Summary

In Armand Eng'r Co. v. Adrien A. Labrie, Inc., 119 N.H. 408, 402 A.2d 184 (1979) (Armand I), we held that a Massachusetts judgment obtained by the plaintiff was entitled to full faith and credit.

Summary of this case from Armand Engineering Co. v. Adrien A. Labrie, Inc.

Opinion

No. 79-008

Decided May 23, 1979

Judgments — Foreign Judgments — Full Faith and Credit Where contract dispute was, by agreement, submitted to arbitration in Massachusetts and Massachusetts court denied defendant's motion to dismiss jurisdiction, and entered a judgment confirming the award, and where defendant had voluntarily appeared before the Massachusetts court and had not prosecuted an appeal from the adverse ruling of that court, trial court's action, in suit brought in New Hampshire on the foreign judgment, holding that the Massachusetts judgment was entitled to full faith and credit, granting plaintiff's motion for summary judgment, and denying all relief sought by the defendant, was affirmed.

Craig, Wenners, Craig McDowell, of Manchester (Thomas E. Craig orally), for the plaintiff.

Spaloss Rosson, of Nashua (Jon Groetzinger, Jr., orally), for the defendant.


MEMORANDUM OPINION

This is an appeal from the granting of a motion for summary judgment filed by the plaintiff, Armand Engineering Company, Inc., pursuant to RSA 491:8(a) (Supp. 1977). Flynn, J., reserved and transferred all questions of law raised by the defendant's exceptions.

A contract dispute, which arose between the parties, was, by agreement, submitted to arbitration in Boston, Massachusetts. A complaint to confirm an arbitration award in favor of the plaintiff was filed in the Superior Court for the Commonwealth of Massachusetts. That court denied defendant's motion to dismiss for lack of jurisdiction, and on July 30, 1976, entered a judgment confirming the award. The defendant did not appeal this order.

Plaintiff subsequently brought suit in New Hampshire on the foreign judgment. Both parties filed numerous motions and pleadings. On May 3, 1978, the court held that the Massachusetts judgment was entitled to full faith and credit, granted plaintiff's motion for summary judgment, and denied all relief sought by the defendant.

The defendant voluntarily appeared before the Massachusetts court, did not prosecute an appeal from the adverse ruling of that court, and for more than one year did not pursue before that court any of the challenges it now urges upon our superior court. We affirm the trial court's action. See Leighton v. Davis, 119 N.H. 115, 398 A.2d 845 (1979).

Exceptions overruled.


Summaries of

Armand Engineering Co. v. Adrien A. Labrie, Inc.

Supreme Court of New Hampshire Hillsborough
May 23, 1979
402 A.2d 184 (N.H. 1979)

In Armand Eng'r Co. v. Adrien A. Labrie, Inc., 119 N.H. 408, 402 A.2d 184 (1979) (Armand I), we held that a Massachusetts judgment obtained by the plaintiff was entitled to full faith and credit.

Summary of this case from Armand Engineering Co. v. Adrien A. Labrie, Inc.
Case details for

Armand Engineering Co. v. Adrien A. Labrie, Inc.

Case Details

Full title:ARMAND ENGINEERING COMPANY INC. v. ADRIEN A. LABRIE, INC

Court:Supreme Court of New Hampshire Hillsborough

Date published: May 23, 1979

Citations

402 A.2d 184 (N.H. 1979)
402 A.2d 184

Citing Cases

Armand Engineering Co. v. Adrien A. Labrie, Inc.

BOIS, J. In Armand Eng'r Co. v. Adrien A. Labrie, Inc., 119 N.H. 408, 402 A.2d 184 (1979) (Armand I), we held…