Opinion
CASE NO.: 3:11-cv-00251-RCJ-WGC
01-10-2013
SUBMITTED BY: HOLLAND & HART, LLP J. Robert Smith, Esq Attorneys for Defendant Ruby Pipeline, LLC Approved as to Form: STORY LAW GROUP Robert Story, NV Bar No. 1268 Attorneys for Plaintiff
J. Robert Smith, Esq. NV Bar No. 10992
jrsmith@hollandhart.com
HOLLAND & HART LLP
5441 Kietzke Lane, Second Floor
Reno, NV 89511
Telephone: (775) 327-3000
Facsimile : (775) 786-6179
Attorneys for Defendant Ruby Pipeline, LLC
JUDGMENT AND DECLARATION
THIS MATTER having been tried without a jury on September 18-19, 2012 on Plaintiff Alice M. Gladwill's claims, and the Court having found in favor of the Defendant and against Plaintiff on all of Plaintiff's claims, and having issued and filed the Court's Findings of Fact and Conclusions of Law;
IT IS HEREBY ORDERED, ADJUDGED AND DECREED that Judgment be entered in favor of the Defendant Ruby Pipeline, LLC and against Plaintiff Alice M. Gladwill.
IT IS FURTHER ORDERED that Plaintiff's request for an injunction is DENIED.
IT IS FURTHER ORDERED that Defendant has a continuing obligation to maintain and repair the Right-of-Way easement that traverses Plaintiff's property pursuant to standards promulgated by the Federal Energy Regulatory Commission.
______________
JUDGE ROBERT C. JONES
United States District Judge
SUBMITTED BY:
HOLLAND & HART, LLP
______________
J. Robert Smith, Esq
Attorneys for Defendant Ruby Pipeline, LLC
Approved as to Form:
STORY LAW GROUP Robert Story, NV Bar No. 1268
Attorneys for Plaintiff