D.C. Mun. Regs. tit. 14, r. 14-5762

Current through Register 71, No. 45, November 7, 2024
Rule 14-5762 - MOVE-IN AND MOVE-OUT INSPECTIONS
5762.1

The Project Owner shall conduct a move- in inspection with the new tenant the same day as the Dwelling Lease is signed for occupancy. DCHA and the tenant shall sign the unit inspection form certifying the condition of the unit, and the equipment provided with the unit, at the end of the inspection.

5762.2

The Project Owner shall conduct a move-out inspection within twenty- four (24) hours of becoming aware that a tenant has vacated a unit or with the tenant on t he day the tenant is scheduled to vacate.

5762.3

Tenants shall be asked to explain the nature and cause of any damage to the premises not documented during prior unit inspections.

5762.4

The tenant and Project Owner shall sign the unit inspection form certifying the condition of the unit, equipment in the unit and assigning tenant responsibility for repair as provided in § 5760 of this chapter.

5762.5

The Project Owner shall furnish the vacated tenant with a statement of total charges for any damages within ten (10) working days after completion of the repairs.

D.C. Mun. Regs. tit. 14, r. 14-5762

Final Rulemaking published at 64 DCR 12956 (12/22/2017); amended by Final Rulemaking published at 66 DCR 6831 (6/7/2019)