From Casetext: Smarter Legal Research

Whitmyer Bros. v. State of New York

Court of Appeals of the State of New York
Jul 3, 1979
47 N.Y.2d 960 (N.Y. 1979)

Summary

awarding damages measured by quantum meruit for a construction delay claim

Summary of this case from Bricklayers Ins. & Welfare Fund v. Minhas Gen. Contractors Co.

Opinion

Argued May 31, 1979

Decided July 3, 1979

Appeal from the Appellate Division of the Supreme Court in the Third Judicial Department, SIDNEY SQUIRE, J.

Robert Abrams, Attorney-General (Richard J. Dorsey, Shirley Adelson Siegel and Jeremiah Jochnowitz of counsel), for appellant. Sayward Mazur and Julius L. Schapira for respondent.


MEMORANDUM.

The order of the Appellate Division should be affirmed, with costs.

A dispute arose between D. Lambert Railing Co. (Lambert), the subcontractor responsible for the guide rail work of the project to improve the condition of the Cross Westchester Parkway, and the State's engineer-in-chief with respect to how the preparatory work required to order the necessary materials was to be conducted and the nature of the guide rail work itself. After completion of this work, claimant, the general contractor, instituted this action pursuant to an agreement with Lambert on the latter's behalf alleging that the State had breached the contract.

As to the issue of liability, the Court of Claims found that the State had interfered in the performance of the guide rail work, thereby causing severe disruption in Lambert's work schedule and resulting in increased costs. These findings, affirmed by the Appellate Division and having support in the record, are beyond our review. (CPLR 5501, subd [b]; e.g., Matter of Rothko, 43 N.Y.2d 305, 318.)

In addition, on the record before us, we agree with the measure of damages as calculated by the Appellate Division. Claimant, seeking the reasonable value of the work actually performed by its subcontractor Lambert, was entitled to recover damages measured on a quantum meruit basis: to wit, actual job cost plus allowance for Lambert's overhead and profit minus the amounts thus far paid for the work performed by Lambert. (See D'Angelo v State of New York, 41 A.D.2d 77, 80, after remand for new trial 46 A.D.2d 983, affd 39 N.Y.2d 781.) We would note that the State had its opportunity before the Court of Claims to submit proof of factual matters which might go to reduce the amount of damages.

Chief Judge COOKE and Judges JASEN, GABRIELLI, JONES, WACHTLER, FUCHSBERG and MEYER concur in memorandum.

Order affirmed.


Summaries of

Whitmyer Bros. v. State of New York

Court of Appeals of the State of New York
Jul 3, 1979
47 N.Y.2d 960 (N.Y. 1979)

awarding damages measured by quantum meruit for a construction delay claim

Summary of this case from Bricklayers Ins. & Welfare Fund v. Minhas Gen. Contractors Co.

In Whitmyer Bros. v. State of New York (___ N.Y. 2d ___ [July 3, 1979]) the Court of Appeals approved this court's measure of damages based upon actual job cost plus overhead and profit minus amounts paid for the work performed.

Summary of this case from Fehlhaber Corp. v. State
Case details for

Whitmyer Bros. v. State of New York

Case Details

Full title:WHITMYER BROS., INC., Respondent, v. STATE OF NEW YORK, Appellant. (Claim…

Court:Court of Appeals of the State of New York

Date published: Jul 3, 1979

Citations

47 N.Y.2d 960 (N.Y. 1979)
419 N.Y.S.2d 954
393 N.E.2d 1027

Citing Cases

Port Chester Electrical Construction Corp. v. HBE Corp.

The New York courts have uniformly condemned such a method of ascertaining damages as speculative and…

Manshul v. Dormitory Auth

Labor inefficiency. As to the first of these items, labor inefficiency, $354,445, the trial court said that…