From Casetext: Smarter Legal Research

Con. F. Co. v. W. T. Grange C. Co.

Supreme Court of Pennsylvania
Nov 25, 1935
320 Pa. 205 (Pa. 1935)

Summary

In Concrete Form Co., the Court held that an anti-assignment clause in a construction contract barred assignment of the right to payment after the 5 construction was complete.

Summary of this case from Gito, Inc. v. Axis Architecture, P.C.

Opinion

October 8, 1935.

November 25, 1935.

Assignments — Partial — Consent of debtor — Contract prohibiting assignment — Acknowledgment of notice as consent to assignment.

1. Notice of a partial assignment is not sufficient and the debtor is not bound thereby unless he gives his consent. [208]

2. A right may not be the subject of an effective assignment when the assignment is prohibited by the contract creating the right. [208]

3. Acknowledgment by contractor of notice by assignee bank of assignment by subcontractor of stated part of compensation under contract between contractor and subcontractor, which prohibited assignment of any payments thereunder except with the consent of the contractor, construed not to express or imply consent by contractor to assignment. [208-9]

4. Restatement, Contracts, sections 151 (c) and 176, cited. [208, 209]

Argued October 8, 1935.

Before FRAZER, C. J., KEPHART, SCHAFFER, MAXEY, DREW, LINN and BARNES, JJ.

Appeal, No. 208, March T., 1935, by defendant, from judgment of C. P. Allegheny Co., Jan. T., 1933, No. 831, in case of Concrete Form Company, Inc., for use of Blairsville Savings and Trust Company, v. W. T. Grange Construction Company. Judgment reversed and judgment herein entered for defendant.

Assumpsit. Before EGAN, J.

The opinion of the Supreme Court states the facts.

Verdict directed for plaintiff and judgment entered thereon. Defendant appealed.

Error assigned, among others, was refusal of judgment n. o. v.

Charles K. Robinson, with him H. A. Robinson, of Dickie, Robinson McCamey, for appellant.

Harvey A. Miller, with him Samuel W. Miller, of Miller Nesbitt, for appellee.


Defendant had been engaged as the general contractor for a large apartment building to be erected in the City of Pittsburgh. The Concrete Form Company, Inc., was subsequently employed by defendant as a subcontractor for the performance of certain work in connection with the construction. The contract was in the total sum of $64,400, and provided that the subcontractor would not "sublet any portion of the work of this contract or . . . hypothecate, pledge or assign any payments thereunder except by and in accordance with the consent of [the] contractor." The contract had been substantially performed when the subcontractor executed an assignment in the sum of $4,000 to the Blairsville Savings and Trust Company. At the time of the assignment the subcontractor's claims against defendant exceeded the amount of the assignment. The bank gave prompt notice of the assignment to defendant and requested an "acknowledgment of this letter." Defendant replied as follows: "This will acknowledge receipt of your letter dated February 9, 1929, concerning an assignment to you by Concrete Form Company of $4,000 claimed to be due from us in connection with the Morewood Gardens Apartment contract. The owners of this building have not approved all of the charges nor all of the work of Concrete Form Company and therefore we are not prepared to state to you that there will be $4,000 due them when all open questions have been settled."

The letter of acknowledgment was dated February 14, 1929. In the following May defendant made final settlement with the subcontractor, payment of $2,775.04 being made directly to the latter. Subsequently the subcontractor became insolvent and the present suit was brought in its name for the use of the bank. It is the contention of the latter that notwithstanding the provision against assignment and regardless of the nature of the assignment, defendant's letter of February 14, 1929, constituted a consent thereto and that defendant's subsequent payment to the assignor without notice to the assignee was at its own risk. Defendant contends that it never gave the consent necessary to the validity of the assignment in question. The court below directed a verdict for plaintiff. Defendant has appealed from the overruling of its motions for a new trial and for judgment n. o. v.

Defendant cannot be held liable to the bank unless it consented to the subcontractor's assignment, irrespective of whether the assignment was total or partial. In the case of a partial assignment we have repeatedly held that notice alone is not enough and that the debtor is not bound thereby unless he gives his consent: Gordon v. Hartford Sterling Co., 319 Pa. 174, 179 A. 234, and cases therein cited. If the assignment is to be regarded as a complete transfer of the assignor's interest, which we think it was not, it still does not follow that notice to defendant was enough and that its assent was unnecessary. The contract between defendant and the assignor prohibited an assignment by the latter without the consent of the former. A right may not be the subject of an effective assignment when the assignment is prohibited by the contract creating the right: see Restatement, Contracts, section 151 (c). Since this prohibition was binding upon the assignee it must be obvious that defendant's consent was an essential prerequisite to its liability to any party other than its subcontractor.

The issue is therefore a very narrow one: Did defendant consent to the assignment? The bank's contention that defendant did so consent is founded solely upon the letter of February 14, 1929, in which it acknowledged receipt of the assignee's letter informing it of the assignment and further stated that the amount of its indebtedness to the assignor had not been determined. This letter did not constitute an unequivocal assent to the assignment. The assignee's letter had requested an acknowledgment of the notice of the assignment therein contained and defendant's letter was in response to that request. The assignee was also informed that a complete accounting had not yet been had and that the amount of the indebtedness had not been finally determined. Beyond that the letter did not go. There was no express consent; nor is there sufficient warrant for any implication of the necessary assent. The original contract expressly forbade assignment. By that provision defendant undoubtedly sought to provide against the introduction of one or more third parties. It was for the benefit of the obligor: see Restatement, Contracts, section 176. Defendant wished to deal with its subcontractor and with it alone. Any waiver of that provision or consent to its violation would have to be clear, distinct and unequivocal. Such is not the present case. The court below should have ruled as a matter of law that defendant did not consent to the assignment and could not, therefore, be held liable.

The judgment of the court below is reversed and judgment is herein entered for defendant.


Summaries of

Con. F. Co. v. W. T. Grange C. Co.

Supreme Court of Pennsylvania
Nov 25, 1935
320 Pa. 205 (Pa. 1935)

In Concrete Form Co., the Court held that an anti-assignment clause in a construction contract barred assignment of the right to payment after the 5 construction was complete.

Summary of this case from Gito, Inc. v. Axis Architecture, P.C.
Case details for

Con. F. Co. v. W. T. Grange C. Co.

Case Details

Full title:Concrete Form Company, Inc., for use, v. W. T. Grange Construction Co.…

Court:Supreme Court of Pennsylvania

Date published: Nov 25, 1935

Citations

320 Pa. 205 (Pa. 1935)
181 A. 589

Citing Cases

Sillman v. Twentieth Century-Fox

Indeed, on facts far stronger than those asserted by plaintiffs, the courts have held, as a matter of law,…

VanderMeer v. State, Department of Revenue

Pennsylvania recognizes that a right may not be effectively assigned where such assignment is prohibited by…