ORS § 279B.030

Current through 2024 Regular Session legislation effective June 6, 2024
Section 279B.030 - Demonstration that procurement will cost less than performing service with contracting agency's own personnel and resources or that performing service is not feasible; exemptions; analysis for procurement related to information technology; rules
(1) Except as provided in ORS 279B.036, before conducting a procurement for services with an estimated contract price that exceeds $250,000, a contracting agency shall:
(a) Demonstrate, by means of a written cost analysis in accordance with ORS 279B.033, that the contracting agency would incur less cost in conducting the procurement than in performing the services with the contracting agency's own personnel and resources; or
(b) Demonstrate, in accordance with ORS 279B.036, that performing the services with the contracting agency's own personnel and resources is not feasible.
(2) If a local contracting agency authorizes a department, bureau, office or other subdivision of the local contracting agency to conduct a procurement on behalf of another department, bureau, office or subdivision of the local contracting agency, the department, bureau, office or subdivision on whose behalf the procurement is conducted shall comply with the requirement set forth in subsection (1) of this section.
(3) Subsection (1) of this section does not apply to:
(a) A local contracting agency or a local contract review board for a city that has a population of not more than 15,000 or a county that has a population of not more than 30,000;
(b) A community college that enrolls not more than 1,000 full-time equivalent students, as defined in ORS 341.005;
(c) A special district, as defined in ORS 198.010, a diking district formed under ORS chapter 551 and a soil and water conservation district organized under ORS 568.210 to 568.808;
(d) The Port of Portland; or
(e) Procurements for client services the definition and scope of which the Oregon Department of Administrative Services specifies by rule.
(4)
(a)
(A) A state contracting agency that conducts a cost analysis in accordance with ORS 279B.033 or makes a determination under ORS 279B.036 in connection with a procurement for services related to information technology, as defined in ORS 291.045, shall provide the State Chief Information Officer and the Legislative Fiscal Office with copies of the final cost analysis the state contracting agency prepared under ORS 279B.033 or the final determination the state contracting agency made under ORS 279B.036.
(B) The requirement to provide the materials described in subparagraph (A) of this paragraph to the State Chief Information Officer does not apply to the Secretary of State or the State Treasurer.
(b) The Legislative Fiscal Office may provide materials the office receives under paragraph (a) of this subsection to a committee of the Legislative Assembly or to the Emergency Board in accordance with policies the office develops.
(c) The State Chief Information Officer shall adopt rules and develop policies for incorporating materials the State Chief Information Officer receives under paragraph (a) of this subsection into the oversight functions that the State Chief Information Officer exercises under ORS 276A.206 and the planning functions that the State Chief Information Officer exercises under ORS 276A.233 and 276A.236.

ORS 279B.030

Amended by 2016 Ch. 16,§ 1, eff. 3/3/2016, op. 6/2/2016.
2009 c. 880, § 2