ORDER


Plaintiff brings this action under the Miller Act, 40 U.S.C. § 3131 et seq. ("Miller Act"), seeking payment for construction materials it provided for a construction project at Fort Benning, Georgia. Presently pending before the Court are Defendant The Guarantee Company of North America's Motion to Dismiss or, in the alternative, Motion for a More Definite Statement (Doc. 19) and Plaintiff's Motion for Leave to File a Second Amended Complaint (Doc. 39). For the following reasons, the Court grants Plaintiff's motion for leave to file an amended complaint. Since The Guarantee Company of North America is not named as a Defendant in Plaintiff's proposed amended complaint, its presently pending motion to dismiss is now moot.

The Federal Rules of Civil Procedure provide that "[a] party may amend its pleading once as a matter of course within . . . 21 days after service of a responsive pleading[.]" Fed.R.Civ.P. 15(a)(1)(B). After that time has expired, "a party may amend its pleading only with the opposing party's written consent or the court's leave." Fed.R.Civ.P. 15(a)(2). A "court should freely give leave when justice so requires." Id. "[T]rial courts have broad discretion in permitting or refusing to grant leave to amend." Garfield v. NDC Health Corp., 466 F.3d 1255, 1270 (11th Cir. 2006).

Plaintiff filed its Complaint on August 4, 2009. Plaintiff filed an Amended Complaint on August 13, 2009 before being served with a responsive pleading. Plaintiff is not allowed to amend its Complaint again as a matter of course. Plaintiff therefore seeks leave to file a second amended complaint to "clarify the correct parties to this lawsuit." (Pl.'s Mot. for Leave to File 2d Am. Compl. 2.) The Court observes that no scheduling order has been entered and that no Defendant has objected to Plaintiff's motion. Therefore, the Court finds that Plaintiff should be permitted to amend its Complaint a second time. Accordingly, Plaintiff's Motion for Leave to File a Second Amended Complaint is hereby granted.

The Court further observes that Plaintiff's proposed Second Amended Complaint omits the following Defendants: (1) Turner Insurance and Bonding Company, Inc.; (2) Richard F. Ferrucci Associates, LLC; (3) Phoenix/McBride, a Joint Venture, consisting of Phoenix Construction Solutions, LLC, and McBride Construction Company, Inc.; and (4) The Guarantee Company of North America, USA. (Ex. A to Pl.'s Mot. for Leave to File 2d Am. Compl., 2d Am. Compl. Against Payment Bond and for Damages.) Therefore, Plaintiff's claims against Richard F. Ferrucci Associates, LLC, Phoenix/McBride, and The Guarantee Company of North America, USA are dismissed.

Turner Insurance and Bonding Company, Inc. was dismissed from this action with prej udice pursuant to a February 9, 2010 stipulation.

CONCLUSION

For the foregoing reasons, Plaintiff's Motion for Leave to File a Second Amended Complaint (Doc. 39) is granted. That ruling makes Defendant The Guarantee Company of North America's Motion to Dismiss or, in the alternative, Motion for a More Definite Statement (Doc. 19) moot.

IT IS SO ORDERED.


Summaries of

U.S. v. Phoenix Construction Solutions, LLC

United States District Court, M.D. Georgia, Columbus Division
Mar 31, 2010
CASE NO. 4:09-CV-90 (CDL) (M.D. Ga. Mar. 31, 2010)
Case details for

U.S. v. Phoenix Construction Solutions, LLC

Case Details

Full title:UNITED STATES OF AMERICA, for the use and benefit of Cemex Construction…

Court:United States District Court, M.D. Georgia, Columbus Division

Date published: Mar 31, 2010

Citations

CASE NO. 4:09-CV-90 (CDL) (M.D. Ga. Mar. 31, 2010)