Section 3137.24 - Why would BLM reject a unit agreement application?

BLM will reject a unit agreement application-

(a) That does not address all mandatory terms, including those required under § 3137.21(b) of this subpart;
(b) If the unit operator-
(1) Has an unsatisfactory record of complying with applicable laws, regulations, the terms of any lease or permit, or the requirements of any notice or order; or
(2) Is not qualified to operate within NPR-A under applicable laws and regulations;
(c) That does not conserve natural resources;
(d) That is not in the public interest;
(e) That does not comply with any special conditions in effect for any part of the NPR-A that the unit or any lease subject to the unit would affect; or
(f) That does not comply with the requirements of this subpart.