30 C.F.R. § 250.204

Current through November 30, 2024
Section 250.204 - Requirements for high pressure high temperature (HPHT) barrier equipment

If you plan to install HPHT barrier equipment, you must submit information with your applicable Project Conceptual Plan, New or Unusual Technology Barrier Equipment Conceptual Plan, DWOP, and applicable permit(s) that demonstrates the equipment is fit for service in the applicable HPHT environment. You must follow the applicable DWOP Process requirements (e.g.,§§ 250.229 and 250.242).

30 C.F.R. §250.204

89 FR 71112 , 10/29/2024