From Casetext: Smarter Legal Research

Balf Co. v. Spera Construction Co.

Supreme Court of Connecticut
May 26, 1992
222 Conn. 211 (Conn. 1992)

Summary

concluding that no appealable final judgment had been rendered where trial court had reserved ruling on postjudgment motion for prejudgment interest

Summary of this case from Town of Ledyard v. WMS Gaming, Inc.

Opinion

(14492)

The plaintiff subcontractor, which had successfully moved for summary judgment in its action to recover for labor and materials furnished on a certain construction project, moved to dismiss an appeal by the defendant surety. The trial court having reserved its ruling on the plaintiff's claim for prejudgment interest pending further factual inquiry, the motion to dismiss was granted. The plaintiff's right to recovery of prejudgment interest was part of its claim to be made whole, and an appeal after a resolution of all the issues will afford a better opportunity for the reviewing court to consider in its entirety the alleged wrongfulness of the challenged conduct and the plaintiffs full damages.

Argued April 28, 1992

Decision released May 26, 1992

Motion by the plaintiff to dismiss the appeal by the defendant Insurance Company of North America from a partial summary judgment rendered by the Superior Court in the judicial district of Hartford-New Britain at Hartford, Wagner, J., in favor of the plaintiff in its action to recover, inter alia, moneys allegedly owed under a certain performance bond. Appeal dismissed.

Thomas W. Witherington, in support of the motion.

James J. Mercier, in opposition to the motion.


The sole issue in this motion to dismiss an appeal is whether a trial court has rendered a final judgment when it has granted a motion for summary judgment that establishes liability for the principal amount claimed by the plaintiff but has reserved a ruling on a claim for prejudgment interest. The plaintiff, The Balf Company, a subcontractor, brought an action against the defendants Spera Construction Company, Inc., a general contractor, and Insurance Company of North America (INA), the surety under a performance bond, to recover for labor and materials furnished on a construction project in Bloomfield. The plaintiff successfully moved for summary judgment against both defendants. With respect to the plaintiff's claim against INA, however, the trial court, Wagner, J., granted the summary judgment motion only in part. Although the court concluded that there was no factual dispute about the plaintiff's right to recover the principal amount from INA, it determined that the plaintiff's alleged entitlement to prejudgment interest from INA required a further factual inquiry. INA appealed to the Appellate Court from the summary judgment rendered against it, and we transferred its appeal here in accordance with Practice Book 4023. The plaintiff has moved this court to dismiss INA's appeal. We conclude that the motion must be granted.

The parties do not dispute the proposition that appeals to the Appellate Court or to this court must ordinarily await the rendering of a final judgment in the trial court. General Statutes 51-197a, 52-263; Practice Book 4000; Stroiney v. Crescent Lake Tax District, 197 Conn. 82, 84, 495 A.2d 1063 (1985). They do not challenge the well established rule that a summary judgment rendered upon the issue of liability only, without deciding damages, is not a final judgment from which an appeal lies. Stroiney v. Crescent Lake Tax District, supra; Pinnix v. LaMorte, 182 Conn. 342, 343, 438 A.2d 102 (1980). Their disagreement centers upon the implication of Paranteau v. DeVita, 208 Conn. 515, 544 A.2d 634 (1988), in which this court concluded that the trial court's determination of liability and damages is a final judgment, for purposes of appeal, even though a supplemental postjudgment claim for statutory attorney's fees has not yet been resolved.

INA's contention that Practice Book 4002(b) on its face authorizes its appeal does not warrant extended discussion. That section includes, within the category of a final judgment, the granting of a summary judgment "on an entire complaint." The pivotal issue in this case is whether summary judgment has been rendered "on an entire complaint" or whether the trial court has rendered only a partial summary judgment.

These cases fully address INA's contention that its appeal can be characterized as an immediately appealable interlocutory appeal under State v. Curcio, 191 Conn. 27, 30, 463 A.2d 566 (1983). The present appeal concerns a ruling that neither terminates a separate and distinct proceeding nor concludes the rights of the parties relating thereto.

In Paranteau the plaintiff filed a claim against the defendant alleging, inter alia, a violation of the Connecticut Unfair Trade Practices Act (CUTPA). General Statutes 42-110a through 42-110q. The plaintiff prevailed on this claim at trial and was awarded damages accordingly. Thereafter, the trial court ordered a supplemental hearing to determine the amount of attorney's fees to which the plaintiff was entitled under 42-110g (d). The defendant filed an appeal in the Appellate Court, after the rendition of a judgment on the attorney's fee, in which it sought to challenge the merits of the judgment on the CUTPA claim. The timeliness of this appeal depended upon whether there had been a final, appealable judgment in advance of the resolution of the attorney's fee issue. This court held that "a judgment on the merits is final for purposes of appeal even though the recoverability or amount of attorney's fees for the litigation remains to be determined." Id., 523. We therefore agreed with the Appellate Court that the defendant's appeal of the judgment on the merits was properly dismissed because it had been filed too late. Id.

The question raised by the present motion is whether the rule of Paranteau should be extended to include a supplemental determination of prejudgment interest.

The plaintiff contends that Paranteau is distinguishable because an award of attorney's fees serves a different function than an award of prejudgment interest. The recovery of attorney's fees permits a plaintiff to defray the costs of litigation, while the recovery of prejudgment interest compensates the plaintiff for the loss suffered by INA's unjustified delay in paying funds to which the plaintiff was entitled. INA maintains, to the contrary, that Paranteau applies to a supplemental claim for prejudgment interest as well as to attorney's fees because we adopted a bright-line rule in that case requiring an immediate appeal after a judgment on the merits regardless of the nature of supplemental postjudgment adjudications. INA reminds us in particular that we held in Paranteau that "the timeliness of an appeal should [not] be based upon retrospective, technical considerations of whether a particular supplemental postjudgment claim for attorney's fees was collateral to, or an integral part of, the judgment on the merits." Id.

The rule we articulated in Paranteau relied on a similar holding by the United States Supreme Court in Budinich v. Becton Dickinson Co., 486 U.S. 196, 108 S.Ct. 1717, 100 L.Ed.2d 178 (1988). That court revisited the subject in Osterneck v. Ernst Whinney, 489 U.S. 169, 109 S.Ct. 987, 103 L.Ed.2d 146 (1989). While the United States Supreme Court had held in Budinich that a request for attorney's fees was not part of the merits of the underlying action, and hence did not postpone the finality of a judgment on the merits; id., 202; the court in Osterneck came to a different conclusion with respect to a postjudgment motion for discretionary prejudgment interest. The court proffered three grounds for its conclusion. First, "unlike attorney's fees, which at common law were regarded as an element of costs and therefore not part of the merits judgment . . . prejudgment interest traditionally has been considered part of the compensation due [the] plaintiff. Second, unlike a request for attorney's fees or a motion for costs, a motion for discretionary prejudgment interest does not `rais[e] issues wholly collateral to the judgment in the main cause of action' . . . nor does it require an inquiry wholly `separate from the decision on the merits' . . . . In deciding if and how much prejudgment interest should be granted, a district court must examine — or in the case of a postjudgment motion, reexamine — matters encompassed within the merits of the underlying action." (Citations omitted.) Osterneck v. Ernst Whinney, supra, 175-76. Third, the conclusion that a postjudgment motion for discretionary prejudgment interest postpones the finality of a judgment on the merits "helps further the important goal of avoiding piecemeal appellate review of judgments." Id., 177.

The underlying reasoning of Osterneck is persuasive even though the United States Supreme Court was applying the Federal Rules of Civil Procedure, which are not identical with the statutes and rules governing appeals as a matter of state law. In this case, the trial court, as in Osterneck, ordered a hearing for the purpose of adjudicating a discretionary award of prejudgment interest. The plaintiff's right to such a recovery is part of its claim to be made whole. Whether it succeeds will depend upon an assessment of the underlying merits of the transaction between the parties. An appeal after a resolution of all the issues will afford an appellate court a better opportunity to review in its entirety the alleged "wrongfulness of the defendant's conduct and the plaintiff's full damages, as well as other matters of equity bearing on the merits of the litigation." Id., 177. INA's day in appellate court has not been lost; it has only been postponed.

The merits of the plaintiff's entitlement to prejudgment interest are not before us at this time.


Summaries of

Balf Co. v. Spera Construction Co.

Supreme Court of Connecticut
May 26, 1992
222 Conn. 211 (Conn. 1992)

concluding that no appealable final judgment had been rendered where trial court had reserved ruling on postjudgment motion for prejudgment interest

Summary of this case from Town of Ledyard v. WMS Gaming, Inc.

adopting United States Supreme Court's reasoning in Osterneck v. Ernst & Whinney , 489 U.S. 169, 173–77, 109 S. Ct. 987, 103 L. Ed. 2d 146, to determine whether judgment was final, "even though the United States Supreme Court was applying [rule 59 (e) of] the Federal Rules of Civil Procedure" and rule 4 of Federal Rules of Appellate Procedure

Summary of this case from Georges v. OB-GYN Servs.

In Balf Co., this court determined that there was no appealable final judgment under such circumstances because, first, "unlike attorney's fees, which at common law were regarded as an element of costs and therefore not part of the merits judgment... prejudgment interest traditionally has been considered part of the compensation due [the] plaintiff.

Summary of this case from Hylton v. Gunter

In Balf Co., this court determined that there was no appealable final judgment under such circumstances because, first, “unlike attorney's fees, which at common law were regarded as an element of costs and therefore not part of the merits judgment... prejudgment interest traditionally has been considered part of the compensation due [the] plaintiff.

Summary of this case from Hylton v. Gunter

In Balf Co. v. Spera Construction Co., 222 Conn. 211, 214-15, 608 A.2d 682 (1992), this court concluded that a judgment on the merits was not a final judgment for purposes of appeal when there was an unresolved claim for discretionary prejudgment interest.

Summary of this case from Gianetti v. Meszoros

In Balf Co. v. Spera Construction Co., 222 Conn. 211, 214-15, 608 A.2d 682 (1992), our Supreme Court concluded that the judgment on the merits was not a final judgment for the purpose of appeal when, as here, there is an unresolved claim for discretionary prejudgment interest.

Summary of this case from Nolan v. Milford

In Balf Co. v. Spera Construction Co., 222 Conn. 211, 214-15, 608 A.2d 682 (1992), our Supreme Court explained that an award of attorney's fees and costs was a means of defraying costs of litigation and was therefore ancillary to the main action.

Summary of this case from IBM Credit Corp. v. Mark Facey & Co.

refusing to extend Paranteau to a supplemental determination of prejudgment interest

Summary of this case from Preston v. Phelps Dodge Copper Products Co.

In Balf Co. v. Spera Construction Co., 222 Conn. 211, 608 A.2d 682 (1992), the Supreme Court of Connecticut adopted the reasoning of Osterneck in a case involving Connecticut procedure.

Summary of this case from Sears, Roebuck Co. v. Board of Tax Review
Case details for

Balf Co. v. Spera Construction Co.

Case Details

Full title:THE BALF COMPANY v. SPERA CONSTRUCTION COMPANY, INC., ET AL

Court:Supreme Court of Connecticut

Date published: May 26, 1992

Citations

222 Conn. 211 (Conn. 1992)
608 A.2d 682

Citing Cases

Hylton v. Gunter

(Internal quotation marks omitted.) Broadnax v. New Haven, 294 Conn. 280, 297, 984 A.2d 658 (2009); see also,…

Georges v. OB-GYN Servs.

(Internal quotation marks omitted.) Broadnax v. New Haven , 294 Conn. 280, 297, 984 A.2d 658 (2009) ; see,…