From Casetext: Smarter Legal Research

Frechie et Ux. v. Boyd

Superior Court of Pennsylvania
Dec 12, 1930
100 Pa. Super. 553 (Pa. Super. Ct. 1930)

Opinion

October 2, 1930.

December 12, 1930.

Real estate — Sale of — Contract — Date of performance — Uncertainty of — Subsequent agreement as to date of performance — Evidence — Admissibility of — Rescision of contract.

In an action of assumpsit to recover a deposit made pursuant to a written contract for the sale of real estate, there was evidence that the defendant agreed to convey to the plaintiffs certain lots in a development and that the plaintiffs made a cash payment at the time of the execution of the contract. The agreement provided that final settlement was to be made when the improvements were completed but not before a certain day. One of the plaintiffs, over the objection of the defendant, testified that a few weeks after the contract was entered into, he and an agent for the defendant agreed that settlement would be made on or before a specified date. The improvements were not completed at the date alleged to have been mutually agreed upon for settlement and the plaintiffs thereafter rescinded the contract.

Held: (1) That oral testimony was admissible to prove the agreement of a definite date for settlement, and (2) that a judgment entered for the plaintiffs will be affirmed.

Where the agreement for the sale of realty provided that settlement was to be made "when the improvements were completed," but the contract was uncertain as to the date of the settlement and what improvements were contemplated, parol evidence was admissible to show that the parties subsequently agreed on a date for settlement. Such evidence did not contradict the terms of the contract but merely makes certain an ambiguous provision.

One may prove the meaning of an ambiguous clause in a written contract, or that a written contract has been subsequently abandoned, in whole or in part, or modified, or a provision thereof has been waived by express agreement or by the conduct of the parties, or the time of payment may be shortened or extended.

Contracts — Performance of — Reasonable time — Delay — Excusable — Rescision of contract — Tender of performance.

Where no time is fixed for the performance of a condition precedent, it will be presumed that it is to be performed within a reasonable time.

If a delay in performance of a contract, caused by impossibility, is excusable and of short duration, the vendee is bound subject to the extent of the delay. If, however, the impossibility persists for a sufficient length of time to go to the essence of the contract, the vendee is justified in rescinding the contract.

A tender of performance by the plaintiff was not necessary when the defendant was in default, since the latter was not in a position to demand performance.

Appeal No. 19, October T., 1930, by defendant from judgment of M.C., Philadelphia County, May T., 1927, No. 1381, in the case of Harry Frechie and Minnie Frechie, his wife, v. William Boyd.

Before TREXLER, P.J., KELLER, LINN, GAWTHROP, CUNNINGHAM, BALDRIGE and WHITMORE, JJ. Affirmed.

Assumpsit to recover hand money paid. Before GLASS, J., without a jury.

The facts are stated in the opinion of the Superior Court.

Finding for plaintiffs in the sum of $2,488 and judgment entered thereon. Defendant appealed.

Error assigned, among others, was the admissibility of the plaintiffs' testimony as to agreement determining final date of settlement.

Robert K. Bell, and with him White Wetherill, for appellant.

M.P. Elwert, and with him Herbert W. Salus, for appellee.


Argued October 2, 1930.


The parties to this suit entered into a written agreement on the 31st of August, 1925, whereby the defendant agreed to sell and convey to the plaintiffs for $15,000, five lots of ground included in a development, known as Shore Gardens, located at Ocean City. Two thousand dollars of the consideration was paid on the execution of the agreement and an additional cash payment of $8250 was to be made at the time of final settlement at the office of J.W. Morrison, "when the improvements are completed, not before September 15, A.D. 1925." The agreement provided further that the lots were "to be brought to established grade, streets to be built of gravel, curb and sidewalks of cement." The plaintiffs rescinded the contract on August 12, 1926, and on May 26, 1927, brought this action to recover the hand money paid, with interest. The case was tried without a jury and a verdict rendered for the plaintiffs.

Harry Frechie, one of the plaintiffs, testified that a few weeks after the contract was entered into he inquired of Morrison, who, under pleadings admitted in evidence, was the agent of the defendant, when he would be ready for a settlement and Morrison then agreed that it would not be later than the 15th of February, 1926. Morrison, called as a witness for the defendant, testified that he remembered Frechie calling at the office and that he may have then agreed to a date of settlement but that he did not recall so doing. Monahan, the contractor, testified that the work was to have been finished February 1, 1926. The improvements were, in fact, not completed until June, 1927.

The major question involved is, whether the oral testimony was admissible to prove an agreement of a definite date for settlement. The improvements, the defendant alleged, included the building of a bulkhead along the ocean front for the entire development for the purpose of preventing the sand, which was dredged and recovered from the bay side, from running into a water thoroughfare. The defendant maintains further that the only time fixed for settlement was in the written agreement and that was to be after all the improvements of the entire development were completed. What improvements were contemplated by the parties to the agreement? Did the entire bulkhead have to be constructed, all the lots have to be filled, which required 300,000 tons of sand, and the streets, curbs and sidewalks in this extensive tract of land have to be built before settlement? Although that is the contention of the appellant, we do not regard this agreement as free of doubt as to that question. The contract itself did not expressly provide that the entire work was to be done in the development of Shore Gardens before settlement.

The parties attempted to fix the date of settlement which was quite uncertain, and, subsequently, they agreed to a definite time when the conditions of the contract were to be fulfilled and the money paid. Such an arrangement was not a contradiction of the terms of the contract; it was a clarification of an obscure provision and made the time of payment certain, which was uncertain. The burden, of course, was on the plaintiffs to show such an agreement and the court held that they successfully did so. One may prove the meaning of an ambiguous clause in a written contract, or that a written contract has been subsequently abandoned, in whole or in part, or modified, or a provision thereof has been waived by express agreement or by the conduct of the parties, or the time of payment may be shortened or extended: Achenbach v. Stoddard, 253 Pa. 338; Anstead v. Cook, 291 Pa. 335; Ketcham v. Central Trust and Savings Co., 71 Pa. Super. 376; Fahey v. Adams, 78 Pa. Super. 209; Hudson v. Hyman, 85 Pa. Super. 245.

We are of the opinion that the court correctly admitted the evidence and was justified in his conclusion that there was a date of settlement agreed upon as of February 15, 1926.

If we would assume that this date was not definitely fixed, we strongly incline to the view that the court could determine what, in the circumstances, was a reasonable time to make the improvements and could very properly have said that the plaintiffs showed sufficient patience before rescinding.

The general rule is that where no time is fixed for the performance of a condition precedent, it will be presumed that it is to be performed within a reasonable time. There is authority for the statement that an exception to this rule exists where the performance is not within the powers of the vendor: 13 C.J. 684. But we are not convinced under the testimony that this case comes within that exception. We think it comes under the principle that if a delay in performance of a contract caused by impossibility is excusable and of short duration, the vendee is bound subject to the extent of the delay. If, however, the impossibility persists for a sufficient length of time to go to the essence of the contract, the vendee is justified in rescinding the contract: Williston on Contracts, Sec. 1957, Page 3324. As the delay in performance was for a period of twenty months, the very substance of this contract was affected to such a degree that the vendee was warranted in seeking its abrogation.

It inevitably follows that as the testimony referred to was admissible and sufficient to sustain the finding of the lower court as to the time for the completion of the improvements, no tender of the additional cash payment by the plaintiffs was necessary before rescinding as they were not in default. A party in default cannot demand performance by the other parties to a contract; that would be a needless and vain thing which the law does not require. It is only when nothing further is to be done by the party to whom the money is payable that a tender is necessary: Eberz v. Heisler, 12 Pa. Super. 388 (391); Romm v. Lobosco, 95 Pa. Super. 373.

All of the assignments of error are overruled and the decree of the learned court below is affirmed.


Summaries of

Frechie et Ux. v. Boyd

Superior Court of Pennsylvania
Dec 12, 1930
100 Pa. Super. 553 (Pa. Super. Ct. 1930)
Case details for

Frechie et Ux. v. Boyd

Case Details

Full title:Frechie et ux. v. Boyd, Appellant

Court:Superior Court of Pennsylvania

Date published: Dec 12, 1930

Citations

100 Pa. Super. 553 (Pa. Super. Ct. 1930)

Citing Cases

The Tenant Union Representative Network v. Pa. Pub. Util. Comm'n

Field v. Golden Triangle Broadcasting, Inc., 305 A.2d 689, 694 (Pa. 1973); Lefkowitz v. Hummel Furniture…

Penn Discount Corp. v. Sharp

The appellants never complied, or offered to comply, with their part of the agreement, and therefore a formal…