The notification/application, work practice, air sampling, clean-up and disposal requirements of this Section shall apply to each owner/operator of a renovation asbestos project, where the combined amount of RACM to be stripped, removed, dislodged, cut, drilled, or similarly disturbed includes at least 260 linear feet on pipes, or 160 square feet on other facility components, or 35 cubic feet off of facility components where the area or length could not be measured prior to abatement.
DANGER
ASBESTOS
CANCER AND LUNG DISEASE HAZARD
AUTHORIZED PERSONNEL ONLY
Each owner/operator engaged in a renovation asbestos project subject to this Section shall ensure that:
The disposal requirements of the Disposal Section of this regulation shall apply.
The background, daily, and clearance air monitoring requirements of the Air Sampling Section of this regulation shall apply.
S.C. Code Regs. § 61-86.1.X