33 C.F.R. § 154.1220

Current through October 31, 2024
Section 154.1220 - Response plan submission requirements
(a) The owner or operator of an MTR facility identified in § 154.1216 as a substantial harm facility, shall prepare and submit to the cognizant COTP a response plan that complies with this subpart and all sections of subpart F of this part, as appropriate, except §§ 154.1015 , 154.1016 , 154.1017 , 154.1028 , 154.1045 and 154.1047 .
(b) The owner or operator of an MTR facility classified by the COTP under § 154.1216(b) as a significant and substantial harm facility, shall prepare and submit for review and approval of the cognizant COTP a response plan that complies with this subpart and all sections of subpart F of this part, as appropriate, except §§ 154.1015 , 154.1016 , 154.1017 , 154.1028 , 154.1045 and 154.1047 .
(c) In addition to the requirements in paragraph (a) of this section, the response plan for a mobile MTR facility must meet the requirements of § 154.1041 subpart F.

33 C.F.R. §154.1220

USCG-1999-5149, 65 FR 40825 , June 30, 2000