S.C. Code Regs. § § 103-760

Current through Register Vol. 48, No. 11, November 22, 2024
Section 103-760 - Utility Inspections and Tests
A. Each utility shall, unless specifically excused by the commission, provide such laboratory, meter-testing equipment and other equipment and facilities as may be necessary to make the tests required of it by these rules or other orders of the commission. The apparatus and equipment so provided shall be subject to the approval of the commission, and it shall be available at all times for the inspection of any member or authorized representative of the ORS.
B. Upon request by a customer and at no charge, the utility shall make a test of the meter serving him, provided that such tests need not be made more frequently than once in 24 months.
1) The customer, or his representative, may be present when his meter is tested.
2) A report of the results of the test shall be made to the customer within a reasonable time after the completion of the test, and a record of the report, together with a complete record of each test, shall be kept on file at the office of the utility.

S.C. Code Regs. § 103-760

Amended by State Register Volume 31, Issue No. 5, eff May 25, 2007.