regarding the total of 18 mgd (gross) that Gainesville withdraws from Lake Lanier under a 1953 agreement incorrectly "reinterpret" the terms of that agreement by imposing a cap on gross withdrawals. USACE disagrees that utilizing the gross withdrawal figure of 18 mgd in the FEIS constitutes a reinterpretation of the 1953 contract or misrepresents Gainesville's current average withdrawals. To the contrary, the 18 mgd figure accurately approximates current withdrawals by Gainesville that, when combined with the approximately 10 mgd that Gainesville returns to Lake Lanier, result in the net withdrawal of 8 mgd pursuant to the relocation agreement. This interpretation is consistent with past practice and with information submitted by the State of Georgia to support its water supply request. Future increases in withdrawals by Gainesville could be accommodated from the storage that would be allocated to water supply under the PAA, pursuant to an agreement with the State of Georgia, which would be responsible for determining withdrawal rights by municipalities and other entities utilizing that storage.
In developing modeling scenarios for alternatives to be considered in the WCM and EIS, USACE made necessary assumptions about the amount of withdrawals that Gainesville and Buford would make under their existing relocation agreements. Those relocation agreements, which were executed without charge in the 1950s in compensation for the relocation of existing facilities during reservoir construction, authorize certain withdrawals from Lake Lanier, regardless of any decisions USACE might make to include storage for additional water supply withdrawals now or in the future. The Gainesville agreement authorizes the City to "remove" up to "eight million gallons of water from the reservoir of Buford Dam within any 24-hour period," and the Buford agreement authorizes the removal of to two million gallons per 24-hour period. Together, the relocation contracts clearly authorize total withdrawals of at least 10 mgd.
approximately 18 mgd and returns approximately 10 mgd, for a net total of 8 mgd. Thus, for purposes of evaluating current withdrawals from Lake Lanier, under relocation agreements, in the FEIS, USACE has included the 18 mgd in gross withdrawals by Gainesville, plus the 2 mgd to which Buford is entitled to withdraw under its relocation agreement, for a total of 20 mgd in withdrawals already authorized under relocation agreements.
The State of Georgia has requested that USACE take action to accommodate additional, uncontracted withdrawals from Lake Lanier as well as future water supply needs projected to the year 2050, well beyond any withdrawals that were contemplated in 1953, when USACE and Gainesville entered into the current relocation agreement. Accordingly, USACE decided to use 20 mgd as the baseline amount of gross withdrawals already made or authorized under relocation agreements at Lake Lanier—18 mgd by Gainesville and 2 mgd by Buford—for purposes of both the NEPA "no action" alternative and the WSSA "future without project condition" alternative (FEIS Alternative 7J). USACE anticipates that, under the PAA, USACE would continue to accommodate existing withdrawals of up to 20 mgd without charges under relocation agreements, and would enter into a new agreement with the State of Georgia for storage sufficient to accommodate the additional water supply withdrawals that the State of Georgia has requested to meet needs projected to the year 2050.
GaEPD, Representative Collins, and the Georgia Water Supply Providers also reiterated comments objecting to the storage accounting methodology reflected in the FEIS and encouraging USACE to adopt a policy that could provide greater credit for return flows or other made inflows. As noted in the comments, the Department of the Army has issued a notice of proposed rulemaking and is currently receiving public comments on a proposed rule that addresses storage accounting and return flow credits with respect to water supply storage uses at USACE reservoirs. The modeling assumptions utilized in the FEIS were not based on this proposed rule, but rather, on methodologies currently employed by the Mobile District, and on withdrawals and returns that are actually occurring or are reasonably expected to occur, regardless of what accounting methodology may be utilized in the future. This Record of Decision for the ACF WCM would not affect that rulemaking, which is proceeding as a separate action.
The FDEP, the State of Alabama, and others submitted comments expressing the view previously stated in comments on the DEIS that the PAA favors the State of Georgia's consumption of water over other authorized purposes, and at the expense of downstream resources in the Apalachicola River and Bay, and exceeds USACE authority under the Water Supply Act. FDEP submitted evidence from the ongoing caseFlorida v. Georgia, No. 142 Orig., in support of its views and requested that USACE delay the record of decision and reevaluate its PAA with respect to the State of Georgia's water supply request. Additionally, Senators Nelson and Rubio, and Representative Dunn and twenty-six Members of Congress, wrote to USACE requesting that implementation of the final WCM be stopped pending resolution of the dispute between the States of Florida and Georgia, in response to a February 14, 2017 report of the Special Master appointed in the case.
The PAA does not favor the State of Georgia's consumption of water over other authorized ACF purposes and does not purport to allocate water between the States of Georgia and Florida, or Alabama. USACE has thoroughly evaluated impacts of the proposed action and concluded that the PAA would accomplish the authorized purposes of the ACF system. More specifically, the reallocation of 254,170 acre-feet of storage in Lake Lanier for water supply would not seriously affect the authorized purposes of the ACF system or involve major structural or operational changes. Although Apalachicola Bay and the Apalachicola River below the GIWW are not physically part of the authorized ACF system of projects, USACE did evaluate, in the FEIS, impacts of the PAA and other alternatives on flow conditions, salinity, and fish and
aquatic species in the River and Bay. Those impacts were found to be negligible overall, and would not be substantially different under any of the alternatives considered—including alternatives that modeled fewer water supply withdrawals from Lake Lanier than are currently taking place or that would be accommodated under the PAA. Thus, the analysis contained within the FEIS does not support the assertion that adjusting USACE operations to accommodate water supply uses under the PAA would come at the expense of downstream resources in the ACF Basin, including the Apalachicola River and Bay, or exceed USACE authority.
With respect to theFlorida v. Georgia case, USACE will review any final decision from the U.S. Supreme Court and consider any operational adjustments that are appropriate in light of that decision, including modifications to the then-existing WCM, if applicable. However, USACE is not a party to the case, and USACE operations are not at issue in the litigation. Rather, the case involves the State of Florida's request for an equitable apportionment of the waters of the ACF Basin, specifically through a cap on consumption of water by the State of Georgia.Florida v. Georgia, No. 142 Orig., Report of the Special Master 18 (February 14, 2017). The United States has participated in the case asamicus curiae, but has taken no position as to whether the State of Florida's requested relief should or will be granted. Should the Supreme Court issue a decree apportioning the waters of the ACF Basin, should the States reach agreement endorsed by Congress on an allocation of basin waters, or should Congress enact other legislation affecting the purposes or operation of the federal ACF system, USACE would take those developments into account and adjust its operations accordingly, including new or revised WCMs, new or supplemental NEPA or ESA documentation, or any other actions as may be appropriate under applicable law. In the meantime, however, the purpose and need stated in the FEIS is to determine how to operate the system of federal projects in the ACF Basin for their authorized purposes, in light of current conditions and applicable law. The adoption of the PAA would, after decades of delay and deferral, result in improved operations under an updated WCM, but would not apportion the waters of the ACF Basin among the States or in any way prejudice the Supreme Court, the States, or the Congress from with respect to a future apportionment of the waters of the ACF Basin.
Finally, NMFS provided additional conservation recommendations in response to the FEIS, as discussed above. The Department of Interior. National Park Service and USFWS, Northwest Florida Water Management District, ACF Stakeholders, Chattahoochee Riverkeeper, and Florida Fish and Wildlife Conservation Commission submitted comments on the FEIS reiterating comments provided earlier. The National Wildlife Federation, Florida Wildlife Federation, and Apalachicola Riverkeeper submitted consolidated comments reiterating previously expressed concerns, and specifically questioning implementation of ESA conservation recommendations. In response to the latter comment, the 2016 Biological Opinion has been included as an appendix to the FEIS, and its reasonable and prudent measures and conservation recommendations are described in Section 6.4.4 of the FEIS, Volume 1. Pursuant to section 7 of the ESA, all terms and conditions, conservation measures, and reasonable and prudent alternatives and measures resulting from the formal consultations shall be implemented in order to minimize take of endangered species and avoid jeopardizing the species.
Conclusion
Technical, environmental, and economic criteria used in the formulation of alternative plans were those specified in the Water Resources Council's 1983 Economic and Environmental Principles and Guidelines for Water and Related Land Resources Implementation Studies. All applicable laws, executive orders, regulations, and local government plans were considered in evaluation of alternatives. All comments received during the WCM update process, including from other Federal agencies, the States of Alabama,
Florida, and Georgia, local agencies, Native American Tribes, and other members of the public were considered. The PAA would satisfy the purpose and need of updating the master WCM to operate the federal ACF projects for their authorized purposes, in light of current conditions and applicable law. The reallocation of 254,170 acre-feet of storage in Lake Lanier for water supply, subject to the execution of a binding agreement with the State of Georgia for the use of that storage and payment of costs allocated thereto, would meet the objective of responding to the 2011 Eleventh Circuit decision and the State of Georgia's revised water supply request, without seriously affecting authorized purposes or involving major structural or operational changes, as documented in the FEIS and WSSA. Finally, implementing the PAA would not apportion the waters of the ACF Basin or preclude the States, the Supreme Court, or the Congress with respect to a possible future apportionment.
Based on the foregoing, I hereby adopt the PAA for the immediate implementation of the updated Apalachicola-Chattahoochee-Flint River Basin Master Manual, and for the reallocation of 254,170 acre-feet of storage in Lake Lanier for water supply. The Commander, South Atlantic Division is authorized to implement the updated water control plans and manuals immediately. The Chief of Engineers is authorized on my behalf to enter into a water supply storage agreement with the State of Georgia or its authorized representatives for the use of 254,170 acre-feet of storage in Lake Lanier.
3-3-17 ________ Date DOUGLAS W. LAMONT, P.E. Senior Official Performing the Duties of the Assistant Secretary of the Army (Civil Works)