From Casetext: Smarter Legal Research

Aetna Casualty Surety Co. v. Kemp Smith Co.

District of Columbia Court of Appeals
Apr 12, 1965
208 A.2d 737 (D.C. 1965)

Summary

In Aetna Casualty Surety Co., et al. v. Kemp Smith Co., Inc., 208 A.2d 737, D.C.Ct. of App., the court had before it a bond which contained essentially the same language as the bond involved here.

Summary of this case from Home Indemnity Co. v. Daniels Construction Co.

Opinion

No. 3579.

Argued November 23, 1964.

Decided April 12, 1965.

APPEAL FROM DISTRICT OF COLUMBIA COURT OF GENERAL SESSIONS, AUSTIN L. FICKLING, J.

Edgar A.B. Spencer, New York City, pro hac vice, by special leave of court, with whom Arthur C. Elgin and F. Granville Munson, Washington, D.C., were on the brief, for appellants.

Louis Ginberg, Washington, D.C., for appellee.

Before HOOD, Chief Judge, and QUINN and MYERS, Associate Judges.


In November 1960, appellant Spencer, White Prentis, Inc. entered into a contract, hereafter "the foundation contract," with International Land Corporation which obligated appellant to perform certain foundation work in connection with the construction of an office building. Thereafter, Spencer, White Prentis engaged W.H. Nicholson Associates, Inc. to undertake excavation work pertinent to the foundation construction, and Nicholson, in turn, on February 14, 1961, contracted with plaintiff-appellee Kemp Smith Co., Inc. for the performance of machine excavation at the job site.

On March 17, 1961, pursuant to a separate contract entered into between International Land and appellant George A. Fuller Co., Inc., under which Fuller became the general contractor on the project, the foundation contract was assigned to Fuller with the consent of Spencer, White Prentis. Subsequently, on March 27, 1961, appellant Fuller as principal and appellant Aetna Casualty Surety Co. as surety executed a Labor and Material Payment Bond for the protection of International Land.

Appellee Smith completed its work on May 5, 1961, and on May 31, notified Aetna of its claim for payment, Nicholson having in the meanwhile defaulted on its contract with Spencer, White Prentis. Smith then filed suit against Aetna, Fuller, and Spencer, White Prentis, and a trial was had which resulted in the judgment appealed from.

Judgment was entered for the plaintiff against Spencer, White Prentis, Inc. and George A. Fuller Co., Inc. for the balance owing in the amount of $3,425.46, and against Aetna Casualty Surety Co. in the amount of $1,290.46, that portion of the balance owing which accrued subsequent to the execution of the bond.

THE CLAIM AGAINST SPENCER, WHITE PRENTIS

Under Article 9 of the General Conditions attached to the foundation contract, Spencer, White Prentis, as contractor, agreed that

"Unless otherwise stipulated, the Contractor shall provide and pay for all materials, labor, water, tools, equipment, light, power, transportation and other facilities necessary for the execution and completion of the work."

On this appeal, it is argued that that promise, running from Spencer, White Prentis to International Land, will not support an action for payment by the appellee as a third party beneficiary. In support of that argument, appellant contends that except where surety contracts are involved, the District of Columbia has not adopted the third party beneficiary doctrine, and that in any event, appellee is at most an incidental beneficiary, and would, accordingly, be without enforceable rights even in those jurisdictions where the doctrine prevails.

Our research reveals no case in this jurisdiction expressly adopting or rejecting the third party beneficiary rule. However, in Marranzano v. Riggs Nat. Bank of Washington, D.C., 87 U.S.App.D.C. 195, 196, 184 F.2d 349, 350 (1950), there was a recognition that there are exceptions "to the general rule that a stranger to a contract may not sue to enforce its terms or to recover damages for a violation thereof"; and there are other cases indicating that the third party beneficiary rule would be applied in a proper case. Hall v. Gardiner, 75 U.S.App.D.C. 226, 126 F.2d 227 (1942); Schwartz v. Brown, D.C.Mun.App., 64 A.2d 298 (1949). In Guinn Company v. Mazza, 111 U.S.App.D.C. 319, 296 F.2d 441 (1961), the rule was recognized, but that case was controlled by the law of New York.

Cf. Bruckner-Mitchell v. Sun Indemnity Co. of New York, 65 App.D.C. 178, 82 F.2d 434 (1936); Sun Indemnity Company v. American University, 58 App.D.C. 184, 26 F.2d 556 (1928).

Turning to other jurisdictions we find that a large majority of the states have adopted the rule. "The great weight of authority recognizes a direct enforceable right, both at law and in equity, arising from a contract promising performance for either of the first two types of beneficiaries — the donee beneficiary and the creditor beneficiary * * *." 2 Williston, Contracts § 356 (3d ed. Jaeger 1959). Restatement, Contracts §§ 133-147 (1932) also recognizes the rule, and it has been said that the Restatement "is entitled to particular respect when authorities are in conflict * * *." Bailey v. Zlotnick, 80 U.S.App.D.C. 117, 118, 149 F.2d 505, 506 (1945). We perceive no reason why this jurisdiction should not adopt the rule followed by the majority of jurisdictions in this country.

It is said in 12 Am.Jur. Contracts § 277 (1938), that the rule exists "in a great majority of American jurisdictions," and it is referred to as the "prevailing rule" in 17A C.J.S. Contracts § 519(3) (1963).

In Nash Engineering Co. v. Marcy Realty Corporation, 222 Ind. 396, 54 N.E.2d 263 (1944), it was held that Article 9, as quoted above, afforded unnamed materialmen a remedy as third party beneficiaries against the contractor. As the Maryland court stated in a case reaching a similar result under the same provisions:

"We find the obligation assumed by the general contractor in the case before us was just what he wrote that it would be, read literally, namely, to pay for all of the materials necessary for the doing of the job." Kirby v. Board of Ed. of Cecil County, 210 Md. 383, 123 A.2d 606, 610 (1956).

Save for the fact that materials were furnished rather than labor, in both the cases cited the plaintiffs stood in precisely the same position vis a vis the contractor as the appellee here. It follows that appellee is entitled to recover for the work it performed, and the judgment against Spencer, White Prentis is, accordingly, affirmed.

Boka Electrical Construction Co. v. W.M. Chappell, Inc., 104 U.S.App.D.C. 407, 262 F.2d 718 (1958), provides additional support for our holding. We recognize that that case involved the statutory obligation contained in D.C. Code 1961 § 1-804 (Supp. IV, 1965), and that accordingly, the policy considerations involved there differ somewhat from those presented in the instant appeal. It is apparent, however, that the undertaking sued upon there is essentially identical to the one before us, and further, that the parties in both cases occupy the same relative positions.

THE CLAIM AGAINST GEORGE A. FULLER CO., INC.

Appellee seeks to support the judgment against appellant Fuller on two grounds. It argues first that when Fuller accepted the benefits of the foundation contract under the assignment, it came under a duty to perform that contract according to the conditions and terms as provided therein. Second, it argues that Fuller became liable, like Spencer, White Prentis, as general contractor under Article 9 of the General Conditions which attached to its contract of March 17, 1961, with International Land.

We find that neither theory has merit. Certainly Fuller did, under the assignment, come under a duty to perform pursuant to the terms of the foundation contract, but that duty was merely to pay Spencer, White Prentis upon the satisfactory completion of the foundation work, precisely the duty originally assumed by International Land.

It is equally clear that Fuller, by virtue of its undertaking under Article 9, could have become liable to laborers and materialmen having no contractual relationship with either Fuller or International Land. We do not think, however, that that doctrine, utilized to support the judgment against Spencer, White Prentis, can be extended to permit recovery against Fuller. When Fuller assumed the status of general contractor in March 1961, the other agreements relevant here had already been executed. Fuller, therefore, had no opportunity to exercise any control over the selection of sub- and sub-sub-contractors, nor to secure itself against the possibility of default by requiring a sub-contractor's bond. To impose liability under these circumstances would defeat the apparent intentions of the parties. The judgment, therefore, against George A. Fuller Co., Inc. must be reversed.

THE CLAIM AGAINST AETNA CASUALTY SURETY CO.

The claim against appellant Aetna is brought on the familiar Labor and Material Payment Bond issued by Aetna as surety for the protection of International Land. That claim, however, is not well founded because the bond in terms limits the class of proper claimants to those having a direct contract with the Principal, here George A. Fuller Co., Inc., or with a sub-contractor of the Principal. Appellee's contract was with Nicholson, at best a sub-sub-contractor of Fuller. It follows that recovery on the bond must be denied. See United States v. Blount Brothers Construction Co., 168 F. Supp. 407 (D.Md. 1958).

Judgment against Spencer, White Prentis, Inc. affirmed; judgments against George A. Fuller Co., Inc. and Aetna Casualty Surety Company reversed.


Summaries of

Aetna Casualty Surety Co. v. Kemp Smith Co.

District of Columbia Court of Appeals
Apr 12, 1965
208 A.2d 737 (D.C. 1965)

In Aetna Casualty Surety Co., et al. v. Kemp Smith Co., Inc., 208 A.2d 737, D.C.Ct. of App., the court had before it a bond which contained essentially the same language as the bond involved here.

Summary of this case from Home Indemnity Co. v. Daniels Construction Co.

In Kemp Smith Co., it relied on the Restatement (First) of Contracts §§ 133-147 and stated that it was adopting "the [third party beneficiary] rule followed by the majority of jurisdictions in this country."

Summary of this case from General Insurance v. Interstate
Case details for

Aetna Casualty Surety Co. v. Kemp Smith Co.

Case Details

Full title:AETNA CASUALTY SURETY CO., Spencer, White Prentis, Inc., a corporation…

Court:District of Columbia Court of Appeals

Date published: Apr 12, 1965

Citations

208 A.2d 737 (D.C. 1965)

Citing Cases

General Insurance v. Interstate

[4] Similarly, the Georgetown bond limitations provision is enforceable against Interstate under District of…

Western U. Telegraph Co. v. Massman Const. Co.

One who is not a party to a contract nonetheless may sue to enforce its provisions if the contracting parties…